BRR : 8057882
Click Here To View Tendering Authority. Aoc City/State :  sambhal, Uttar Pradesh
Tender Brief : Tender For Financial Year 24-25 Under Reconstruction Work Of Chitora To Bamneta Road- Construction of embankment with approved material obtained from borow pits with all lifts and leads trancporting upto 3 Km upto sites, spreading, grading to required slope and compected to meet requirement of table 300.2 and lead andincluding all material, labour, labour cess, T&P royalty, all tasex etc. complete as per diretcion by i-in-c but excluding G.S.T. 2 Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam specification including spreading in uniform ... Read More
Tender Value
67,00,000
Contract Value
₹ 66,29,213.25
Saving / Difference
₹ 70,787 ▲
Submission Date
29-03-2025
Contract Date
04-10-2025
Completion Date
180 days
Participated Bidder List
12 No of Bidder(s)
Sr No. Bidder Name Bid Analytics Technical Bid Financial Bid AOC Bid Value Rank
1 cnet-technologies Bid Analytics 57,89,291.93 L11
2 cnet-technologies Bid Analytics 56,34,831.26 L10
3 cnet-technologies Bid Analytics 59,66,954.85 L12
4 cnet-technologies Bid Analytics 54,36,617.79 L7
5 cnet-technologies Bid Analytics 50,77,977.35 L4
6 cnet-technologies Bid Analytics 47,33,258.26 L2
7 cnet-technologies Bid Analytics 49,65,280.72 L3
8 cnet-technologies Bid Analytics 52,98,730.15 L5
9 cnet-technologies Bid Analytics 55,61,909.92 L9
10 cnet-technologies Bid Analytics 55,15,505.42 L8
11 cnet-technologies Bid Analytics 53,70,325.65 L6
12 cnet-technologies Bid Analytics 46,57,022.31 L1
Work Detail
tender for financial year 24-25 under reconstruction work of chitora to bamneta road- construction of embankment with approved material obtained from borow pits with all lifts and leads trancporting upto 3 km upto sites, spreading, grading to required slope and compected to meet requirement of table 300.2 and lead andincluding all material, labour, labour cess, t&p royalty, all tasex etc. complete as per diretcion by i-in-c but excluding g.s.t. 2 providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with smoothwheel roller 80-100 kn in stages to proper grade and camber, applying and brooming, stone screening to fill-up the interstices of coarse aggregate, watering and compacting to the required density grading 2as per technicalspecification clause 405. andincluding all material, labour, labour cess, t&p royalty, all tasex etc. complete as per diretcion by i-in-c but excluding g.s.t. 3 providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with smoothwheel roller 80-100 kn in stages to proper grade and camber, applying and brooming, stone screening to fill-up the interstices of coarse aggregate, watering and compacting to the required density grading 3as per technicalspecification clause 405. andincluding all material, labour, labour cess, t&p royalty, all tasex etc. complete as per diretcion by i-in-c but excluding g.s.t. 4 brick edging on both sides of the road of first class (m-150) brick on edge laid with mud mortar including labour and supply of bricks finished to the required templete and in proper alignment and also including dressing and ramming the excavated earth as directed by the engineer-in-charge. si no 765andincluding all material, labour, labour cess, t&p royalty, all tasex etc. complete as per diretcion by i-in-c but excluding g.s.t. 5 providing and applying primer coat with bitumen emulsion (ss) on prepared surface of granular base including cleaning of road surface and spraying primer at the rate of 0.70kg/sqm using mechanical means as per technical specification clause 502 andincluding all material, labour, labour cess, t&p royalty, all tasex, bitumen ect. complete as per direction by i-in-c but excluding g.s.t. 6 providing & applying tack coat with bitumen vg-10 using pressure distributor at the rate of 0.30 kg per sqm on the prepared bituminous/granular surface cleaned with hydraulic burmer incliding as per tecnical specification clause 503. andincluding all material, labour, labour cess, t&p royalty, all tasex, bitumen ect. complete as per direction by i-in-c but excluding g.s.t. 7 p/l of open graded premix carpeting of 20mm thick composed with 13.2 mm to 5.60mm grit aggregate or approved graded grit @ 0.27 cum/10sqm. usingbitumen (vg-10) @ 146.00 kg./100sqm.as bearing course, including heating of bitumen to required temperature, andincluding all material, labour, labour cess, t&p royalty, all tasex, bitumen ect. complete as per direction by i-in-c but excluding g.s.t. tecnical specification clause 508 8 providing and applying seal coat type ‘c’ with 2.36 mm gauge stone grit @ 0.90 cum/100 sqm & bitumen (vg-10) 65 kg/100 sqm including heating of bitumen to required temperature, mixing of stone grit with suitable mixol, laying and rolling with a smooth wheeled roller andincluding all material, labour, labour cess, t&p royalty, all tasex, bitumen ect. complete as per direction by i-in-c but excluding g.s.t. 9 excavation in foundation in ordinary soil (loan, clay or sand) including lift up to 1.5 m and lead up to 30m and including filling waterning and ramming of excavated earth in to the trenches or in to the space in to the building and the side of foundation tranches.3andincluding all material, labour, labour cess, t&p royalty, all tasex, bitumen ect. complete as per direction by i-in-c but excluding g.s.t. 10 plain cement concrete with 4cm guage stone ballast and fine sand of 1.25 f.m and cement in proportion of 1:4:8 in foundation and under floorsand incliding supply of all meterial t&p and labour cess etc. as per direction of engineer in charge.required for propercompletion of the work. si no- 281 andincluding all material, labour, labour cess, t&p royalty, all tasex, bitumen ect. complete as per direction by i-in-c but excluding g.s.t. 11 laying and compacting dry o.b.b. 40mm. gauge in foundation in layers of not more than 15cm. thickness including local sand, in ratio 2:1 andincluding all material, labour, labour cess, t&p royalty, all tasex, bitumen ect. complete as per direction by i-in-c but excluding g.s.t. 12 m-150 brick work in 1:3 cement and coarse sand mortar in foundation and plinth andincluding all material, labour, labour cess, t&p royalty, all tasex, bitumen ect. complete as per direction by i-in-c but excluding g.s.t. 13 supply and laying & fixing np-3, 650mm diahumepipeandincluding all material, labour, labour cess, t&p royalty, all tasex, bitumen ect. complete as per direction by i-in-c but excluding g.s.t. 14 struck pointing with cement mortar consisting of 1 part cement and 2 part of the fine sand of 1.25 finenes modulus on brick work andincluding all material, labour, labour cess, t&p royalty, all tasex, bitumen ect. complete as per direction by i-in-c but excluding g.s.t. 15 concrete with 2 cm guage stone grit instead4cm guage stone ballastoffine sand of 1.25 f.m and cement in proportion of 1:2:4 in foundation and under floorsandincluding all material, labour, labour cess, t&p royalty, all tasex, bitumen ect. complete as per direction by i-in-c but excluding g.s.t.(si no- 279 a) 16 mantinance part a @ 7.50 % 17 maintenance of constructed bituminous road next five year after completion the contractor shall be paid total maintenance cost 7.5% of tender civil cost for five year in the form of instalment as below. the payment shall be inclusive of cess but excluding gst payment shall be done as per satisfaction of engineer in charge regarding maintenance work carried out by contractor (including cess and excluding gst)for 1st year 0.00% 18 item no. 17but for 2nd year 0.75% 19 item no. 17but for 3rd year 1.50% 20 item no. 17 but for 4th year 2.25% 21 item no. 17 but for 5th year 3.00%
View Original Notice/Document
Result Documents
Tender Documents
Download File Name File Description
Download 0d062d9e-0048-44b3-8a40-b1194cc6105c
Download 362
Download boqcomparativechart
Download finance_1815384
Download finsummary_1815384
Download technical_1815384
Download techsummary_1815384
Download File Name File Description
Download 214959bb-e07d-490f-9170-a2249e198173 Tender Documents
Download BOQ_1815384 Tender Documents
Download Tendernotice_1 Tender Documents
Download T_2 Tender Documents
Disclaimer

We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender

✦ ✦ ✦
Awarded Bidder(s)
1
cnet-technologies
Rank : L1 (Lowest)
Bid Amount : ₹ 1,00,00,000