| 1 | 1 | Scheme 1 | BI01010001010000000000000515BI0100001113 | | |
|---|
| 2 | 1.01 | 60.7.1 : DRY RUBBLE MASONRY _ Dry rubble without concrete levelling course masonry with good quality blasted rubble including packing to compactness to lines and levels cost and conveyance of all materials labour charges etc. complete as per direction of Departmental officers at site | BI01010001010000000000000515BI0100001114 | 28.25 | cum |
|---|
| 3 | 1.02 | 2.6.1 : Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including disposal of excavated earth, lead up to 50 m and lift up to 1.5 m, disposed earth to be levelled and neatly dressed.All kinds of soil | BI01010001010000000000000515BI0100001115 | 66.95 | cum |
|---|
| 4 | 1.03 | 4.1.5 : Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 20 mm nominal size) | BI01010001010000000000000515BI0100001116 | 0.75 | cum |
|---|
| 5 | 2 | Scheme 2 | BI01010001010000000000000515BI0100001117 | | |
|---|
| 6 | 2.01 | 2.6.1 : Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including disposal of excavated earth, lead up to 50 m and lift up to 1.5 m, disposed earth to be levelled and neatly dressed.All kinds of soil | BI01010001010000000000000515BI0100001118 | 9.45 | cum |
|---|
| 7 | 2.02 | 4.1.8 : Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 nominal size) | BI01010001010000000000000515BI0100001119 | 4.725 | cum |
|---|
| 8 | 2.03 | 4.1.3 : Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:2:4 (cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size) | BI01010001010000000000000515BI0100001120 | 8.925 | cum |
|---|
| 9 | 2.04 | 4.3.1 : Centering and shuttering including strutting, propping etc. and removal of form work for:Foundations, footings, bases for columns | BI01010001010000000000000515BI0100001121 | 95.01 | sqm |
|---|
| 10 | 2.05 | 5.22.6 : Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more | BI01010001010000000000000515BI0100001122 | 133.875 | kilogram |
|---|
| 11 | 3 | Scheme 3 | BI01010001010000000000000515BI0100001123 | | |
|---|
| 12 | 3.01 | 2.6.1 : Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including disposal of excavated earth, lead up to 50 m and lift up to 1.5 m, disposed earth to be levelled and neatly dressed.All kinds of soil | BI01010001010000000000000515BI0100001124 | 9.45 | cum |
|---|
| 13 | 3.02 | 4.1.8 : Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 nominal size) | BI01010001010000000000000515BI0100001125 | 4.725 | cum |
|---|
| 14 | 3.03 | 4.1.3 : Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:2:4 (cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size) | BI01010001010000000000000515BI0100001126 | 8.925 | cum |
|---|
| 15 | 3.04 | 4.3.1 : Centering and shuttering including strutting, propping etc. and removal of form work for:Foundations, footings, bases for columns | BI01010001010000000000000515BI0100001127 | 95.01 | sqm |
|---|
| 16 | 3.05 | 5.22.6 : Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more | BI01010001010000000000000515BI0100001128 | 133.875 | kilogram |
|---|
| 17 | 4 | Scheme 4 | BI01010001010000000000000515BI0100001129 | | |
|---|
| 18 | 4.01 | 2.6.1 : Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including disposal of excavated earth, lead up to 50 m and lift up to 1.5 m, disposed earth to be levelled and neatly dressed.All kinds of soil | BI01010001010000000000000515BI0100001130 | 9.45 | cum |
|---|
| 19 | 4.02 | 4.1.8 : Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 nominal size) | BI01010001010000000000000515BI0100001131 | 4.725 | cum |
|---|
| 20 | 4.03 | 4.1.3 : Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:2:4 (cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size) | BI01010001010000000000000515BI0100001132 | 8.925 | cum |
|---|
| 21 | 4.04 | 4.3.1 : Centering and shuttering including strutting, propping etc. and removal of form work for:Foundations, footings, bases for columns | BI01010001010000000000000515BI0100001133 | 95.01 | sqm |
|---|
| 22 | 4.05 | 5.22.6 : Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more | BI01010001010000000000000515BI0100001134 | 133.875 | kilogram |
|---|
| 23 | 5 | Scheme 5 | BI01010001010000000000000515BI0100001135 | | |
|---|
| 24 | 5.01 | 2.6.1 : Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including disposal of excavated earth, lead up to 50 m and lift up to 1.5 m, disposed earth to be levelled and neatly dressed.All kinds of soil | BI01010001010000000000000515BI0100001136 | 9.45 | cum |
|---|
| 25 | 5.02 | 4.1.8 : Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 nominal size) | BI01010001010000000000000515BI0100001137 | 4.725 | cum |
|---|
| 26 | 5.03 | 4.1.3 : Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:2:4 (cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size) | BI01010001010000000000000515BI0100001138 | 8.925 | cum |
|---|
| 27 | 5.04 | 4.3.1 : Centering and shuttering including strutting, propping etc. and removal of form work for:Foundations, footings, bases for columns | BI01010001010000000000000515BI0100001139 | 95.01 | sqm |
|---|
| 28 | 5.05 | 5.22.6 : Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more | BI01010001010000000000000515BI0100001140 | 133.875 | kilogram |
|---|
| 29 | 6 | Scheme 6 | BI01010001010000000000000515BI0100001141 | | |
|---|
| 30 | 6.01 | 2.6.1 : Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including disposal of excavated earth, lead up to 50 m and lift up to 1.5 m, disposed earth to be levelled and neatly dressed.All kinds of soil | BI01010001010000000000000515BI0100001142 | 8.1 | cum |
|---|
| 31 | 6.02 | 4.1.8 : Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 nominal size) | BI01010001010000000000000515BI0100001143 | 4.05 | cum |
|---|
| 32 | 6.03 | 4.1.3 : Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:2:4 (cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size) | BI01010001010000000000000515BI0100001144 | 7.65 | cum |
|---|
| 33 | 6.04 | 4.3.1 : Centering and shuttering including strutting, propping etc. and removal of form work for:Foundations, footings, bases for columns | BI01010001010000000000000515BI0100001145 | 81.51 | sqm |
|---|
| 34 | 6.05 | 5.22.6 : Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more | BI01010001010000000000000515BI0100001146 | 114.75 | kilogram |
|---|
| 35 | 7 | Scheme 7 | BI01010001010000000000000515BI0100001147 | | |
|---|
| 36 | 7.01 | 2.6.1 : Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including disposal of excavated earth, lead up to 50 m and lift up to 1.5 m, disposed earth to be levelled and neatly dressed.All kinds of soil | BI01010001010000000000000515BI0100001148 | 8.1 | cum |
|---|
| 37 | 7.02 | 4.1.8 : Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 nominal size) | BI01010001010000000000000515BI0100001149 | 4.05 | cum |
|---|
| 38 | 7.03 | 4.1.3 : Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:2:4 (cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size) | BI01010001010000000000000515BI0100001150 | 7.65 | cum |
|---|
| 39 | 7.04 | 4.3.1 : Centering and shuttering including strutting, propping etc. and removal of form work for:Foundations, footings, bases for columns | BI01010001010000000000000515BI0100001151 | 81.51 | sqm |
|---|
| 40 | 7.05 | 5.22.6 : Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more | BI01010001010000000000000515BI0100001152 | 114.75 | kilogram |
|---|
| 41 | 8 | Scheme 8 VCB Repair-DS Apron | BI01010001010000000000000515BI0100001153 | | |
|---|
| 42 | 8.01 | 2.6.1 : Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including disposal of excavated earth, lead up to 50 m and lift up to 1.5 m, disposed earth to be levelled and neatly dressed.All kinds of soil | BI01010001010000000000000515BI0100001154 | 5.4 | cum |
|---|
| 43 | 8.02 | 4.1.3 : Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:2:4 (cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size) | BI01010001010000000000000515BI0100001155 | 5.4 | cum |
|---|
| 44 | 8.03 | 4.3.1 : Centering and shuttering including strutting, propping etc. and removal of form work for:Foundations, footings, bases for columns | BI01010001010000000000000515BI0100001156 | 2.7 | sqm |
|---|
| 45 | 8.04 | 5.22.6 : Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more | BI01010001010000000000000515BI0100001157 | 54 | kilogram |
|---|
| 46 | 9 | Scheme 9 VCB Repair-US Apron and curtain wall | BI01010001010000000000000515BI0100001158 | | |
|---|
| 47 | 9.01 | 2.6.1 : Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including disposal of excavated earth, lead up to 50 m and lift up to 1.5 m, disposed earth to be levelled and neatly dressed.All kinds of soil | BI01010001010000000000000515BI0100001159 | 7.56 | cum |
|---|
| 48 | 9.02 | 4.1.3 : Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:2:4 (cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size) | BI01010001010000000000000515BI0100001160 | 7.56 | cum |
|---|
| 49 | 9.03 | 4.3.1 : Centering and shuttering including strutting, propping etc. and removal of form work for:Foundations, footings, bases for columns | BI01010001010000000000000515BI0100001161 | 17.1 | sqm |
|---|
| 50 | 9.04 | 5.22.6 : Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more | BI01010001010000000000000515BI0100001162 | 97.2 | kilogram |
|---|
| 51 | 10 | Scheme 10 Pier Maintenance | BI01010001010000000000000515BI0100001163 | | |
|---|
| 52 | 10.01 | 4.1.3 : Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:2:4 (cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size) | BI01010001010000000000000515BI0100001164 | 0.945 | cum |
|---|
| 53 | 10.02 | 2.6.1 : Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including disposal of excavated earth, lead up to 50 m and lift up to 1.5 m, disposed earth to be levelled and neatly dressed.All kinds of soil | BI01010001010000000000000515BI0100001165 | 23.35 | cum |
|---|
| 54 | 10.03 | 4.3.1 : Centering and shuttering including strutting, propping etc. and removal of form work for:Foundations, footings, bases for columns | BI01010001010000000000000515BI0100001166 | 7.65 | sqm |
|---|
| 55 | 10.04 | 5.22.6 : Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more | BI01010001010000000000000515BI0100001167 | 18.9 | kilogram |
|---|
| 56 | 10.05 | 60.8 : Shutter for check dams- Supplying and providing Thambagam wood shutter planks 5cm thick including cost of materials and labour charges etc complete | BI01010001010000000000000515BI0100001168 | 32.55 | 10 cud m |
|---|
| 57 | 10.06 | 60.3 : Supplying and fixing structural steel channel ISMC 75X40mm for holding shutter planks including cutting ,hoisting fixing in position with material and labour charges etc complete | BI01010001010000000000000515BI0100001169 | 10.4 | metre |
|---|
| 58 | 10.07 | 60.4 : Locking Arrangements - Supplying and Fixing lock and locking arrangements with suitable chain hooks,and padlock of 65mm size. | BI01010001010000000000000515BI0100001170 | 2 | each |
|---|
| 59 | 10.08 | 60.5 : MS Rings - 100mm dia | BI01010001010000000000000515BI0100001171 | 4 | set |
|---|
| 60 | 10.09 | 5.23 : Smooth finishing of the exposed surface of RCC work with 6mm thick cement mortar 1:3 ( cement : 3 fine sand). | BI01010001010000000000000515BI0100001172 | 7.65 | sqm |
|---|