| 1 | 1 | Description of work to be executed | BI01010001010000000000000515BI0100001112 | | |
|---|
| 2 | 1.01 | Carefully removal of sunken, uneven, damaged stone flooring including excavation & throwing away debris to a far off place leveling the surface watering ramming etc complete as directed by site in-charge. | BI01010001010000000000000515BI0100001113 | 62.26 | cmt |
|---|
| 3 | 1.02 | Laying of base concrete in lime, sand, surkhi mortar (1:3:6)with 20mm brick aggregate for flooring including ramming, mixing, curing etc complete as directed by site in-charge. | BI01010001010000000000000515BI0100001114 | 30.06 | cmt |
|---|
| 4 | 1.03 | Laying stone flooring using 0.12M thick with local hard stone using lime mortar 1:1:1 including plain dressing, cutting, setting, curing etc complete. (size 0.60x0.45m) as directed by site in-charge. | BI01010001010000000000000515BI0100001115 | 29.65 | cmt |
|---|
| 5 | 1.04 | Carefully dismantling the damaged, decade architectural members like kumbhi, pillars, capital, lintel, slab, steps, Chajjas etc collecting stacking and throwing away the debris to a far off place etc complete (as per measurement sheet enclosed) as directed by site in-charge. | BI01010001010000000000000515BI0100001116 | 10.85 | cmt |
|---|
| 6 | 1.05 | Reconstructing of architectural members like kumbhi, pillars, capital, lintel, slab steps, Chajjas etc with local stone in lime, surkhi, sand mortar 1:1:1 including dressing, molding, cutting, setting & fixing, curing as per original etc complete. (as per measurement sheet enclosed) as directed by site in-charge. | BI01010001010000000000000515BI0100001117 | 19.11 | cmt |
|---|
| 7 | 1.06 | carefully dismantling the damaged and warn out ashlar stone masonry supporting wall including stacking out materials and throwing away the debris to a far off place etc complete. | BI01010001010000000000000515BI0100001118 | 9.87 | cmt |
|---|
| 8 | 1.07 | Reconstructing ashlar stone masonry supporting wall using local stone set in 1:1:1 lime, surkhi, sand mortar to match with existing including dressing of new stone & pointing, curing etc complete. | BI01010001010000000000000515BI0100001119 | 11.59 | cmt |
|---|
| 9 | 1.08 | Carefully removal of old decade, damaged cement plaster from wall etc collecting stacking and throwing away the debris to a far off place etc complete (as per measurement sheet enclosed) as directed by site in-charge. | BI01010001010000000000000515BI0100001120 | 76.78 | cmt |
|---|
| 10 | 1.09 | Applying Lime plaster to walls in 1:1:1 Lime sand surkhi mortar including curing etc. complete as directed by site in-charge. | BI01010001010000000000000515BI0100001121 | 76.78 | Sq.mt |
|---|
| 11 | 1.1 | Dismantling of old damaged wooden doors of small temples for prevent of bats and other animals inside the garbh gruh of temples and making new wooden doors including jali work, color work, transportation, fixing, labour, materials etc. complete. (size : 3 nos. x 0.90 x1.60) (as per enclosed drawing ) as directed by site in-charge. | BI01010001010000000000000515BI0100001122 | 3 | nos |
|---|
| 12 | 1.11 | Supply of water by tanker with a capacity of 5000lit . | BI01010001010000000000000515BI0100001123 | 25 | trip |
|---|