North Eastern Electric Power Corporation Limited-NEEPCO has published Up Gradation Of Fire Fighting System Supply , Overhauling , Rectification And Modification Work Of Deluge Valve , Automation Of Water Reservoir , Up Gradation Of Fire Hydrant Network And Equipment Of Dikrong Power House , Ranganadi He Plant , Neepco. Submission Date for this Tender is 20-01-2021. Fire Fighting Consumable Tenders in Dikrong Power House, Hoz, Papumpare, Ar. Pradesh Arunachal Pradesh. Bidders can get complete Tender details and download the document.
Sr No | CorrigendumDate | Corrignedum | CorrigendumType | NewSubmissionDate |
1 | 05-Jan-2021 | Corrigendum No. 01 dtd. 05.01.2021 | Date | 20-01-2021 |
Name of Work: Supply, Overhauling, Rectification & Modification Work of Deluge Valve, Automation of Water Reservoir, Up gradation of Fire Hydrant Network & Equipments of Dikrong Power House, Ranganadi H.E. Plant, Dist Lower Subansiri, Arunachal Pradesh | |||||
---|---|---|---|---|---|
Sl. No. | Item Description | Item Code / Make HSN No. | Quantity | Units | |
1 | 1 | SUPPLY PART | |||
2 | 1.1 | Deluge valve rectification and modification work | |||
3 | 1.11 | Supply the Defective deluge trim fittings for individual deluge valve as well as supply the trim fittings for up gradation of the deluge system. (See the supply specification) | 20 | Set | |
4 | 1.12 | Supply of Electrical & manually operated Butterfly valve (100 mm dia).(See the supply specification) | 18 | Set | |
5 | 1.13 | Supply of Electrical & manually operated Butterfly valve (80 mm dia). (See the supply specification) | 2 | Set | |
6 | 1.14 | Supply of Complete Deluge valve Trim fittings. (See the supply specification) | 5 | Set | |
7 | 1.15 | Supply of outdoor type Pressure Switch withisolation valve with all fittings acceries. (See the supply specification) | 60 | Set | |
8 | 1.16 | Supply of outdoor type Pressure gauge with valve with all fittings acceries. (See the supply specification) | 40 | Set | |
9 | 1.17 | Supply of primer & paint for two coat painting of Sprinkler and detection pipe line. (See the supply specification) | 1 | lot | |
10 | 1.18 | Supply of diffective Quartzoid bulb. (tentive qty) (See the supply specification Page 5 of ). | 40 | Pcs | |
11 | 1.19 | Supply of defective or missing Spray nozzle. (See the supply specification Page 6 of ). | 40 | Pcs | |
12 | 1.2 | Supply of PLC (Including HMI display) control panel to control & monitor all 20 nos Deluge valve with spare of two nos. As well as dispalying and control two nos reservior water label. | 1 | Pcs | |
13 | 1.21 | Supply of PLC control with HMI display to control all 20 nos active deluge valve 2 nos spare Deluge valve. | 1 | Pcs | |
14 | 1.22 | Supply of Power and signal cable between deluge valve & DV control panel. Between MCC panel to DV control panel. | 1 | lot | |
15 | 1.23 | Supply of Junction and control BOX near Deluge valve. | 20 | lot | |
16 | 1.24 | Supply of MS PIPE 80NB (HEAVY GRADE) use for bypass network. | 18 | Mtr | |
17 | 1.25 | Supply of MS PIPE 100NB (HEAVY GRADE) use for bypass network. | 300 | Mtr | |
18 | 1.26 | Supply of the small part gate valve use in deluge network (40 nos valve) | 1 | lot | |
19 | 1.27 | Supply strainer in sprinkler header network with isolation Butterfly valve. | 2 | nos | |
20 | 1.28 | Reservior automation project. | |||
21 | 1.29 | Supply of Label transmitter switch with controller for reservoir automation.\n\n | 2 | nos | |
22 | 1.3 | Supply of 7 x 1.5 sqmm armoured copper cable from reservoir filling pump room to reservoir. | 2000 | Mtr | |
23 | 1.31 | Supply of Interconnection of label control panel to MCC panel & DV control panel. | 200 | Mtr | |
24 | 1.32 | Supply of electrical component for existing MCC panel up gradation for reservoir filling automation. | 1 | lot | |
25 | 1.33 | Fire Hydrant network and equipment upgradation | |||
26 | 1.34 | Supply of defective part of existing of hose reel drum. | 10 | nos | |
27 | 1.35 | FRP hose box supply for outdoor area. | 10 | nos | |
28 | 1.36 | Supply of deffective part of existing Hydrant valve. | 1 | lot | |
29 | 1.37 | Supply all diffective part of isolation isolation valve to repairing & maintains. | 1 | lot | |
30 | 1.38 | Supply of primer & PO red paints outdoor yard sprinkler & hydrant pipe network only surrounding plant area. \n \n\n\n\n\n | 1 | lot | |
31 | 2 | SERVICE PART | |||
32 | 2.1 | Deluge valve rectification and modification works | |||
33 | 2.11 | Deleuge valve with all deluge trim equipment overhauling work with small diffective part supply. | 20 | Set | |
34 | 2.12 | Electrical & manually operated Butterfly valve newlly installed at new bypass valve. (100 mm dia) | 18 | Set | |
35 | 2.13 | Electrical & manually operated Butterfly valve newlly installed at new bypass valve. (80 mm dia) | 2 | Set | |
36 | 2.14 | Deleuge valve Trim fittings supply and installation. | 5 | Set | |
37 | 2.15 | Pressure Switch with valve & fittings supply and installation. | 60 | Set | |
38 | 2.16 | Pressure gauge with valve supply and installation. | 40 | Set | |
39 | 2.17 | Sprinkler and detection pipe line rectification with painting work with supply of paint pipe and fittings. | 20 | lot | |
40 | 2.18 | Supply and installed of diffective Quartzoid bulb. (tentive qty) | 40 | Pcs | |
41 | 2.19 | Supply and installed of Spray nozzle. | 40 | Pcs | |
42 | 2.2 | Deluge valve control & monitoring panel for 20 nos active deluge valve 2 nos spare Deluge valve. Reservior label indication & Panel for bypass control 20 nos active deluge valve 2 nos spare Deluge valve. Reservior label indication. | 1 | Pcs | |
43 | 2.21 | Panel for bypass control 20 nos active deluge valve 2 nos spare Deluge valve. Reservior label indication. | 1 | Pcs | |
44 | 2.22 | Power and signal cable between deluge valve & DV control panel. Between MCC panel to DV control panel. | 1 | lot | |
45 | 2.23 | Junction and control BOX near Deluge valve | 20 | lot | |
46 | 2.24 | MS PIPE 80NB (HEAVY GRADE) use for bypass network. | 18 | Mtr | |
47 | 2.25 | MS PIPE 100NB (HEAVY GRADE) use for bypass network. | 300 | Mtr | |
48 | 2.26 | Overhauling the all gate in deluge network (40 nos valve) | 1 | lot | |
49 | 2.27 | Use strainer network with isolation Butterfly valve. | 2 | nos | |
50 | 2.28 | Reservior automation project | |||
51 | 2.29 | Lebel transmitter switch with controller for reservior automation. | 2 | nos | |
52 | 2.3 | 7 x 1.5 mm2 armoued copper cable from reservior filling pump room to reservior. | 2000 | Mtr | |
53 | 2.31 | Interconnection of lebel control panel to MCC panel & DV control panel. | 200 | Mtr | |
54 | 2.32 | MCC panel upgradation for reservior filling automation. | 1 | lot | |
55 | 2.33 | Fire Hydrant network and equipment upgradation. | |||
56 | 2.34 | Rectifiaction & repairing of hose reel drum. | 10 | nos | |
57 | 2.35 | FRP hose box supply for outdoor area. | 10 | nos | |
58 | 2.36 | Hydrant valve repairing & rectification | 1 | lot | |
59 | 2.37 | All isolation valve repairing & maintance. | 1 | lot | |
60 | 2.38 | All out door area pipe painting. | 1 | lot |