Supply , Installation , Testing And Commissioning Of Gas-Based Fire Suppression System Supply , Installation , Testing And Commissioning Of Gas-Based Fire Suppression System In Nerldc , Shillong, NERLDC, POWERGRID COMPLEX, LAPALANG, SHILLONG-Meghalaya

Power System Operation Corporation Limited-POSOCO has published Supply , Installation , Testing And Commissioning Of Gas-Based Fire Suppression System Supply , Installation , Testing And Commissioning Of Gas-Based Fire Suppression System In Nerldc , Shillong. Submission Date for this Tender is 30-10-2020. Fire Suppression System Tenders in NERLDC, POWERGRID COMPLEX, LAPALANG, SHILLONG Meghalaya. Bidders can get complete Tender details and download the document.




Tender Notice

25677285
Supply , Installation , Testing And Commissioning Of Gas-Based Fire Suppression System Supply , Installation , Testing And Commissioning Of Gas-Based Fire Suppression System In Nerldc , Shillong
Open Tender
Indian
Meghalaya
NERLDC, POWERGRID COMPLEX, LAPALANG, SHILLONG
30-10-2020

Tender Details

Supply , Installation , Testing And Commissioning Of Gas-Based Fire Suppression System Supply , Installation , Testing And Commissioning Of Gas-Based Fire Suppression System In Nerldc , Shillong

Key Value

Document Fees
Refer document
EMD
INR 136000.0 /-
Tender Value
Refer document

BOQ Items

Name of Work: Supply, Installation, testing and commissioning of Gas-based Fire Suppression System in NERLDC, Shillong
Sl. No. Item Description Item Code / Make Quantity Units
1 1 Server Room 1 (1st Floor): Length: 5.49 m, Width: 3.66 m, Height: 2.74 m
2 1.01 SEAMLESS STEEL CONTAINERS - EMPTY - Vertical Mount - Capacity 80 Ltrs. cylinder shall be provided with a safety rupture disc. An increase in internal pressure due to high temperature shall rupture the safety disc and allows the content to vent before the rupture pressure of the container reaches. The contents shall not be vented through the discharge piping and nozzles. item1 1 No
3 1.02 NOVEC 1230 item2 60 Kg
4 1.03 Electric Control Head, Stack, 24VDC item3 1 No
5 1.04 Manual Actuator item4 1 No
6 1.05 65NB Discharge Hose (Flexible Hose Ø1.25"x30" Single Braid) item5 1 No
7 1.06 Cylinder Strap, And Bottom Support 35mm wide, 4mm thick item6 2 Nos
8 1.07 Nozzle 360 Deg item7 3 Nos
9 1.08 Warning Sign & Instruction Board as per specification item8 1 No
10 1.09 Supply, erection, testing, jointing and commissioning of Heavy class MS pipes. Pipe specials such as bends, tees, reducers etc. shall confirm to ASTM A 234 Gr WPB forged. The pipe shall be with flanged joints / weld joints. Rate quoted shall include for necessary pair of flanges gaskets, nuts, bolts & painting etc, for pipes being suspended from ceilings beam bottom, clamped on to the walls, drop to the false ceiling level etc., complete. item9 1 Per Cylinder System
11 1.1 4 ZONE CONVENTIONAL fire Alarm panel with Gas Release module and battery backup. item10 1 No
12 1.11 Conventional Photoelectric smoke Detector item11 6 Nos
13 1.12 Manual Call Point item12 1 No
14 1.13 Response indicator item13 4 Nos
15 1.14 Hooter Cum Strobe item14 1 No
16 1.15 2-core, 1.5 sq. mm. Shielded armoured cable item15 100 Mtrs.
17 1.16 Release Switch item16 1 No
18 1.17 Abort Switch item17 1 No
19 1.18 Installation Charges item18 1 Job
20 1.19 Freight and Insurance item19 1 Lumpsum
21 2 Server Room 2 (3rd Floor): Length: 13.41 m, Width: 8.08 m, Height: 6.10 m
22 2.01 SEAMLESS STEEL CONTAINERS - EMPTY - Vertical Mount - Capacity 140 Ltrs. cylinder shall be provided with a safety rupture disc.\nAn increase in internal pressure due to high temperature shall rupture the safety disc and allows the content to vent before the rupture pressure of the container reaches. The contents shall not be vented through the discharge piping and nozzles. item20 4 Nos
23 2.02 NOVEC 1230 item21 480 Kg
24 2.03 Electric Control Head, Stack, 24VDC item22 1 No
25 2.04 Manual Actuator item23 1 No
26 2.05 65NB Discharge Hose (Flexible Hose Ø1.25"x30" Single Braid) item24 1 No
27 2.06 Slave cylinder\n(with total 03 nos. Pneumatic Valve & 03 nos. Discharge Hose) item25 3 Nos
28 2.07 Return Air valve\n(with total 04 nos. Check Valves) item26 4 Nos
29 2.08 Cylinder Strap, Header using SCD 40 pipe and Bottom Support 35mm wide, 4mm thick item27 1 No
30 2.09 Pressure switch item28 1 No
31 2.1 Nozzle 360 Deg item29 6 Nos
32 2.11 Warning Sign & Instruction Board as per specification item30 1 No
33 2.12 Supply, erection, testing, jointing and commissioning of Heavy class MS pipes. Pipe specials such as bends, tees, reducers etc. shall confirm to ASTM A 234 Gr WPB forged. The pipe shall be with flanged joints / weld joints. Rate quoted shall include for necessary pair of flanges gaskets, nuts, bolts & painting etc, for pipes being suspended from ceilings beam bottom, clamped on to the walls, drop to the false ceiling level etc., complete. item31 1 Per Cylinder System
34 2.13 4 ZONE CONVENTIONAL fire Alarm panel with Gas Release module and battery backup. item32 1 No
35 2.14 Conventional Photoelectric smoke Detector item33 9 Nos
36 2.15 Manual Call Point item34 1 No
37 2.16 Response indicator item35 4 Nos
38 2.17 Hooter Cum Strobe item36 1 No
39 2.18 2-core, 1.5 sq. mm. Shielded armoured cable item37 200 Mtrs.
40 2.19 Release Switch item38 1 No
41 2.2 Abort Switch item39 1 No
42 2.21 Installation Charges item40 1 Job
43 2.22 Freight and Insurance item41 1 Lumpsum
44 3 Auxiliary Supply System Room - Length: 13.16 m, Width: 7.98 m, Height: 6.37 m
45 3.01 SEAMLESS STEEL CONTAINERS - EMPTY - Vertical Mount - Capacity 140 Ltrs. cylinder shall be provided with a safety rupture disc. An increase in internal pressure due to high temperature shall repture the safety disc and allows the content to vent before the rupture pressure of the container reaches. The contents shall not be vented through the discharge piping and nozzles. item42 4 Nos
46 3.02 NOVEC 1230 item43 490 Kg
47 3.03 Electric Control Head, Stack, 24VDC item44 1 No
48 3.04 Manual Actuator item45 1 No
49 3.05 65NB Discharge Hose (Flexible Hose Ø1.25"x30" Single Braid) item46 1 No
50 3.06 Slave cylinder\n(with total 03 nos. Pneumatic Valve & 03 nos. Discharge Hose) item47 3 Nos
51 3.07 Return Air valve\n(with total 04 nos. Check Valves) item48 4 Nos
52 3.08 Cylinder Strap, Header using SCD 40 pipe and Bottom Support 35mm wide, 4mm thick item49 1 No
53 3.09 Pressure switch item50 1 No
54 3.1 Nozzle 360 Deg item51 6 Nos
55 3.11 Warning Sign & Instruction Board as per specification item52 1 No
56 3.12 Supply, erection, testing, jointing and commissioning of Heavy class MS pipes. Pipe specials such as bends, tees, reducers etc. shall confirm to ASTM A 234 Gr WPB forged. The pipe shall be with flanged joints / weld joints. Rate quoted shall include for necessary pair of flanges gaskets, nuts, bolts & painting etc, for pipes being suspended from ceilings beam bottom, clamped on to the walls, drop to the false ceiling level etc., complete. item53 1 Per Cylinder System
57 3.13 4 ZONE CONVENTIONAL fire Alarm panel with Gas Release module and battery backup. item54 1 No
58 3.14 Conventional Photoelectric smoke Detector item55 9 Nos
59 3.15 Manual Call Point item56 1 No
60 3.16 Response indicator item57 4 Nos
61 3.17 Hooter Cum Strobe item58 1 No
62 3.18 2-core, 1.5 sq. mm. Shielded armoured cable item59 200 Mtrs.
63 3.19 Release Switch item60 1 No
64 3.2 Abort Switch item61 1 No
65 3.21 Installation Charges item62 1 Job
66 3.22 Freight and Insurance item63 1 Lumpsum
67 4 AMC of entire system
68 4.01 Comprehensive AMC for the entire commissioned system after expiry of 1 year warranty period item64 3 Years
Disclaimer :
We takes all possible care for accurate & authentic tender information, however Users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender.
Tell us about your Product / Services,
We will Find Tenders for you

Copyright © 2024 · All Rights Reserved. Terms of Usage | Privacy Policy

For Tender Information Services Visit : TenderDetail