BRR : 4562350
Click Here To View Tendering Authority. Aoc City/State :  AMBALAMEDU, Kerala
Tender Brief : Replacement Of Damaged Bottom Plate And Patch Work In Digestion Vessel 02 In Pa Plant , Fact Cd . , Replacement Of Damaged Bottom Plate And Patch Work In Digestion Vessel 02 In Pa Plant , Fact Cd . , Replacement Of Damaged Bottom Plate In Digestion Vessel 02 In Pap . Work Involves: Collect Required Tools And Tackles For The Work . Make Required Site Arrangement . The Existing 12 Mm Thick Ms Bottom Plates Shall Be Cut Removed Completely , As Required At Site To Meet With The Replacement Procedure . Temporary Re- Inforcement Members Shall Be Provided To The Bottom Plate And Shell ... Read More
Tender Value
Ref. Document
Contract Value
₹ 3,76,250
Submission Date
16-04-2020
Contract Date
09-05-2020
Completion Date
180 days
Participated Bidder List
6 No of Bidder(s)
Sr No. Bidder Name Bid Analytics Technical Bid Financial Bid AOC Bid Value Rank
1 cnet-technologies Bid Analytics 5,70,000 L5
2 cnet-technologies Bid Analytics 3,76,250 L1
3 cnet-technologies Bid Analytics 4,49,400 L2
4 cnet-technologies Bid Analytics 5,86,500 L6
5 cnet-technologies Bid Analytics 5,39,750 L4
6 cnet-technologies Bid Analytics 5,08,080 L3
Work Detail
replacement of damaged bottom plate and patch work in digestion vessel 02 in pa plant , fact cd . , replacement of damaged bottom plate and patch work in digestion vessel 02 in pa plant , fact cd . , replacement of damaged bottom plate in digestion vessel 02 in pap . work involves: collect required tools and tackles for the work . make required site arrangement . the existing 12 mm thick ms bottom plates shall be cut removed completely , as required at site to meet with the replacement procedure . temporary re- inforcement members shall be provided to the bottom plate and shell area of the tank . the shell shall be cut at a suitable distance from the top of the shell-to-bottom plate fillet weld such that the launder openings at the top are not misaligned with other vessels . the launder openings/nozzles shall be reworked if required to maintain the alignment by the contractor . the vertical shell bottom edges shall be ground properly with suitable bevel / double vee , where the welding is to be done . new bottom plate shall be fabricated out of 12mm thick ms plate . the plate shall be marked and cut as per relevant drawing to suit with the site condition . inside edge of the new cut plate shall be ground properly with suitable bevel / single vee , where the welding is to be done . the required backing strip plate shall be prepared from 6mm plate . the backing strip plate as required shall be full welded to the new 12mm thick cut plate . all bottom plate connection joint welds shall be full welded . the new 12mm thick cut plate with the backing strip plate shall be inserted / positioned properly with correct root gap . the vertical shell bottom edges shall be full welded [outside and inside] , to the newly replaced bottom plate with required fillet . shell-to bottom plate weld shall be full-penetration fillet weld . the newly welded all areas at inside of the storage tank shall be ground flush to facilitate rubber lining . after replacement of bottom plate , temporary re- inforcement members / plates shall be removed . damaged bottom plates and other scrap shall be transported to scrap yard . , patchwork on digestion vessel 02 shell: work involves: collect required materials from store . make site arrangements for the work including scaffolding . all the hv 09 encasings shall be cut and removed damaged/weak areas of dv 02 shell shall be cut and removed . necessary temporary supports shall be provided . patch work shall be done using 10mm thick ms plate . plates shall be cut , marked and rolled to suit the shell dia . fit up shall be done suitably . proper full welding at inside and out side of the joints and grinding of the welded area shall be done as per the instruction of officer in charge . dp test shall be done on weld joint and defects if any to be rectified . manholes/drain nozzles etc . shall be maintained as per original condition . existing manhole flanges and nozzles shall be used after necessary repair . weak areas near the launder nozzles shall be replaced with new plates . the nozzles shall be cut and removed for patch work . these nozzles shall be reused after repair . all welding joints inside and outside the shell shall be properly ground to facilitate rubber lining . , dismantling and refixing of existing launder between digestion vessel 01 and 03: make required site arrangements for work . the interconnection launder ( moc: ss 904l ) between dv 01 & dv 03 shall be dismantled suitably and removed from position to enable patchwork . the launder shall be cut and removed in segments if required as per site instruction . the cutting shall be plasma cutting only . necessary repairs shall be on the launder and its flanges as per site requirement . once the patchwork is complete the launder shall be erected back in position . the launder if cut , shall be erected with proper fit up and full welding of joints to be done . pad plates on the welding joints shall be provided . any rework on the launder to fit through the connecting flanges of dv 01 and 03 shall be done by the contractor . additional structural supports if required shall be provided . all the flange connection joints shall be properly tightened with gaskets to ensure leak proof joints . 1 no . quantity means dismantling and refixing both included . , dismantle , repair/modify/existing erect interconnection launders between digestion vessels 01 and 02 and digestion vessels 02 and 03: collect the required materials for the work . the launders shall be dismantled from the digestion vessels after site arrangements . the dismantled launders shall be repaired and modifies to suit the new flange orientation between dv 01&02 and dv 02&03 . patch works , repairs on the launder and its flanges shall be done as per site instructions . the modification of the launders shall be in such a manner that these shall be erected without any strain . the launders after rubber / brick lining shall be provided with hv 9 encasing inside with 300 mm extension towards downstream side on dv 02 and dv 03 . the launders shall be erected after getting clearance and serviced without any leak . dismantling of dv01-dv03 interconnection launder shall be in this scope of work . the dismantled launder shall be transported and stacked in earmarked area as per site instructions .
View Original Notice/Document
Result Documents
Tender Documents
Download File Name File Description
Download a7e386b8-33c2-4f31-823a-c0f60b56743f
Download File Name File Description
Download 797B34ED-70F7-466A-BC8E-55B14B27A03B Tender Documents - Tender Notice
Download Tendernotice_1 Tender Documents - NIT
Download BOQ_581707 Tender Documents - BOQ
Download SpecialConditions Tender Documents - Special conditions
Download TenderDocumentR1 Tender Documents - Tender documents
Disclaimer

We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender

✦ ✦ ✦
Awarded Bidder(s)
1
cnet-technologies
Rank : L1 (Lowest)
Bid Amount : ₹ 1,00,00,000