| 1 | 1 | Annual Maintenance Contract of Field Instruments of U#7, U#8/ DPPS including U#7 & U#8 PWPS, Intake Raw Water System, FAHS, Fire Detection & Protection System, DPPS | | | |
|---|
| 2 | 1.01 | Mandatory Part Annual Maintenance Contract of Field Instruments of U#7, U#8/ DPPS including U#7 & U#8 PWPS, Intake Raw Water System, FAHS, Fire Detection & Protection System, DPPS | Mandatory Part | 12 | Months |
|---|
| 3 | 2 | Optional Job: B | | | |
|---|
| 4 | 2.01 | Cable Laying upto 7-Core x1.5/2.5mm2 | 1 | 900 | Mtr |
|---|
| 5 | 2.02 | Cable Jointing upto 7-Core x1.5/2.5mm2 | 2 | 80 | Nos |
|---|
| 6 | 2.03 | Cable termination upto 7-Core x1.5/2.5mm2 | 3 | 90 | Nos |
|---|
| 7 | 2.04 | Cable Laying upto 8~19-Core x1.5/2.5mm2 | 4 | 900 | Mtr |
|---|
| 8 | 2.05 | Cable Jointing upto 8~19-Core x1.5/2.5mm2 | 5 | 90 | Nos |
|---|
| 9 | 2.06 | Cable termination upto 8~19-Core x1.5/2.5mm2 | 6 | 90 | Nos |
|---|
| 10 | 2.07 | Cable Laying above 19-Core x1.5/2.5mm2 | 7 | 200 | Mtr |
|---|
| 11 | 2.08 | Cable Jointing above 19-Core x1.5/2.5mm2 | 8 | 40 | Nos |
|---|
| 12 | 2.09 | Cable termination above 19-Core x1.5/2.5mm2 | 9 | 40 | Nos |
|---|
| 13 | 2.1 | Laying of MI cable | 10 | 500 | Mtr |
|---|
| 14 | 2.11 | Laying of compensating cable upto 4-Pair | 11 | 800 | Mtr |
|---|
| 15 | 2.12 | Laying of compensating cable 4~ 10-Pair | 12 | 700 | Mtr |
|---|
| 16 | 2.13 | Laying of compensating cable above 10-Pair | 13 | 700 | Mtr |
|---|
| 17 | 2.14 | Optical Fibre laying | 14 | 1700 | Mtr |
|---|
| 18 | 2.15 | Optical Fibre Jointing | 15 | 30 | Nos |
|---|
| 19 | 2.16 | Optical Fibre Checking by OTDR | 16 | 10 | Nos |
|---|
| 20 | 2.17 | Laying of UTP cable | 17 | 900 | Mtr |
|---|
| 21 | 2.18 | Termination of UTP cable | 18 | 15 | Nos |
|---|
| 22 | 2.19 | Crimping of co-axial cable | 19 | 10 | Nos |
|---|
| 23 | 2.2 | CS Impulse Pipe 14~21mm laying, painting with support | 20 | 50 | Mtr |
|---|
| 24 | 2.21 | AS Impulse Pipe 14~21mm laying, painting with support | 21 | 50 | Mtr |
|---|
| 25 | 2.22 | AS IBR Impulse Pipe 14~21mm laying, painting with support | 22 | 50 | Mtr |
|---|
| 26 | 2.23 | Low pressure argon welding | 23 | 50 | Per joint |
|---|
| 27 | 2.24 | IBR argon welding | 24 | 50 | Per Joint |
|---|
| 28 | 2.25 | Replacement of 10~25NB low pressure valve | 25 | 20 | Per valve |
|---|
| 29 | 2.26 | Replacement of 10~25NB IBR valve | 26 | 20 | Per valve |
|---|
| 30 | 2.27 | Replacement of IBR condensate pot | 27 | 20 | Per pot |
|---|
| 31 | 2.28 | Structure work including fabrication & scrap cutting, painting | 28 | 8 | Per MT |
|---|
| 32 | 2.29 | Installation of Junction Box upto 10-Way | 29 | 12 | Per Piece |
|---|
| 33 | 2.3 | Installation of Junction Box from 12 to 24 Way | 30 | 12 | Per Piece |
|---|
| 34 | 2.31 | Servicing of Control Valve upto Size 50 diaphragm | 31 | 10 | Nos |
|---|
| 35 | 2.32 | Refitting / Replacement of Control Valve upto Size-46 diaphragm | 32 | 10 | Nos |
|---|
| 36 | 2.33 | Servicing of Control Valve Size-47~60 diaphragm | 33 | 10 | Nos |
|---|
| 37 | 2.34 | Refitting / Replacement of Control Valve Size-47~60 diaphragm | 34 | 10 | Nos |
|---|
| 38 | 2.35 | Servicing of Control Valve Size-61~76 diaphragm | 35 | 10 | Nos |
|---|
| 39 | 2.36 | Refitting/Replacement of Control Valve Size-61~76 diaphragm | 36 | 3 | Nos |
|---|
| 40 | 2.37 | Servicing of Control Valve Size-60~65 diaphragm at DM Plant | 37 | 3 | Nos |
|---|
| 41 | 2.38 | Replacement of Control Valve Size-60~65 diaphragm at DM Plant | 38 | 3 | Nos |
|---|
| 42 | 2.39 | Servicing of double acting control valve | 39 | 10 | Nos |
|---|
| 43 | 2.4 | Refitting/Replacement of double acting control valve | 40 | 3 | Nos |
|---|
| 44 | 2.41 | Servicing of rotary actuator of bore 2”~4” | 41 | 70 | Nos |
|---|
| 45 | 2.42 | Refitting/Replacement of rotary actuator of bore 2”~4” | 42 | 65 | Nos |
|---|
| 46 | 2.43 | Servicing of rotary actuator of bore 4.1”~10” | 43 | 20 | Nos |
|---|
| 47 | 2.44 | Replacement of rotary actuator of bore 4.1”~10” | 44 | 8 | Nos |
|---|
| 48 | 2.45 | Servicing of power cylinder of bore below 4” | 45 | 40 | Nos |
|---|
| 49 | 2.46 | Replacement of power cylinder of bore below 4” | 46 | 18 | Nos |
|---|
| 50 | 2.47 | Servicing of power cylinder of bore 4”~10” | 47 | 45 | Nos |
|---|
| 51 | 2.48 | Replacement of power cylinder of bore 4”~10” | 48 | 45 | Nos |
|---|
| 52 | 2.49 | Servicing of power cylinder of bore above 10” | 49 | 18 | Nos |
|---|
| 53 | 2.5 | Replacement of power cylinder of bore above 10” | 50 | 18 | Nos |
|---|
| 54 | 2.51 | Servicing of electrical actuator | 51 | 8 | Nos |
|---|
| 55 | 2.52 | Replacement of electrical actuator | 52 | 2 | Nos |
|---|
| 56 | 2.53 | Adjustment/calibration of positioner | 53 | 35 | Nos |
|---|
| 57 | 2.54 | Adjustment/calibration of position feedback unit | 54 | 35 | Nos |
|---|
| 58 | 2.55 | Laying of 12~16mm SS tube with support | 55 | 15 | Per Mtr |
|---|
| 59 | 2.56 | Laying of 28mm SS tube with support | 56 | 15 | Per Mtr |
|---|
| 60 | 2.57 | Loop checking | 57 | 150 | Per No |
|---|
| 61 | 2.58 | Covering instrument by transparent polythene cover | 58 | 90 | Per No |
|---|
| 62 | 2.59 | FTU replacement at DCS | 59 | 5 | Per No |
|---|
| 63 | 2.6 | Fan/Filter cleaning at DCS/PLC/LVS | 60 | 25 | Per No |
|---|
| 64 | 2.61 | Igniter rod chokage cleaning | 61 | 10 | Per No |
|---|
| 65 | 2.62 | Unit Mill Area Instrument cleaning | 62 | 6 | Per area |
|---|
| 66 | 2.63 | Unit Coal Feeder Area cleaning | 63 | 6 | Per area |
|---|
| 67 | 2.64 | Unit Boiler Front Area (0~12M) cleaning | 64 | 4 | Per area |
|---|
| 68 | 2.65 | Unit Boiler Front Area (15~32M) cleaning | 65 | 4 | Per area |
|---|
| 69 | 2.66 | Unit Boiler Front Area (35~60M) cleaning | 66 | 4 | Per area |
|---|
| 70 | 2.67 | Unit DCS Room Panel (Control Room, Engineering Work Station, Equipment Room) cleaning | 67 | 25 | Per area |
|---|
| 71 | 2.68 | Unit PA/ID/FD/CST area Instrument cleaning | 68 | 2 | Per area |
|---|
| 72 | 2.69 | CPU (Control Room, Mixed Bed, Regeneration, Neutralising) Instrument cleaning | 69 | 2 | Per area |
|---|
| 73 | 2.7 | Unit SWAS cleaning | 70 | 2 | Per area |
|---|