Tamil Nadu Generation And Distribution Corporation Limited-TANGEDCO has published Works Contract In Respect Of West/Attur Sub- Division. Submission Date for this Tender is 06-07-2020. Miscellaneous Fasteners Tenders in Attur Tamil Nadu. Bidders can get complete Tender details and download the document.
Name of Work: - Works Contract in respect of West/Attur Sub- Division | |||||
---|---|---|---|---|---|
Sl. No. | Item Description | Item Code / Make | Quantity | Units | |
1 | 1 | Transporting of poles/Materials/Conductors | |||
2 | 2 | Below 8 Kms | 100 | Per Tonne | |
3 | 3 | Above 8 Kms for additional Km | 120 | Per Tonne | |
4 | 4 | Transporting of poles from road side to pole pit for 30 " and above including RSJ Pole | 250 | Per Pole | |
5 | 5 | Loading/Unloading of Poles | |||
6 | 6 | Loading of Poles upto 27" | 250 | Per Pole | |
7 | 7 | Loading of Poles upto 30"/RSJ Pole | 120 | Per Pole | |
8 | 8 | Unloading of Poles upto 27" | 250 | Per Pole | |
9 | 9 | Unloading of Poles upto 30"/RSJ Pole | 120 | Per Pole | |
10 | 10 | Excavation of Pole/Stay pits | |||
11 | 11 | Excavation of pole pit up to 27”(8.0m) pole | 250 | Each Pit | |
12 | 12 | Stay bit 4.5” to 5” depth | 250 | Each Pit | |
13 | 13 | Excavation of pole pit up to 9.14 Mtr pole | 100 | Each Pit | |
14 | 14 | Excavation of RSJ Pole pit above 36" | 20 | Each Pit | |
15 | 15 | Hard rock with out blasting | 30 | Each Pit | |
16 | 16 | Hard Rock Requires Blasting | 30 | Each Pit | |
17 | 17 | Medium rock and Dense Medium rock requires blasting | 25 | Each Pit | |
18 | 18 | Erection of Poles | |||
19 | 19 | RCC poles/Metal pole up to 8.00m (27’) | 250 | Each Pole | |
20 | 20 | RCC poles/Metal pole up to 9.14.m(30’) | 100 | Each Pole | |
21 | 21 | RSJ Rail fabricated poles above 30" (9.14 mtr) | 10 | Each Pole | |
22 | 22 | RSJ Rail fabricated poles above 36" | 10 | Each Pole | |
23 | 23 | Erection of stay set complete | 250 | Each Stay | |
24 | 24 | Concreting of Poles | |||
25 | 25 | Mass concreting including materials ( Cement 1/2 bag + river sand and blue metals and watering) | 20 | Per Pole | |
26 | 26 | Sleeve concreting | 10 | Per Pole | |
27 | 27 | Fixing of line materials | |||
28 | 28 | HT V Cross arms / Channel Cross arms / Guarding Cross arm 4 1/2 | 150 | Each | |
29 | 29 | LT 3 Phase cross arm | 400 | Each | |
30 | 30 | LT single Phase cross arm | 350 | Each | |
31 | 31 | HT / LT TI Fitting | 100 | Each | |
32 | 32 | Fixing of HT Pin Insulators (11/22/33KV) | 630 | Each | |
33 | 33 | Fixing of HT 11KV strain disc | 270 | Each | |
34 | 34 | Fixing of LT Pin Insulators | 400 | Each | |
35 | 35 | Fixing of LT Shackle | 600 | Each | |
36 | 36 | Fixing of Aluminium knob | 550 | Each | |
37 | 37 | Earthing of Pole with Pin Including burying looping and binding | 150 | Each | |
38 | 38 | Paving and Stringing of conductor | |||
39 | 39 | Paving of conductor ,Stringing , binding , Jumpering etc..7/4.09mm ACSR | 500 | Per Wire Per Span | |
40 | 40 | 7/3.35mm ACSR 7/3.15mmAAAC | 500 | Per Wire Per Span | |
41 | 41 | 7/2.59mm ACSR & 7/2.11mm ACSR | 600 | Per Wire Per Span | |
42 | 42 | Guarding Arrangements | |||
43 | 43 | LT Split neutral guarding | 120 | Per Span | |
44 | 44 | HT Guarding | 30 | Per Span | |
45 | 45 | Structure Erection | |||
46 | 46 | Structure poles ,fixing of top channel seating ,wiring earthing , fixing of open type fuse units, HT/LT/LAS and jumpering 3 Nos, earth pits with tubes including painting of metal parts, structure poles, fixing of top channel seating channel, belting angle (except erection of transformer ) | 10 | Per Str | |
47 | 47 | DP Erection | |||
48 | 48 | Erection of D.P structure with AB switch top channel , cross bracing ,Earthing, Painting, providing stay and pole concreting | 6 | Per Str | |
49 | 49 | Erection of Transformer | |||
50 | 50 | Loading and unloading of Transformer upto 200 KVA | 10 | Each | |
51 | 51 | Loading and unloading of Transformer above 200 KVA | 10 | Each | |
52 | 52 | Erection of New Transformer upto 200 KVA | 10 | Each | |
53 | 53 | Replacement of failed Transformers upto 200 KVA | 10 | Each | |
54 | 54 | Loading & Erection of HT Metering Set | 10 | Each | |
55 | 55 | Conversion of Pin Point to Cut Point | |||
56 | 56 | (A) L.T | |||
57 | 57 | Removing the Pin | 250 | Each | |
58 | 58 | Fixing the shackle | 500 | Each | |
59 | 59 | Re-Sagging (LT) | 1330 | Per Wire Per Span | |
60 | 60 | (B) H.T | |||
61 | 61 | Removing the Pin | 250 | Each | |
62 | 62 | Fixing the Strain Disc | 250 | Each | |
63 | 63 | Service Connections | |||
64 | 64 | Erection of street light including fixture fitting | 50 | Each | |
65 | 65 | Erection of Street light service | 100 | Each | |
66 | 66 | Fixing of new SV/MV lamp fittings | 50 | Each | |
67 | 67 | Releasing of grills from RCC Poles | 500 | Each | |
68 | 68 | Agriculture service fixing/Service | 30 | Each | |
69 | 69 | Releasing of Single Phase service wire and refixing | 50 | Each | |
70 | 70 | Releasing of Three Phase service wire and refixing | 45 | Each | |
71 | 71 | Labour Charges for Alteration of Clamps to suit for the works | |||
72 | 72 | Back Clamp | 25 | Each | |
73 | 73 | Stay Clamp | 25 | Each | |
74 | 74 | Erection of new earth pipe by replacing the corroded earth pipe | 10 | Each | |
75 | 75 | Re-stringing of LT line for all sizes of conductor | 25 | Per Wire Per Span | |
76 | 76 | Re-stringing of HT line for all sizes of conductor | 10 | Per Wire Per Span | |
77 | 77 | Provinding LT Bus bar arrangement in Distn.Tr Structures | 15 | Per DT | |
78 | 78 | Fencing of Distribution Transformer Structure at Road side fabrication and erection | 5 | Per Struct | |
79 | 79 | Erection of New 10' Earthh pipe replacing carroded earth pipe and renewal of earthing including burying looping and binding | 10 | Per Struct | |
80 | 80 | Renewal of Jumper from 22/11 KV line to AB switch to HG fuse to Distn. Transformer with PG Clamps | 10 | Per Struct | |
81 | 81 | Cutting of Coconut leaves | 50 | Per Tree | |
82 | 82 | Drilling of hoe in channel only 3/4" & 1" per hole | 300 | Each | |
83 | 83 | Cutting of flat | 20 | Each | |
84 | 84 | Cutting of Channel | 20 | Each | |
85 | 85 | Cutting of Angle | 20 | Each | |
86 | 86 | Cutting of Pipe | 10 | Each | |
87 | 87 | Dismantling of Line Materials | |||
88 | 88 | Dismantling of pole (9.14mtr) | 25 | Each | |
89 | 89 | Dismantling of pole (7.5mtr & 8mtr) | 200 | Each | |
90 | 90 | Dismantling of HT Pin Insulator | 125 | Each | |
91 | 91 | Dismantling of HT /LT TI Fitting | 40 | Each | |
92 | 92 | Dismantling of 3 PH X arm | 50 | Each | |
93 | 93 | Dismantling of Tapping X arm, V X arm & Guarding X arm | 50 | Each | |
94 | 94 | Dismantling of 1 PH X arm | 150 | Each | |
95 | 95 | Dismantling of Alu Knob | 100 | Each | |
96 | 96 | Dismantling of LT pin Insulator | 200 | Each | |
97 | 97 | Dismantling of LT Shackle Insulator | 100 | Each | |
98 | 98 | Dismantling of Stayset Complete | 50 | Each | |
99 | 99 | Dismantling of Line Materials & Transformers | 2 | Per DT | |
100 | 100 | Dismanlting of Single Pole Structure | 10 | Per Struct | |
101 | 101 | Releasing of Conductor ACSR 7/2.11 mm & 7/2.59 mm | 56 | Per Wire Per Span | |
102 | 102 | Releasing of Conductor ACSR 7/3.00 mm & 7/3.35 mm | 70 | Per Wire Per Span | |
103 | 103 | E.S.I. @ 3.25 % should be Entered by the Bidder. | 1 | Percentage | |
104 | 104 | E.P.F. @ 13 % should be Entered by the Bidder. | 1 | Percentage | |
105 | 105 | G.S.T. @ 18% should be Entered by the Bidder. | 1 | Percentage |
Copyright © 2024 · All Rights Reserved. Terms of Usage | Privacy Policy
For Tender Information Services Visit : TenderDetail