BRR : 6910524
Tender Brief : Reconstruction Of Aqueduct Trough From Km. 3.040 To Km. 3.600 Of Dihi Dy. - Dismantling of old & damaged reinforced cement concrete including removing and stacking of refuse as per directed by Engineer in charge. 2 C.R.Stone masonry in 1:3 cement sand mortar including cost of all material labor and T&P etc. 3 Centering and shuttering for concrete work including cost of all materials, labour and T&P etc. required for proper completion of work as per direction of Engineer in - charge. 4 Steel reinforcement in slab bed and wall including cutting bending, binding and placing in proper position... Read More
Tender Value
₹
1,87,20,000
Contract Value
₹ 1,67,22,447.86
Saving / Difference
₹ 19,97,552
▲
Submission Date
16-12-2024
Contract Date
03-03-2025
Completion Date
180 days
Participated Bidder List
2 No of Bidder(s)
| Sr No. | Bidder Name | Bid Analytics | Technical Bid | Financial Bid | AOC | Bid Value | Rank |
|---|---|---|---|---|---|---|---|
| 1 | cnet-technologies | Bid Analytics | 1,77,86,421.5 | L2 | |||
| 2 | cnet-technologies | Bid Analytics | 1,67,22,447.86 | L1 |
Work Detail
reconstruction of aqueduct trough from km. 3.040 to km. 3.600 of dihi dy. - dismantling of old & damaged reinforced cement concrete including removing and stacking of refuse as per directed by engineer in charge. 2 c.r.stone masonry in 1:3 cement sand mortar including cost of all material labor and t&p etc. 3 centering and shuttering for concrete work including cost of all materials, labour and t&p etc. required for proper completion of work as per direction of engineer in - charge. 4 steel reinforcement in slab bed and wall including cutting bending, binding and placing in proper position including cost of steel, binding wire, labour and t&p etc. 5 laying r.c.c. 1:1:2 (m-30) with cement, coarse sand, stone grit 4.75 to 20 mm in size including cost of all materials, labour, t&p etc. required for proper completion of work as per direction of engineer in charge. 6 p/l 22 gauge copper seal including of all materials, labour t&p etc. required for proper completion of work as per direction of engineer in - charge. 7 p/l water stop pvc seal including cost of all materials, labour t&p etc. required for proper completion of work as per direction of engineer in - charge. 8 p/l 24mm acrylic sheet including cost of all materials, labour t&p etc. required for proper completion of work as per direction of engineer in - charge.
View Original Notice/Document
Result Documents
Tender Documents
Disclaimer
We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender
✦ ✦ ✦
Awarded Bidder(s)
1
cnet-technologies
Rank : L1 (Lowest)
Bid Amount :
₹
1,00,00,000