BRR : 1752317
Tender Brief : Work Of Business Plan Against Sanction Packages At Various Divisions 33 / 11 Kv S / S Under Edc-1 Agra.- 1 Carriage Of Following From 132 Kv Taj Agra To Work Related 33 / 11 Kv S / S Through The Kacha And Pakka Road Including The Work Of Its Loading And Unloading At The Respective Ends Including The Cost Of Arrangement Of Labour, T&P, Carrier Etc. Required For Proper Completion Of Work. ( Distance 00-50Kms. ) A ) Pcc Pole 8.5 Mtr. Long 2 Carriage Of Following From 132 Kv Taj Agra To Site Of Work Through The Kacha And Pakka Road Including The Work Of Its Loading And Unloading At The ... Read More
Tender Value
₹
1,70,000
Contract Value
₹ 1,28,841.6
Saving / Difference
₹ 41,158
▲
Submission Date
12-12-2022
Contract Date
13-05-2023
Completion Date
60 days
Participated Bidder List
3 No of Bidder(s)
| Sr No. | Bidder Name | Bid Analytics | Technical Bid | Financial Bid | AOC | Bid Value | Rank |
|---|---|---|---|---|---|---|---|
| 1 | cnet-technologies | Bid Analytics | 1,69,650 | L3 | |||
| 2 | cnet-technologies | Bid Analytics | 1,28,841.6 | L1 | |||
| 3 | cnet-technologies | Bid Analytics | 1,68,143 | L2 |
Work Detail
work of business plan against sanction packages at various divisions 33 / 11 kv s / s under edc-1 agra.- 1 carriage of following from 132 kv taj agra to work related 33 / 11 kv s / s through the kacha and pakka road including the work of its loading and unloading at the respective ends including the cost of arrangement of labour, t&p, carrier etc. required for proper completion of work. ( distance 00-50kms. ) a ) pcc pole 8.5 mtr. long 2 carriage of following from 132 kv taj agra to site of work through the kacha and pakka road including the work of its loading and unloading at the respective ends including the cost of arrangement of labour, t&p, carrier etc. required for proper completion of work. ( distance 00-50kms. ) c ) 400 / 250 kva t / f 3 carriage of following from 132 kv taj agra to site of work through the kacha and pakka road including the work of its loading and unloading at the respective ends including the cost of arrangement of labour, t&p, carrier etc. required for proper completion of work. ( distance 00-50kms. ) d ) 100 / 63 kva t / f 4 carriage of following from 132 kv taj agra to work related 33 / 11 kv s / s through the kacha and pakka road including the work of its loading and unloading at the respective ends including the cost of arrangement of labour, t&p, carrier etc. required for proper completion of work. ( distance 00-50kms. ) c ) line material viz. aerial bunch conductor / weasal conductor / dog, g.i. earth wire, cross arm, angle, channel, insulators, clamps and other line material, as required 5 installation of400 / 250 kva t / f on plinth in proper alignment by making its ht / lt side connections properly as per direction of superivsing engineer. 6 installation of100 / 63 kva t / f on plinth in proper alignment by making its ht / lt side connections properly as per direction of superivsing engineer. 7 dismentaling / removal of 250 kva t / f from existing double pole after opening ht / lt connections and their carriage work site to 132 kv taj store / je store agra including loading and unloading at both end. 8 dismentaling / removalof 63 / 25 / 10 kva t / f from existing double pole after opening ht / lt connections and their carriage work site to 132 kv taj store / je store agra including loading and unloading at both end. 9 erection and grouting of single pole on 8.5 mtr. long pcc poles in 1:2:4 ( cement sand, and bricks blast ) , including fixing ofaccessories for double pole s / s as per respo manual. 10 erection and grouting of double pole on 8.5 mtr. long pcc poles in 1:2:4 ( cement sand, and bricks blast ) , including fixing ofaccessories for double pole s / s as per respo manual. 11 making ht t off connection on existing mains labour, t &p and carrier etc. required for proper completion of work. 12 laying sagging stringing and binding and jumpering etc of in lt line as per respo manual and as per direction of supervising engineer. it includes the cost of labour, t & p, carrier etc reauired for proper completion of work. a ) ab conductor 3x50 / 3x95 sqmm. 13 erection and grouting of stays as per respo manual and as per direction of supervising engineer including the costof arrangement of labour, t&p, carrier etc. required for proper completion of work. grouting material i.e. cement, sand, brick ballast / stone ballast etc. shall be arranged by the contractor at his own cost. 14 fixing of earthing rod as per respo manual and as per direction of supervising engineer including the cost of arrangement of labour, t&p, carrier etc. required for proper completion of work. 15 laying sagging stringing and binding and jumpering etc of in lt line as per respo manual and as per direction of supervising engineer. it includes the cost of labour, t & p, carrier etc reauired for proper completion of work. a ) acsr weasel conductor
View Original Notice/Document
Result Documents
Tender Documents
Disclaimer
We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender
✦ ✦ ✦
Awarded Bidder(s)
1
cnet-technologies
Rank : L1 (Lowest)
Bid Amount :
₹
1,00,00,000
Similar Tenders Results