| 1 | 1 | Excavation of eath in ordinary soil with lift up to 1.5 m&lead up to 50m filling, watering and ramming of excavated earth into frnches or into the space between the building and sides of foundation frenches or into the plinth and disposal of surplus erth up to a distance of 50m from the center of the foundalion frinches. | | 14.58 | Cum |
|---|
| 2 | 2 | Concrete with 40 mm gauge First class brick ballast, locl sand and cement in prortion of 8:4:1 in foundation and plinth including supply of all materials, labour, T&P etc, required for proper completion of the work. | item2 | 2.43 | Cum |
|---|
| 3 | 3 | 25 mm thick damp proof course with cement, coarse sand and stone girt (1:1.5:3) including 5% water proofing materials componund including supply of all materials labour T&P etc, required for proper completion of the work. | item3 | 3.6 | Sqm |
|---|
| 4 | 4 | Ist class brick work in 1:4 coarse sand cement in foundation , plinth including supply of all materials, labour, T&P etc. required for proper completion of the work. | item4 | 3.56 | Cum |
|---|
| 5 | 5 | Ist class brick work in 1:6 cement and coarse sand mortar in super structure including supply of all materials, labour, T&P etc. required for proper completion of work. | item5 | 10.8 | Cum |
|---|
| 6 | 6 | R.C.C work with cement approved coarse sand and 20 mm gauge approved stone ballast in the proportion 1:1.5:3 in lintels of doors, windows & sunshades excluding reinforcement and uts bending but including its fixing and binding the 24 BWG wire as per specification ob P.W.D Schedule T&P etc required for proper completion of work.\n\nBeam | item7 | 1.4 | Cum |
|---|
| 7 | 6.1 | Slab | item8 | 4.76 | Cum |
|---|
| 8 | 7 | Mild steel or plain work such as reinforced comcert or reinforced brick work wrought to required shape as necessary including building for for proper completion of work and including supply of steel its wastage band hooks and authorized over lapping shall be measured floor tow level. | item13 | 4.29 | Qtl |
|---|
| 9 | 8 | Supply and fixing of M.S angle 40*40*6 mm door chaukhat including supply and fixing hinged as per direction of Engineer-in-charge(A) 1.20*2.10m*1.00*2.10m | item14 | 1 | Qtl |
|---|
| 10 | 9 | Supply and fixing of Z-section M.S window as per departmental drawing including supply and fitting of handle locking arrangement etc complete. | item15 | 1 | Qtl |
|---|
| 11 | 10 | Provide 40mm thick plaster 1:2 in cement and coarse sand over Rcc roof/floor including claaning and washing the dust or any other foreign matter including supply of all materials labour T&P etc required for proper complection of work. | item16 | 36 | Sqm |
|---|
| 12 | 11 | 12mm thick plaster with cement mortor in proportion of 1:3 cement coarse sand over bricks works minimum thickness not be less than 10 mm including supply of all materials, labour T&P etc, required for proper completion of work. | item17 | 105.44 | Sqm |
|---|
| 13 | 12 | Supply and fixing of approved quality plywood Door shutter of required size of 32 mm thick waterproof including all labour T&P etc, complete but eluding painting and including all labour T&P etc, complete but eluding painting and including heavy size steel fitting e.g tower bolt sliding bold handle etc, completes as per direction . | item18 | 9.92 | Sqm |
|---|
| 14 | 13 | Painting or varnishing two coats over one coat of primer over new iron or wood work including supply of all materials labour T&P etc, required. | item19 | 79.36 | Sqm |
|---|
| 15 | 14 | Finishing of wall with three coat of approved weather proof /apex exterior paont of reputed co. (eg. Asian, berger, nerolac) to give a smoth & even colour / shade incoluding supply of all materials, labour T&P atc xcomplete. | item20 | 141.43 | Sqm |
|---|
| 16 | 15 | Electricfication work | item21 | 1 | Job |
|---|
| 17 | 16 | Water supply, Sanitary work and disposal work of pollute water | item24 | 1 | Job |
|---|
| 18 | 17 | ALL RATE INCLUDED WITH GST | item46 | | |
|---|