| 1 | 1 | SUPPLY & ERECTION OF GI TUBULER POLE SP-80 PERPENDECULER TO GROUND LEVEL INCLUDING THE EXCAVATION OF EARTH PIT HAVING DEPTH OF 1/6 OF\nLENGTH OF POLE AND CROSS SECTION 0.65Mtr. X0.65Mtr. WITH GROUTING IN PROPORTION OF 1:2:4 CC FOUNDATION (2.6Mtr. x50cm x50cm) INCLUDING TAMPING ,RAMPING , VIBRATING CURING ,SHUTTING , REFILING ETC.HAVING PCC BASE FOUNDATION OF SIZE (15CM X 60CM X 60CM) EDGE BRICK SOILING INCLUDING PLASTERING ABOVE GROUND LEVEL PORTION (2FT) COMPLETE WITH ALL LABOUR AND TOOLS AS PER DIRECTION OF EIC REFILLING. | | 6 | NO |
|---|
| 2 | 2 | Supply, fitting & fixing of GI Channel Cross Arm (100x50x6x3200mm) in pole with proper clamp and nuts & bolts with washer. | | 16 | NO |
|---|
| 3 | 3 | Supply, fitting & fixing of 33KV Porcelain/Polymer Pin Insulator. | | 12 | NO |
|---|
| 4 | 4 | Supply, fitting & fixing of 33KV Composite Porcelain/Polymer Disc Insulator 70KN with proper hardware fittings. | | 12 | NO |
|---|
| 5 | 5 | SUPPLY & INSTALLTION OF HARDWARE OF 33KV DISC\nINSULATOR(POLYMER/PORCELAIN) ALONG WITH TRANSPORTAION, HANDING AND\nLABOUR CHARGE | | 12 | NO |
|---|
| 6 | 6 | SUPPLY & INSTALLTION OF TENSION CLAMP OF 33KV DISC INSULATOR(POLYMER) ALONG WITH TRANSPORTAION, HANDING AND LABOUR CHARGE | | 12 | NO |
|---|
| 7 | 7 | SUPPLY & FITTING & FIXING OF TOP CLEAT(1000X50X6X350mm) FOR 33KV ALONG\nWITH TRANSPORTAION, HANDING AND LABOUR CHARGE | | 2 | NO |
|---|
| 8 | 8 | SUPPLY INSTALLATION AND COMMISSIONING OF TURN BUCKLE FOR HT GURDING ALONG WITH TRANSPORTAION, HANDING AND LABOUR CHARGE | | 14 | NO |
|---|
| 9 | 9 | SUPPLY INSTALLATION AND COMMISSIONING OF GI WIRE 6 SWG ALONG WITH TRANSPORTAION, HANDING AND LABOUR CHARGE | | 250 | KG |
|---|
| 10 | 10 | SUPPLY INSTALLATION AND COMMISSIONING OF GI WIRE 8 SWG ALONG WITH TRANSPORTAION, HANDING AND LABOUR CHARGE | | 130 | KG |
|---|
| 11 | 11 | Supply, Fitting & fixing of 50 x 50 x 6mm GI Angle with proper fixtures required for Pole Bracing. | | 216 | Mtr |
|---|
| 12 | 12 | Supply, fitting & fixing of HT Stay Set complete with HT Guy Insulator, 7/10SWG Stay wire and cement concrete grouting of CC ratio 1:3:6. | | 8 | NO |
|---|
| 13 | 13 | SUPPLY & INSTALLTION OF GI STAY WIRE 7/10 SWG ALONG WITH TRANSPORTAION, HANDING AND LABOUR CHARGE | | 200 | KG |
|---|
| 14 | 14 | Supply & Erection of GI Earth Pipe of 1.8Mtr. long with inner dia 100mm ,outer dia 110mm 50x 6mm GI Strip, Charcoal, Salt, Nickel nuts & bolts, etc. for earthing of Pole. | | 5 | NO |
|---|
| 15 | 15 | SUPPLY & INSTALLTION OF GI STRIP 50X6 FOR STRUCTURE EARTHING ALONG WITH TRANSPORTAION, HANDING AND LABOUR CHARGE | | 70 | Mtr |
|---|
| 16 | 16 | SUPPLY & STRINGING OF 33KV XLPE INSULATED ABC 3CX185SQ.MM +1C X240SQ.MM WITH PG CLAMP, TENTION CLAMP ETC. ALONG WITH TRANSPORTAION, HANDING AND LABOUR CHARGE | | 110 | Mtr |
|---|
| 17 | 17 | SUPPLY & INSTALLTION OF PG CLAMP FOR AAAC RACOON ALONG WITH\nTRANSPORTAION, HANDING AND LABOUR CHARGE | | 12 | NO |
|---|
| 18 | 18 | GI NUT BOLTS AND THROUGH BOLT ASSORTED ALONG WITH TRANSPORTAION, HANDING AND LABOUR CHARGE | | 25 | KG |
|---|
| 19 | 19 | SUPPLY & INSTALLTION OF SUNDRY MATERIALS (SALT, CHARCOAL & GLAND ETC) ALONG WITH TRANSPORTAION, HANDING AND LABOUR CHARGE | | 1 | LS |
|---|