BRR : 9306793
Tender Brief : Tender for E/Work In Excavation In Hard Soil In Fdn. Including Rough Dressing & Levelling The Bed Not Exceeding 0.30 M Depth As Per Specification , Earthwork In Excavation Of Foundation In Hard Soil Such As Hard Stiff Clay, Stiff Black Cotton, Hard Red Earth, Shales, Moorum Ordinary Gravels Etc Within 50M.Initial Lead And 1.5M. Initial Lift Including Rough Dressing And Levelling The Bed And Depositing The Excavated Materials Within Initial Lead At Nearby The Worksite For Reuse Including Breaking Clods And Stacking Rubble For Spreading And Leveling As The Case May Be Etc Complete As Per Direct... Read More
Tender Value
₹
30,86,386
Contract Value
₹ 36,41,935
Saving / Difference
₹ -5,55,549
▼
Submission Date
04-11-2025
Contract Date
02-04-2026
Completion Date
90 days
Participated Bidder List
2 No of Bidder(s)
| Sr No. | Bidder Name | Bid Analytics | Technical Bid | Financial Bid | AOC | Bid Value | Rank |
|---|---|---|---|---|---|---|---|
| 1 | cnet-technologies | Bid Analytics | 36,41,935 | L1 | |||
| 2 | cnet-technologies | Bid Analytics | 32,40,705.3 | L2 |
Work Detail
tender for e/work in excavation in hard soil in fdn. including rough dressing & levelling the bed not exceeding 0.30 m depth as per specification , earthwork in excavation of foundation in hard soil such as hard stiff clay, stiff black cotton, hard red earth, shales, moorum ordinary gravels etc within 50m.initial lead and 1.5m. initial lift including rough dressing and levelling the bed and depositing the excavated materials within initial lead at nearby the worksite for reuse including breaking clods and stacking rubble for spreading and leveling as the case may be etc complete as per direction of the engineer-in-charge. (excavation by mechanical means 60% & manually 40%) , filling in f&p with sand wall watered and rammed. , cement concrete (1:4:8) with 40mm size of h.g. metal. , filling in f&p with excavated materials quantity same as item no-1 above , filling in f&p with excavated materials in layers not exceeding 0.30m including breaking clods within 50m. initial lead including leveling the tranches as the case may be etc complete as per direction of the engineer-in-charge.(quantity by means of mechanical 60% & mannually 40% i.e. of respective item no. 2 above) , cement concrete (1:2:4) with 12mm size c.b. chips including hoisting and laying , brick masonary in cm (1:6) in foundation & plinth.(fly ash) , brick masonary in cm (1:6) in superstructure.(fly ash) , 12mm thick cement plaster over brick works. , rigid and smooth centering & shuttering for reinforced cement concrete works including tales works after dismantlling then after centering including cost of all materials in ground floor , column , b) roof slab , c) lintel , 2.5cm a.s. flooring with c.c.(1:2:4) including punning with 12mm size chips. , cement punning , white washing two coats to walls with shell lime of approved shade on new work to give an even shade including cost of lime & labour etc. complete. , finishing walls with water proofing cement paint of approved shade on new work ( 2 coats ) to gi
View Original Notice/Document
Result Documents
Tender Documents
| Download | File Name | File Description |
|---|---|---|
| Download | technical_557827 | aoc document |
| Download | techsummary_557827 | aoc document |
| Download | 5c6780d3-82a3-4839-925f-0939617c17f2 | technicalevaluation notice |
| Download | 60aaa01f-dd0a-4851-8536-bedddea603bc | result notice |
| Download | boqcomparativechart | boq document |
| Download | finance_557827 | aoc document |
| Download | finsummary_557827 | aoc document |
| Download | joka_i | aoc document |
Disclaimer
We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender
✦ ✦ ✦
Awarded Bidder(s)
1
cnet-technologies
Rank : L1 (Lowest)
Bid Amount :
₹
1,00,00,000