| 1 | 1 | Earth work in excavation of foundation in hard soil or gravelly soil within the initial lead and lift including dressing and levelling the bed and depositing the excavated materials away from the work site etc. all complete as directed by the Engineer-in-charge | BI01010001010000000000000515BI0100001104 | 71.55 | one cum |
|---|
| 2 | 2 | Sand Filling foundation and plinth with sand well watered and rammed including all cost, carriage, royality, taxes and all labour, T & P etc. all complete as per the direction of Engineer-in- charge. | BI01010001010000000000000515BI0100001106 | 208.25 | one cum |
|---|
| 3 | 3 | Cement concrete (1:3:6) using 40mm and down gradedhard granite crusher broken metal including all cost , carriage, royality, taxes, and all labour involved for completion of item of work as per the direction of Engineer- in - charge. | BI01010001010000000000000515BI0100001107 | 28.49 | one cum |
|---|
| 4 | 4 | R.C.C work of M20 grade with 20 mm and down grade crusher broken hard granite chips including hosting and laying all cost of materials, labour, conveyance, royalty, cess, Tools and Plants water for curing etc. all complete, as per OPWD specification. | BI01010001010000000000000515BI0100001110 | 37.33 | one cum |
|---|
| 5 | 5 | TMT reinforcement for R.C.C. work including cutting, bending, binding and placing in position Labor for including cost of binding wire 18 to 20 gauge and cost conveyance of M.S. rod etc. all complete. | BI01010001010000000000000515BI0100001116 | 24.64 | one qntl |
|---|
| 6 | 6 | Brickwork in Fly ash bricks having crushing strength not less than 75 Kg/cm2 with in cement mortar (1:6) in foundation and plinth including all cost of materials, labour, conveyance, royalty, cess,Tools and Plants water for curing etc.all complete. | BI01010001010000000000000515BI0100001108 | 52.19 | onecum |
|---|
| 7 | 7 | Labour for fixing MS Sheet in roof drilling hole in wind ties including fixing of ridges valleys wind ties etc. excluding cost of fitting | BI01010001010000000000000515BI0100001109 | 412.6 | onecum |
|---|
| 8 | 8 | Cement concrete (1:2:4) with 12 mm size hard broken hard granite chips (CB) including all cost of materials, labour, conveyance, royalty, Tools and Plants water for curing etc.all complete. \n | | 11.76 | onecum |
|---|
| 9 | 9 | Cost of MS Tube pipe for posts 150 mm dia. X 4.85 mm. thickness ( Medium ) for Posts including fitting, fixing,Cutting, welding & Errection at site, | | 1544.49 | one kg |
|---|
| 10 | 10 | Cost of MS Tube pipe for posts 65 mm dia. X 3.65 mm. thickness ( Medium ) Trusses including fitting, fixing,Cutting, welding & Errection at site, | | 500.2 | one kg |
|---|
| 11 | 11 | Cost of MS Tube pipe for posts 40 mm dia. X 3.65 mm. thickness ( Medium ) for Purlins including fitting, fixing,Cutting, welding & Errection at site, | | 1708.25 | one kg |
|---|
| 12 | 12 | Cost of MS Tube pipe for posts 25 mm dia. X 3.25 mm. thickness ( Medium ) for Purlins including fitting, fixing,Cutting, welding & Errection at site, | | 274.988 | one kg |
|---|
| 13 | 13 | Cost of MS base Plates for posts 5 mm thickness including fitting, fixing,Cutting, welding & Errection at site, | | 225.79 | one kg |
|---|
| 14 | 14 | Cost of MS Flats for wind ties 25 mm dia. X 6.00 mm. thickness including fitting, fixing,Cutting, welding & Errection at site, | | 396.48 | one kg |
|---|
| 15 | 15 | Cost of MS Flats Jally 25 mm dia. X 6.00 mm. thickness for Litch pit including fitting, fixing,Cutting, welding & Errection at site, | | 280 | one kg |
|---|
| 16 | 16 | Supplying, fitting and fixing of MS Grill incl. all cost complete | | 1411.2 | one sqm |
|---|
| 17 | 17 | Cost of Bitumen Washer, J hook, Nut bolt and other unforeseen item etc. | | 1 | LS |
|---|