BRR : 10225889
Click Here To View Tendering Authority. Price Bid City/State :  baraut, Uttar Pradesh
Tender Brief : Tender For Breakdown Of 33 Kv And 11 Kv Lines In Future Due To Natural Calamity In The Area Of ​​Sub-Division Fifth Baraut Under Power Distribution Division Ii Baraut Work Related To-1 , Lt / Ht On Site For Replacement Of Broken Damaged Pcc / Stp, Loading Of Pole From Storage Center / Baghpat / Meerut / Reaching The Site, Erecting Pole By Digging Pit, Hanging The Wires By Applying Clamp, Cross Arm, Insulator Etc. On The Pole | Switch On The Power Supply. 2 , New Pole ( Pcc / Stp ) For Installation Of Low Hanging Wires / Av Cables At Site Loading / Transportation Of Pole... Read More
Tender Value
Ref. Document
Submission Date
13-06-2023
Participated Bidder List
3 No of Bidder(s)
Sr No. Bidder Name Bid Analytics Technical Bid Financial Bid AOC Bid Value Rank
1 cnet-technologies Bid Analytics 2,01,500 L2
2 cnet-technologies Bid Analytics 2,02,000 L3
3 cnet-technologies Bid Analytics 1,99,500 L1
Work Detail
tender for breakdown of 33 kv and 11 kv lines in future due to natural calamity in the area of ​​sub-division fifth baraut under power distribution division ii baraut work related to-1 , lt / ht on site for replacement of broken damaged pcc / stp, loading of pole from storage center / baghpat / meerut / reaching the site, erecting pole by digging pit, hanging the wires by applying clamp, cross arm, insulator etc. on the pole | switch on the power supply. 2 , new pole ( pcc / stp ) for installation of low hanging wires / av cables at site loading / transportation of pole from storage center to site erection of pole, clamp on pole, cross arm, insulator etc. to start the power supply by continuously hanging the wires. 3 , pole repair work by welding additional channel / angle / iron strip to st pole ( 04 m / 11 m / 13 m ) damaged due to corrosion etc. near the ground near the site. ( required | channel / angle / strip to be paid by the tenderer ) 4 loose wire / ab cable / new wire ( lt line / vt line ) pull-tightening per span and maintaining safe ground clearance. 5 to straighten the polo by pulling it diagonally when the soil / boulder / packing. work of straightening the pole by filling and tightening the staywire. 6 the work of starting power supply from clear line by cutting / pruning the branches of trees covered on lt / 11 kv / 33 kv line. 7 , 02 nos pole, stay bear and other fittings for double pole construction. transporting the material from the storage center to the work place ( including loading and unloading ) , erecting poles by digging pits and fitting double | pole preparation ( decentralized material to be paid by the tenderer )
View Original Notice/Document
Result Documents
Tender Documents
Download File Name File Description
Download 2dbdd3fc-9aa2-4be0-aa7d-77c6e3745591 financialevaluation notice
Download boqcomparativechart boq document
Download finance_1356739 aoc document
Download finsummary_1356739 aoc document
Download File Name File Description
Download 5f3360fe-e422-418f-be29-16fefea19cb0 Tender Documents
Download BOQ_1356739 Tender Documents
Download Tendernotice_1 Tender Documents
Disclaimer

We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender

Financial Evaluation In Progress

Financial bids are currently under review. Awarded bidder information will be published after final evaluation.

PriceBid
Similar Tenders Results
TenderDetail
Loading tenders