| 1 | 1 | Charges for Removing, cleaning, transporting, servicing, air leak and operation checking, re fixing and checking of Retractor Assembly of HEA Ignitors. | item1 | 12 | Nos |
|---|
| 2 | 2 | Charges for painting retractor assembly of HEA Ignitors and Power cylinders (Double coating). | item2 | 12 | Nos |
|---|
| 3 | 3 | Charges for removing, transporting, cleaning, servicing, refixing and checking of flame scanners. | item3 | 32 | Nos |
|---|
| 4 | 4 | Charges for removing, transporting, cleaning and refixing after calibration local pressure gauges/ temperature gauges. | item4 | 100 | Nos |
|---|
| 5 | 5 | Charges for Removal of Pressure/DP/ temperature switches and refixing them after calibration | item5 | 44 | Nos |
|---|
| 6 | 6 | Charges for dismantling, transporting, cleaning and refixing them after calibration of Pressure Transmitters. | item6 | 7 | Nos |
|---|
| 7 | 7 | Charges for removing from field, transporting to LAB, cleaning, calibrating, and refixing after calibration of air regulator with gauges. | item7 | 48 | Nos |
|---|
| 8 | 8 | Charges for removing from field, transporting to LAB, cleaning, re fixing after calibration of I/P converter. | item8 | 23 | Nos |
|---|
| 9 | 9 | Charges for opening and cleaning of 1/2\" impulse line and catch pot in mills,Flue gas, primary and secondary air paths. | item9 | 26 | Nos |
|---|
| 10 | 10 | Charges for releasing of Electronic cards , cleaning of panels & reinserting the cards, terminal tightness checking of FSSS DCS , Feeder, HYDRASTEP ,Flame scanner, 110 V AC & 220 V DC distribution panels and CHARGER Panels. | item10 | 31 | Nos |
|---|
| 11 | 11 | Charges for removing, cleaning, servicing, refixing and checking of SADC positioners. | item11 | 48 | Nos |
|---|
| 12 | 12 | Removing the terminal connections, Replacing the broken Terminal Blocks and reconnecting the terminal connections and checking in Various Junction boxes at Boiler and mill area. | item12 | 100 | Nos |
|---|
| 13 | 13 | Charges for removing, cleaning solenoid valves, air filter cum lubricator & the airlines and replacing the ‘O’ rings in the solenoid valves and refixing the solenoid valves, air filter cum lubricator & the airlines in the HAGs | item13 | 6 | Nos |
|---|
| 14 | 14 | Charges for cutting and welding of take-off catch pot in mills, flue gas, primary and secondary air path. | item14 | 15 | Nos |
|---|
| 15 | 15 | Supply of required U seals etc. for the above Sl.No.1 work. | item15 | 12 | SET |
|---|
| 16 | 16 | Supply of required Paint, Cotton waste, Kerosene, rust remover etc. for the above Sl.No.2 work. | item16 | 12 | SET |
|---|
| 17 | 17 | Supply of required petrol, dungry cloth etc. for the above Sl.No.3 work. | item17 | 32 | SET |
|---|
| 18 | 18 | Supply of required Bellows, dungry cloth & petrol etc. for the above Sl.No.11 work. | item18 | 48 | SET |
|---|
| 19 | 19 | Supply of required ‘O’ rings and U seals, dungry cloth & petrol etc., for the above Sl.No.13 work. | item19 | 6 | SET |
|---|
| 20 | 20 | Supply of required gas, welding electrodes & consumables such as cotton waste, hacksaw blade etc. for the above Sl.No. 14 work. | item20 | 15 | SET |
|---|