Outsourcing Of Services For Operation And Maintenance Of Ac Plants At Auditorium Exposition Hall Mems Ehsv Clean Room 0011 0202 0203 0501 0601 And 0901A Under Ge I Rnd Rci , Hyderabad, GE(I) R AND D RCI, HYDERABAD-Telangana

Military Engineer Services-MES has published Outsourcing Of Services For Operation And Maintenance Of Ac Plants At Auditorium Exposition Hall Mems Ehsv Clean Room 0011 0202 0203 0501 0601 And 0901A Under Ge I Rnd Rci , Hyderabad. Submission Date for this Tender is 31-12-2020. HVAC Tenders in GE(I) R AND D RCI, HYDERABAD Telangana. Bidders can get complete Tender details and download the document.




Tender Notice

26173563
Corrigendum : Outsourcing Of Services For Operation And Maintenance Of Ac Plants At Auditorium Exposition Hall Mems Ehsv Clean Room 0011 0202 0203 0501 0601 And 0901A Under Ge I Rnd Rci , Hyderabad
Open Tender
Indian
Telangana
GE(I) R AND D RCI, HYDERABAD
31-12-2020

Tender Details

Outsourcing Of Services For Operation And Maintenance Of Ac Plants At Auditorium Exposition Hall Mems Ehsv Clean Room 0011 0202 0203 0501 0601 And 0901A Under Ge I Rnd Rci , Hyderabad

Corrigendum Details

Sr No CorrigendumDate Corrignedum CorrigendumType NewSubmissionDate
1 24-Dec-2020 Bid Auto Extn Corrigendum Bid Auto Extn Corrigendum 31-12-2020

Key Value

Document Fees
INR 500 /-
EMD
INR 98000.0 /-
Tender Value
Refer document

BOQ Items

Name of Work: OUTSOURCING OF SERVICES FOR OPERATION AND MAINTENANCE OF AC PLANTS AT AUDITORIUM, EXPOSITION HALL, MEMS, EHSV CLEAN ROOM, 0011, 0202, 0203, 0501, 0601 AND 0901A UNDER GE(I) R&D RCI, HYDERABAD
Sl No. Item Description Item Code / Make Quantity Units
1 1 Outsourcing of services for operation of central AC plant 2 x 40TR capacity water cooled system at Auditorium Plant comprising of Air Cooled/Water cooled chilled water plants i.e. chiller package consisting of compressors, condensers, cooling towers, AHUs, fan coil units, chilled water pipe lines and pumps, condenser water pipe lines and pumps, refrigerant piping, expansion valves, filters, suction and discharge valves, gauges, controls including all starters, electrical panel, cable from panel to individual machine, routine checks like: checking of oil level, tension in 'V' belts, leak testing, greasing to motors, replacement of ‘O’ rings, gaskets, bolts, nuts & washers, gland packing to pump etc., but excluding repairs to the plants by providing One Senior Refrigeration Mechanic per shift of 08 hours for One shift in a day on all days except Sundays and Holidays complete all as specified and directed.\nNote: Repairs and supply only of refrigerant gas will be measured and paid separately. 9 Per Month
2 2 All as per item No 01 above but 2 x 75TR capacity Air Cooled Chiller Package AC plants at Exposition Hall by providing One Refrigeration Mechanic per shift of 08 hours for One shift in a day on all days except Sundays and Holidays. 9 Per Month
3 3 All as per item No 01 above but 2 x 95TR capacity Air Cooled Chiller Plant at MEMS Technology centre by providing One Refrigeration Mechanic per shift of 08 hours for Two shifts in a day on all days except Sundays and Holidays. 9 Per Month
4 4 All as per item No 01 above but of 3 x 75TR capacity Air Cooled Screw Chiller twin circuit with hot water dehumidification and BMS system for class 10,000 Clean Room at EHSV facility by providing One Refrigeration Mechanic per shift of 08 hours for Two shifts in a day on all days except Sundays and Holidays. 9 Per Month
5 5 Outsourcing of services for operation of central AC plant 3 x 50TR capacity water cooled system at 0202 Building comprising of Air Cooled/Water cooled chilled water plants i.e. chiller package consisting of compressors, condensers, cooling towers, AHUs, fan coil units, chilled water pipe lines and pumps, condenser water pipe lines and pumps, refrigerant piping, expansion valves, filters, suction and discharge valves, gauges, controls including all starters, electrical panel, cable from panel to individual machine, routine checks like: checking of oil level, tension in 'V' belts, leak testing, greasing to motors, replacement of ‘O’ rings, gaskets, bolts, nuts & washers, gland packing to pump etc., but excluding repairs to the plants by providing One Refrigeration Mechanic per shift of 08 hours for One shift in a day on all days except Sundays and Holidays complete all as specified and directed.\nNote: Repairs and supply only of refrigerant gas will be measured and paid separately. 9 Per Month
6 6 All as per item 5 above but 2 x 45 TR capacity Air Cooled Chilled Water System at 0501 Building by providing One Refrigeration Mechanic per shift of 8 hours per day for One shift in a day on all days except Sundays and Holidays. 9 Per Month
7 7 All as per item 5 above but 3 x 11TR capacity Air Cooled Chiller Package System, 3 x 9.2TR Air Cooled Chilled Water AC plants, 3 x 25TR Water Cooled Direct Expansion DX type AC plants at 0011 Building by providing One Refrigeration Mechanic per shift of 8 hours per day for Two shifts in a day on all days except Sundays and Holidays. 9 Per Month
8 8 All as per item 5 above but 2 x 34TR capacity Air Cooled Chilled Water System at 0203 Building by providing One Refrigeration Mechanic per shift of 8 hours per day for One shift in a day on all days except Sundays and Holidays. 9 Per Month
9 9 All as per item 5 above but 2 x 45TR capacity Air Cooled Chilled Water System at 0901A Building by providing One Refrigeration Mechanic per shift of 8 hours per day for One shift in a day on all days except Sundays and Holidays. 9 Per Month
10 10 All as per item 5 above but 2 x 11TR capacity Air Cooled Chiller Package System at 0601 Building by providing One Refrigeration Mechanic per shift of 8 hours per day for Three shifts in a day on all days including Sundays and Holidays. 9 Per Month
11 11 All as per item No 1 above but for each additional hour duration over and above the shift of 8 hours for each Operator for item 1 to 10. 150 Per Hour
12 12 Outsourcing of services for assisting in maintaining of AC plants mentioned at Sl No 1 to 10 above including cleaning of rooms and surrounding area, clearing of grass, cutting of vegetation etc., by providing Two Unskilled labours per shift of 08 hours (General shift) for One shift in a day on all day except Sundays and Holidays all as specified and directed. 9 Per Month
13 12.01 Notes for the serial item No 01 to 12:\nServices required under outsourcing are such that One Senior Refrigeration Mechanic shall be made available for the entire plants as and when maintenance works are executed and the unit rates quoted shall be deemed to include for this provision.
14 12.02 Contractor shall maintain daily log sheet duly signed by the users at each AC Plant Room all as directed by the Engineer in Charge.
15 12.03 The cleaning of filters, cooling tower etc., is responsibility of the contractor and deemed to be included in the unit rates quoted.
16 12.04 All T&P required for operating, repair and maintenance are deemed to be included in the unit rates quoted.
17 12.05 All stationary for Duty Roster, Attendance register, Wages register, Log sheet book, maintenance record etc., shall be arranged, maintained and submitted by the contractor to Engineer in charge in the first week of every month.
18 12.06 Any loss due to negligence, faulty operation shall be made good by the contractor without any extra cost to the department.
19 12.07 Wage period shall not exceed one month. Wages for all workers employed shall be paid before 7th day of every month through bank account without fail irrespective of whether RAR is claimed or not.
20 12.08 Minimum wages, EPF, ESI, Bonus etc., to the workers shall be paid by the contractor as per regional Labour/PF Commissioner, Gazette Notification including DA all as authorized.
21 12.09 Labour elements for fixing of spares/parts mentioned in this Schedule/BOQ as 'Supply only' shall be deemed to include in the unit rate quoted.
22 12.1 The workers employed by the contractor for outsourcing shall be entitled for one day weekly off and the contractor has to provide suitable substitute in the concerned shifts. The unit rate quoted shall be deemed to include for this provision.
23 12.11 Quoted rate against items 1 to 12 above shall be deemed to be inclusive of cost of taking down the old items being replaced, necessary cleaning, fixing, making connections, testing, commissioning etc., in respect of BOQ items indicated here in after as 'Supply only'.
24 12.12 Unskilled labour shall be responsible for cleaning of AHU Filters, inlet Diffusers, Micro Filters of Diffusers, return air ducts of Clean Room facility of EHSV & MEMS AC plant.
25 12.13 Un skilled labour shall also assist the mechanics for routine maintenance and break down of AC Plants at Sl No 1 to 10.
26 13 Leak testing of complete gas circulating system of Water Cooled Chilled System AC plants of 40/45 TR Capacity compressor with dry nitrogen after evacuating of the existing gas from the system into empty cylinder by separating the entire system like compressors, condensers, cooling coils and flushing out complete system, vaccumising for a period of 24 hours and recharging the refrigerant gas including replacement of unserviceable of copper filter, capillary tube, ‘U’ foam etc., with new ones, cutting brazing, leak detection and rectification etc., complete all as directed.\nNote: Nitrogen shall be arranged by the contractor 1 Each Job
27 14 All as per item No 13 above but for Air Cooled chiller AC Plant of capacity 34TR 1 Each Job
28 15 All as per item No 13 above but for Air Cooled chiller AC Plant of capacity 75TR 1 Each Job
29 16 All as per item No 13 above but for Air Cooled chiller AC Plant of capacity 95TR 1 Each Job
30 17 All as per item No 13 above but for Air Cooled chiller AC Plant of capacity 50TR 1 Each Job
31 18 All as per item No 13 above but for Air Cooled Package system of capacity 9.2/11/15TR \nNote for item No 13 to 18: Nitrogen required shall be arranged by the contractor. Plant Operator employed under Sl item No 1 to 12 above will also assist the technician for carrying out the job. 1 Each Job
32 19 Descaling of condenser of 25TR capacity by circulating descaling agent (HCL) through condensers by forced feed method, removing the end covers of the condensers, cleaning each tube of condenser thoroughly by brushing, re-fixing the end covers with new rubber gasket, bolts, nuts & washers and testing complete all as specified and directed. 3 Each Job
33 20 All as per item No 19 above but condensor of capacity 40/50TR 3 Each Job
34 21 All as per item No 19 above but Air cooled condensor of capacity 34TR including cleaning externally with special chemical to remove the unwanted dust particles to bring down the high pressure. 2 Each Job
35 22 All as per item No 19 above but Air cooled condensor of capacity 9.2/11TR including cleaning externally with special chemical to remove the unwanted dust particles to bring down the high pressure. 2 Each Job
36 23 All as per item No 19 above but Air cooled condensor of capacity 45TR including cleaning externally with special chemical to remove the unwanted dust particles to bring down the high pressure.\nNote for item No 19 to 23: Plant Operator employed under Sl item No 1 to 12 above will also assist the team for carrying out the job. 2 Each Job
37 24 Supply only Refrigerant gas R-22 61 KG
38 25 Supply only Refrigerant gas R-407C 61 KG
39 26 Supply only 'V" belts of size A-40 complete all as specified. 5 Each
40 27 Supply only 'V" belts of size A-42 complete all as specified. 4 Each
41 28 Supply only 'V" belts of size B-92 complete all as specified. 6 Each
42 29 Supply only 'V" belts of size B-98 complete all as specified.\nMake for item No 26 to 29: Dunlop/Fenner/PIX/ Continental 8 Each
Disclaimer :
We takes all possible care for accurate & authentic tender information, however Users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender.
Tell us about your Product / Services,
We will Find Tenders for you

Copyright © 2024 · All Rights Reserved. Terms of Usage | Privacy Policy

For Tender Information Services Visit : TenderDetail