BRR : 7173875
Click Here To View Tendering Authority. Aoc City/State :  khurja, Uttar Pradesh
Tender Brief : Construction Of V.R.B. - Reconstruction work of bridge at Km 10.900 of Parauri Nala.Reconstruction work of bridge at Km 10.600 of Parauri Nala.Reconstruction work of bridge at Km 9.100 of Parauri Nala.Reconstruction work of bridge at Km 7.780 of Parauri Nala.Reconstruction work of bridge at Km 14.500 of Parauri Nala.Reconstruction work of bridge at Km 13.200 of Parauri Nala - Earth work in excavation by mechanical means (Hydraulic excavator) / manual means in foundationincluding dressing of sides and ramming of bottoms, for all lift, including getting out the excavated soil and disposal of su... Read More
Tender Value
35,00,000
Contract Value
₹ 26,16,590
Saving / Difference
₹ 8,83,410 ▲
Submission Date
12-02-2025
Contract Date
25-03-2025
Completion Date
120 days
Participated Bidder List
8 No of Bidder(s)
Sr No. Bidder Name Bid Analytics Technical Bid Financial Bid AOC Bid Value Rank
1 cnet-technologies Bid Analytics 33,09,805 L8
2 cnet-technologies Bid Analytics 28,90,020 L4
3 cnet-technologies Bid Analytics 27,43,110 L2
4 cnet-technologies Bid Analytics 28,16,690 L3
5 cnet-technologies Bid Analytics 30,10,867 L5
6 cnet-technologies Bid Analytics 31,86,225 L7
7 cnet-technologies Bid Analytics 30,26,594 L6
8 cnet-technologies Bid Analytics 26,16,590 L1
Work Detail
construction of v.r.b. - reconstruction work of bridge at km 10.900 of parauri nala.reconstruction work of bridge at km 10.600 of parauri nala.reconstruction work of bridge at km 9.100 of parauri nala.reconstruction work of bridge at km 7.780 of parauri nala.reconstruction work of bridge at km 14.500 of parauri nala.reconstruction work of bridge at km 13.200 of parauri nala - earth work in excavation by mechanical means (hydraulic excavator) / manual means in foundationincluding dressing of sides and ramming of bottoms, for all lift, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m. 2 providing and laying in position cement concrete of 1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 40 mm nominal size) excluding the cost of centering and shuttering. 3 providing and laying in position reinforcement cement concrete of 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size) excluding the cost of centering and shuttering. 4 providing and laying in position reinforcement cement concrete of 1:1.5:3 (1 cement : 1.5 coarse sand : 3 graded stone aggregate 20 mm nominal size) excluding the cost of centering and shuttering. 5 providing and laying c.c 1:1.5:3 with coarse sand and crushed stone aggregate with mechanical mixing including all cost of material, labour and t&p. 6 centering and shuttering for c.c. work including strutting, propping etc. and removal of form work for foundations, footings, base etc. below bed. 7 centering and shuttering for c.c. work including strutting, propping etc. and removal of form work for piers, abutments, pillars, above bed. 8 centering and shuttering for r.c.c. workincluding strutting, propping etc. and removal of form work. 9 supplying laying of one layer of tar felt i.s.i marked at the junction of wall and roof or any place i/c necessary overlap giving a coat of approved mastic paint below the tar felt i/c cost of all material ,labour and t&p. etc complete. 10 steel reinforcement for r.c.c. work including straightening, cutting, bending, placing position and binding all complete upto plinth level.thermo-mechanically treated (tmt)bars of grade fe-500d or more 11 supplying and filling ec bags with earth filled and placing in position with in 60 mtr distance for making bundh includingall cost of material, labour and t&p. etc. complete. 12 earth work in excavation by mechanical /manual including getting out and disposal of excavated earth lead upto 50 m and for all lift, as directed by engineer-in charge. 13 filling available excavated earth in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 and for all lift etc complete. 14 s/f 75mm dia upvc pipe(working pressure 4kg/ sqm) single socketed pipe 15 finishing with epoxy paint (two or more coats) at all locations prepared and applied as per manufacturer’s specifications including appropriate priming coat, preparation of surface, etc. complete. on concrete work. 16 dewatering by 10 h.p.pup set i/c all complete the work.
View Original Notice/Document
Result Documents
Tender Documents
Download File Name File Description
Download 9907c2de-7fbb-4d1a-bdbd-0a1a7cc69912
Download 79
Download boqcomparativechart
Download finance_1787818
Download finsummary_1787818
Download technical_1787818
Download techsummary_1787818
Download File Name File Description
Download Tendernotice_1 Tender Documents
Download b4b2b2a3-fe14-4d48-a8ba-0aebf8af6c1a Tender Documents
Download BOQ_1787818 Tender Documents
Disclaimer

We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender

✦ ✦ ✦
Awarded Bidder(s)
1
cnet-technologies
Rank : L1 (Lowest)
Bid Amount : ₹ 1,00,00,000