| 1 | For 13 KL ( Item no. 01 To 09)Supply & installation of Vertical Cryogenic tanks 13 KL for LOX (Vacuum insulated with foundation bolts designed as per enclosed specifications )a) Supply of 13 KL Cryogenic Tank for LOXb) Civil Foundations of Size 3.5x3.5 Sq meter for 13 KL LOX tank with required depth to carry load in full load capacityc) Unloading,handling & installation charges of cranes for Tank & Vapouriserd) MAWP - 17 to 23 Bar |
| 2 | Supply & installation of Vertical Atmoshperic Vapouriser for LOX designed as per ASME codes. Capacity - 500 Nm3/hr with Civil foundation works 2.5x2.5 sq. meter |
| 3 | Supply, Installation, Testing of PR skids within tank battery limit a) Two PRV with flow capacity 500 Nm3/hr, Inlet- 40 kg/cm2, Outlet- 8 kg/cm2b) Ball Valve, 3 piece, Size- 1\", Working Pressure - 40 kg/cm2, quantity- 3 Nosc) SRV - Peso approved for Oxygen Service- 1 Nosd) Line pressure Guage with ball valve - 1 Nose) NRV - 2 Nosf) Line purge valve- 1 Nosg) SS 304 flange, Size- 1 1/2\", Class- 300 - 2 Setsh) SS 304 Seamless pipe, sch40 - 12 mtri) SS 316 Unions with teflon sheets - 6 Nosj) MS Support Structure |
| 4 | Supply, erection & testing of Copper piping from tank battery limit to buildinga) Copper Line with socket, elbow & tee, Size- 42 mm, Qty- 100 Mtrb) Line ball valve - 3 Nosc) MS Support Structure |
| 5 | Peso Approval for 3 years |
| 6 | Erection & Installation of fire fighting equipments |
| 7 | Statutory requirement as per PESO guidelines to be installed at site |
| 8 | Crane Handling Charges for loading Unloading and Installation (As per Reqirement) |
| 9 | Additional Civil Work as perRequirementif Necessary (As per Requirement) |
| 10 | For 10 KL ( Item no. 10 To 18)Supply & installation of Vertical Cryogenic tanks 10 KL for LOX (Vacuum insulated with foundation bolts designed as per enclosed specifications )e) Supply of 10 KL Cryogenic Tank for LOXf) Civil Foundations of Size 3.5x3.5 Sq meter for 10 KL LOX tank with required depth to carry load in full load capacityg) Unloading,handling & installation charges of cranes for Tank & Vapouriserh) MAWP - 17 to 23 Bar |
| 11 | Supply & installation of Vertical Atmoshperic Vapouriser for LOX designed as per ASME codes. Capacity - 500 Nm3/hr with Civil foundation works 2.5x2.5 sq. meter |
| 12 | Supply, Installation, Testing of PR skids within tank battery limit k) Two PRV with flow capacity 500 Nm3/hr, Inlet- 40 kg/cm2, Outlet- 8 kg/cm2l) Ball Valve, 3 piece, Size- 1\", Working Pressure - 40 kg/cm2, quantity- 3 Nosm) SRV - Peso approved for Oxygen Service- 1 Nosn) Line pressure Guage with ball valve - 1 Noso) NRV - 2 Nosp) Line purge valve- 1 Nosq) SS 304 flange, Size- 1 1/2\", Class- 300 - 2 Setsr) SS 304 Seamless pipe, sch40 - 12 mtrs) SS 316 Unions with teflon sheets - 6 Nost) MS Support Structure |
| 13 | Supply, erection & testing of Copper piping from tank battery limit to buildingd) Copper Line with socket, elbow & tee, Size- 42 mm, Qty- 100 Mtre) Line ball valve - 3 Nosf) MS Support Structure |
| 14 | Peso Approval for 3 years |
| 15 | Erection & Installation of fire fighting equipments |
| 16 | Statutory requirement as per PESO guidelines to be installed at site |
| 17 | Crane Handling Charges for loading Unloading and Installation (As per Reqirement) |
| 18 | Additional Civil Work as perRequirementif Necessary (As per Requirement) |
| 19 | For 20 KL ( Item no. 19 To 27)Supply & installation of Vertical Cryogenic tanks 20 KL for LOX (Vacuum insulated with foundation bolts designed as per enclosed specifications )a) Supply of 20 KL Cryogenic Tank for LOXb) b) Civil Foundations of Size 3.5x3.5 Sq meter for 20 KL LOX tank with required depth to carry load in full load capacityc) c) Unloading,handling & installation charges of cranes for Tank & Vapouriserd) MAWP - 17 to 23 Bar |
| 20 | Supply & installation of Vertical Atmoshperic Vapouriser for LOX designed as per ASME codes. Capacity - 500 Nm3/hr with Civil foundation works 2.5x2.5 sq. meter |
| 21 | Supply, Installation, Testing of PR skids within tank battery limita) Two PRV with flow capacity 500 Nm3/hr, Inlet- 40 kg/cm2, Outlet- 8 kg/cm2b)Ball Valve, 3 piece, Size- 1\", Working Pressure - 40 kg/cm2, quantity- 3 Nosc)SRV - Peso approved for Oxygen Service- 1 Nosd)Line pressure Guage with ball valve - 1 Nose)NRV - 2 Nosf) Line purge valve- 1 Nosg) SS 304 flange, Size- 1 1/2\", Class- 300 - 2 Setsh) SS 304 Seamless pipe, sch40 - 12 mtri) SS 316 Unions with teflon sheets - 6 Nosj) MS Support Structure |
| 22 | Supply, erection & testing of Copper piping from tank battery limit to buildinga) Copper Line with socket, elbow & tee, Size- 42 mm, Qty- 200 Mtrb) Copper Line with socket, elbow & tee, Size- 25 mm, Qty- 50 Mtrc) Line ball valve - 3 Nosd) MS Support Structure |
| 23 | Peso Approval for 3 years |
| 24 | Erection & Installation of fire fighting equipments |
| 25 | Statutory requirement as per PESO guidelines to be installed at site |
| 26 | Crane Handling Charges for loading Unloading and Installation (As per Reqirement) |
| 27 | Additional Civil Work as perRequirementif Necessary (As per Requirement) |