BRR : 11881646
Tender Brief : Tender for Providing Culvert At Tv Room Street Head Of Mulvoy Panchayat Span (1.5M) , Earth Work Excavation And Depositing On Bank With Initial Lead Of 10M Initial Lift Of 2M In Hard Stiff Clay Soil Etc Complete For Open Foundation As Per Ss 20 B , Plain Cement Concrete 1:4:8 Mix Using 40Mm Hbg Metal Including Cost And Conveyance Of All Materials And All Labour Charges For Mixing Laying And Compacting Etc. Complete , Supply And Erection Of Centering For All Plain Cement Concrete Item Including Cost And Conveyance Labour Charges Etc Complete , Supply And Erection Of Centering For All Plain Cem... Read More
Tender Value
₹
3,12,000
Contract Value
₹ 3,06,189.94
Saving / Difference
₹ 5,810
▲
Submission Date
09-02-2026
Contract Date
18-08-2026
Completion Date
180 days
Participated Bidder List
2 No of Bidder(s)
| Sr No. | Bidder Name | Bid Analytics | Technical Bid | Financial Bid | AOC | Bid Value | Rank |
|---|---|---|---|---|---|---|---|
| 1 | cnet-technologies | Bid Analytics | 3,06,315.02 | L2 | |||
| 2 | cnet-technologies | Bid Analytics | 3,06,189.94 | L1 |
Work Detail
tender for providing culvert at tv room street head of mulvoy panchayat span (1.5m) , earth work excavation and depositing on bank with initial lead of 10m initial lift of 2m in hard stiff clay soil etc complete for open foundation as per ss 20 b , plain cement concrete 1:4:8 mix using 40mm hbg metal including cost and conveyance of all materials and all labour charges for mixing laying and compacting etc. complete , supply and erection of centering for all plain cement concrete item including cost and conveyance labour charges etc complete , supply and erection of centering for all plain cement concrete item including cost and conveyance labour charges etc complete , cement concrete 1:3:6 mix using 20mm metal including cost and conveyance of all materials to work site and all labour charges etc. , supply and fabrication of steel for reinforced cement concrete items including cost and conveyance of binding wire, etc., complete , reinforced cement concrete 1:1.5:3 mix using 20 mm iss sine hbg metal including cost and conveyace of all materials and all labour charges,etc, , gst amount for providing service to government contract works for the above construction & maintenance works. { gst amount is the total gst amount for overall quoted amount (both construction and maintenance) above this row in column bb for all works in this package} (refer clause 13.2 & 13.3 of section 2 of instruction to bidders (itb) of sbd)
View Original Notice/Document
Result Documents
Tender Documents
| Download | File Name | File Description |
|---|---|---|
| Download | 8f76f1fe-48ce-4539-8e05-bab5ef56cf7e | financialevaluation notice |
| Download | boqcomparativechart | document |
| Download | finsummary_780609 | document |
| Download | techsummary_780609 | document |
| Download | c6cfda34-9f04-4b67-a0e9-9cbe741c1479 | result notice |
| Download | AOC | document |
Disclaimer
We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender
✦ ✦ ✦
Awarded Bidder(s)
1
cnet-technologies
Rank : L1 (Lowest)
Bid Amount :
₹
1,00,00,000