BRR : 11588377
Tender Brief : Tender for Charges For Dismantling The Cooling Water Pump Motor From Motor Stool Assembly, Moving To Repair Bay And Positioning On The Spare Motor Stool Assembly. Again Lifting And Moving Towards The Cooling Water Pump, Positioning And Reassembling The Motor After Completion Of Cooling Water Pump Overhaul Works. , Charges For Dismantling The Flexible Coupling Assembly, Lock Nut, Bearing Plate, Thrust Bearing, Cooling Coil & Its Cooling Coil Water Lines And Bearing Oil Pan. Cleaning And Inspection Of The Components, Bearing, Renewing The Worn-Out Components And Reassembling Of Cooling Water Pu... Read More
Tender Value
₹
Ref. Document
Submission Date
09-03-2026
Participated Bidder List
2 No of Bidder(s)
| Sr No. | Bidder Name | Bid Analytics | Technical Bid | Financial Bid | AOC | Bid Value | Rank |
|---|---|---|---|---|---|---|---|
| 1 | cnet-technologies | Bid Analytics | 7,05,552 | L1 | |||
| 2 | cnet-technologies | Bid Analytics | 7,27,318 | L2 |
Work Detail
tender for charges for dismantling the cooling water pump motor from motor stool assembly, moving to repair bay and positioning on the spare motor stool assembly. again lifting and moving towards the cooling water pump, positioning and reassembling the motor after completion of cooling water pump overhaul works. , charges for dismantling the flexible coupling assembly, lock nut, bearing plate, thrust bearing, cooling coil & its cooling coil water lines and bearing oil pan. cleaning and inspection of the components, bearing, renewing the worn-out components and reassembling of cooling water pump. , charges for dismantling of motor stool with pump components of thrust block, discharge elbow, drive shaft, element - iii & ii, intermediate shaft top half coupling, intermediate shaft, element - i, pump shaft half coupling, pump casing, bearing housing, pump shaft with impeller, suction bell mouth assembly, bell mouth liner, etc of cooling water pump. , charges for cutting and removal of existing worn-out shaft sleeves (ss) in impeller shaft bottom / impeller shaft top / intermediate shaft / drive shaft stuffing box sleeve and assembling of new sleeves by gas flame heating. of cooling water pump. , charges for lifting of impeller along with pump shaft, setting to the impeller stand, removing the impeller from the pump shaft by using hydraulic jack and gas flame heating over the impeller stem portion and reassembling of existing/new impeller with existing / new pump shaft and finally tightening of impeller lock nut and deflector with s.s. allen screws and tag welding of cooling water pump. , after completion of overhaul works, charges for measuring overall lift, providing correct lift and locking with lock nut. alignment of cooling water pump with motor after tightening of motor bed bolts and finally observation and attending of minor defects noticed during trial run of cooling water pump. , charges for loading and unloading the shafts and bushes . cooling water pump capaci
View Original Notice/Document
Result Documents
Tender Documents
Disclaimer
We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender
Financial Evaluation In Progress
Financial bids are currently under review. Awarded bidder information will be published after final evaluation.
PriceBid
Similar Tenders Results