Metallurgical Industries sector projects by Vedanta Ltd in Navelim village
Project Information
6953
Vedanta Ltd
Goa Investment Promotion Board (GIPB) has granted in-principle approval to various proposals by Vedanta Ltd for the expansion of existing capacities at its pig iron plant (PIP).
The company had submitted a proposal for the enhancement of its pig iron, coke, sinter and power plant at Navelim village, about 30 km from here, a senior GIPB member told PTI.
The company has sought expansion of its pig iron capacity by 0.45 mtpa from the existing 0.74 mtpa.
When commissioned, the company will achieve additional 61 per cent increase in pig iron capacity, he said.
GIPB, which met under the chairmanship of Chief Minister Laxmikant Parsekar, had last evening granted approval to various proposals by Vedanta along with several other projects, including starred hotels and industrial expansions.
Vedanta has also proposed the expansion of sinter plant at its PIP facility to cater to the requirement of sinter feed for the new blast furnaces which will result in 50 per cent capacity increase.
The company also plans to increase its power generation by 30 MW capacity (addition of 33 per cent to existing capacity) after the expansion of non-recovery coke oven plant which is a raw material to generate electricity.
Project Value
Refer document
Clearances Approved
Navelim village
Goa
India
Metallurgical Industries
Disclaimer :