BRR : 8492895
Tender Brief : Tender For D Type Qtr Of Tahasil Chilika At Gangadharpur For The Year 2025-26- 1 Providing cement concrete (1:3:6) in foundation with 40mm & down graded size of crusher broken hard granite stone aggregate of approved quality from approved quarry including hoisting, lowering and laying in position, including curing, dewatering, shoring, centering & shuttering if necessary at the time of laying concrete with cost, conveyance, royalty and taxes of all materials requried for the work etc.complete in all respect as per specification and direction of the Engineer-in-Charge. 2 Providing Cement Conc... Read More
Tender Value
₹
4,24,000
Contract Value
₹ 3,59,038.94
Saving / Difference
₹ 64,961
▲
Submission Date
20-11-2025
Contract Date
25-12-2025
Completion Date
60 days
Participated Bidder List
12 No of Bidder(s)
| Sr No. | Bidder Name | Bid Analytics | Technical Bid | Financial Bid | AOC | Bid Value | Rank |
|---|---|---|---|---|---|---|---|
| 1 | cnet-technologies | Bid Analytics | 3,59,038.94 | L3 | |||
| 2 | cnet-technologies | Bid Analytics | 3,59,038.94 | L3 | |||
| 3 | cnet-technologies | Bid Analytics | 3,59,038.94 | L3 | |||
| 4 | cnet-technologies | Bid Analytics | 3,59,038.94 | L3 | |||
| 5 | cnet-technologies | Bid Analytics | 3,59,038.94 | L1 | |||
| 6 | cnet-technologies | Bid Analytics | 3,59,038.94 | L3 | |||
| 7 | cnet-technologies | Bid Analytics | 3,59,038.94 | L3 | |||
| 8 | cnet-technologies | Bid Analytics | 3,59,038.94 | L3 | |||
| 9 | cnet-technologies | Bid Analytics | 3,59,038.94 | L3 | |||
| 10 | cnet-technologies | Bid Analytics | 3,59,038.94 | L3 | |||
| 11 | cnet-technologies | Bid Analytics | 3,59,038.94 | L3 | |||
| 12 | cnet-technologies | Bid Analytics | 3,59,038.94 | L3 |
Work Detail
tender for d type qtr of tahasil chilika at gangadharpur for the year 2025-26- 1 providing cement concrete (1:3:6) in foundation with 40mm & down graded size of crusher broken hard granite stone aggregate of approved quality from approved quarry including hoisting, lowering and laying in position, including curing, dewatering, shoring, centering & shuttering if necessary at the time of laying concrete with cost, conveyance, royalty and taxes of all materials requried for the work etc.complete in all respect as per specification and direction of the engineer-in-charge. 2 providing cement concrete (1:2:4) with 12mm stone aggregate in foundations upto a depth of 1.5m below ground level and upto a height of 1.5m above ground level / bed level including cost and conveyance of all materials to site, and all labour charges complete as per direction of e.i.c. 3 providing fitting and fixing of false celling with aluminium anodised t section no. 3215 with 2-0 center to centr, l section no. 1705 up to 15 micron on 4 walls to be fixed by means of steel screw and pvc plug and the aluminium grid 2-0 x 2-0 with prelaminated particle board suspended from celling etc. complete as per specification and direction of the engineer-in-charge. 4 providing fitting and fixing of false celling boarder withall cost suspended from celling etc. complete as per specification and direction of the engineer-in-charge. 5 12mm thick cement plaster in c.m. (1:6) over brick masonry & wall surface after racking out joints, cleaning & finishing the plaster surface smooth including watering & curing with cost, conveyance, royalty and taxes of all materials and cost of all labour with t&p required for the work etc. complete as per specification and direction of the engineer-in-charge . 6 anti termite treatment in floor basement including all round the plinth area to the required depth(as per epm specification)including cost, conveyance, labour, tax, t&p,cess, etc., required for the work as per direction of the engineer-in-charge. 7 fixing virtified tiles in floors 600x600mm size including cost and conveyance of all materials to site, and all labour charges complete including cost at tiles etc.as per direction of e.i.c.. 8 16mm thick cement plaster with c.m. (1:6) over brick masonry & wall surface after racking out joints, cleaning & finishing the plaster surface smooth including watering, curing, scaffolding, screening sand with cost, conveyance, royalty and taxes of all materials and cost of all labour with t&p etc. complete as per specification and direction of the engineer-in-charge . 9 distempering two coats to wall with distemper of approved shade over interior surface of walls & ceiling to given an even shade including cost of all materials cost of all labour & t&p required for the work etc. complete as per direction of the engineer-in-charge. 10 providing weather coat two coats over a coat of primer of approved shed to give an even shade including cost of sand paper, polishing the surface with cost, conveyance and taxes of all materials and labour with t&p required for the work etc. complete in all respect as direction of the engineer - in-charge . please enable macros to view boq information
View Original Notice/Document
Result Documents
Tender Documents
Disclaimer
We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender
✦ ✦ ✦
Awarded Bidder(s)
1
cnet-technologies
Rank : L1 (Lowest)
Bid Amount :
₹
1,00,00,000