| 1 | 1.1 | Construction of multi-storeyed RCC buildings upto Six storey and one basement, guard room including structural designing, planning & design of services by incorporating stipulated specifications for E&M, Civil and horticulture works, all complete as per scope of work & direction of Engineer-in-charge and handover the same in good condition.\na)Basements for parking and other services along with foundation (of any type as per soil strata) complete work in all respect as per scope of work (quantity to be measured as Plinth Area as per CPWD PAR, 2019).\nb) E & M services i.e. internal electrical installation, firefighting and sprinkler system, LAN wiring, electrical vehicle charging system, mechanical ventilation, intelligent addressable fire alarm and PA system etc. in basement and parking space. | | 2690 | Sqm |
|---|
| 2 | 1.2 | a) Super Structure complete in all respect as per scope of work Upto Six Storeys Building including exterior façade with dry cladding granite , ACP cladding, structural glazing as per design and high-pressure laminate panels upto all heights of approved colour and design in proportions as per Front, Back, Left and Right elevations and grit wash to side to terrace staircase lift wall and mumty . \n(quantity to be measured as Plinth Area as per CPWD PAR, 2019).\nb) E & M services i.e. internal electrical installation, firefighting and sprinkler system, LAN wiring, intelligent addressable fire alarm and PA system etc. up to 6 storey building. | | 5270 | Sqm |
|---|
| 3 | 2 | Development of whole premises, infrastructure facilities of the project required as per scope of work and drawings attached complete as per direction of Engineer-in-charge, which includes:\na. Roads, paths, water-supply system including terrace tank, sewerage system, solid waste management system, open parking space, drainage system & rainwater harvesting system including recharge wells/ pits and water supply system for horticulture works etc. and E & M services i.e. compound lighting, boom barrier and boosting water supply system etc.\nNote: Work of STP & sump shall be measured & paid separately. | | 4495 | Sqm |
|---|
| 4 | 3 | Construction of 2.10 metre high boundary wall with 0.90 metre high wall with granite cladding & 1.20 meter high SS grill railing and required no. of steel gates and wicket gates etc. all complete. | | 285 | M |
|---|
| 5 | 4 | Supplying, installation, testing and commissioning of STP of any modern technology including Civil Works, electrical & tertiary treatment etc. for the building/ office campus, plant size is 25000 LPD and also including the cost of operation & maintenance of STP for two years from date of completion. | | 1 | Per job |
|---|
| 6 | 5 | Construction of RCC underground sump including water proofing covering tile work inside complete of 125 KL capacity. | | 1 | Per job |
|---|
| 7 | 6 | ELECTRICAL E & M\nSITC of diesel engine DG set of 380 KVA capacity complete with acoustic enclosure developing 415 volts, 3 phase 4 wire 50 Hz at 0.8 power factor (lagging) A.C. supply comprising alternator directly coupled with water cooled electric start diesel engine of suitable BHP at 1500 R.P.M mounted on common M.S. channel iron base frame complete with in-built fuel tank charged battery, battery leads, control panel, residential silencer and anti-vibration amounting pads protection connection, inter connection, including AMF Panel with suitable amps. rating, four pole AC duty contractor i/c making suitable size c.c. foundation etc. as per specifications attached. | | 1 | Per job |
|---|
| 8 | 7 | SITC & putting into operation13 passengers capacity lifts (884 Kg) with machine room i/c all accessories and control equipment for a total rise of 22.5 mtr (approx.) (one way) with 7 landings/openings, speed 1.5 m/s as per the detail specification enclosed i/c providing I section / C section (as per scope of work attached). | | 2 | Each |
|---|
| 9 | 8 | SITC of substation 2 x 800 KVA consisting of HT panel (having arrangement of suitable rating of VCB, PT etc), dry type transformer11 KV/0.415 KV, 3 phase, 50 Hz Dyne 11 copper wound, on load tape changing arrangement (OLTC) on H.V. side, main electric supply MV panel, essential supply panel having suitable rating incoming/outgoing ACB/MCCB indicating instruments, HT cables, bus trunking /bus ducting, LT panel, bus coupler and earthing etc complete as required (as per scope of work attached). | | 1 | Per job |
|---|
| 10 | 9 | SITC of modular type VRV/VRF air cool air conditioning system having cooling and heating (both) arrangements with all hermetically shield inverter type scroll compressors, minimum two compressor for above 14 HP modules, microprocessor based controller, top discharge type condensing unit, with R 410 A refrigerant, vibrant isolators with suitable foundation complete as required.\nNOTE:- This VRV/VRF AC system consists of outdoor units, indoor units, refrigerant piping, cable tray, electrical MV panels with suitable incoming/outgoing MCCBs, PVC/XLPE copper armoured cable, PVC/XLPE aluminum armoured cable, inline fan for fresh/exhaust air with centrifugal blower and motor, volume control damper, GSS ducting, drain piping and control cable etc as required (as per scope of work attached). | | 338 | HP |
|---|
| 11 | 10 | SITC of CCTV surveillance system consisting of IP-Vandal Dome camera, IP-Vandal bullet camera, PoE switch, LAN switch, HD LED display panel of suitable size with speaker, hard disk drive, steel conduit, UTP 4 pair CAT 6 cable, MS equipment rack etc as required (as per scope of work attached). | | 1 | Per job |
|---|
| 12 | 11 | SITC of EPBAX system IP based communication server having the features i.e. analog extension 250 nos. (tentative), digital extension, 20 nos. PRI card-1 no., 12 port analog trucks, Linux operating system, CSTA application control, remote maintenance, rack mount, multiparty conferencing, inbuilt 30 minutes backup with SMF batteries, analog CLI phones- 250 nos. (approx.) etc as required (as per scope of work attached). | | 1 | Per job |
|---|
| 13 | 12.1 | Providing operation & maintenance services for two years of all E/M assets created out of the agreement after completion of project, subsuming the defect liability period of two years after completion of original work as enshrined in respective clause of GCC, including deployment maintenance staff of required trade as per CPWD maintenance manual, complete job in all respects.(As per Part-18)\na) First year (from 1st day to 365th day after completion of the project. | | 1 | Per job |
|---|
| 14 | 12.2 | b) Second Year (from 366th day to 730th day after completion of project | | 1 | Per job |
|---|
| 15 | 13 | Completion of Horticulture work complete in all respect as per the scope of work | | 1 | Per job |
|---|