Tender For Mtps-I - Tm-I - Breakdown Maintenance Work In Main Turbine & Its Auxiliaries In Unit-I To Iv For A Period Of One Year During 2026-27 As And When Required Basis.
Tender Value
Ref. Documents
Estimated cost
Bid Submission
09 Dec 2026
11 days left
EMD
15600
Bank guarantee accepted
Document Fee
Ref. Documents
Non-refundable
Tender Type
Online
Tender Overview
Organization
Tender ID
Competition Type
NCB
Bidding Type
Tender
Location / State
Salem → Tamil Nadu
EMD Exemption
Available
Quantity
Not Available
Website
Contact Person
Address
Project Description
Tender for Mtps-I - Tm-I - Breakdown Maintenance Work In Main Turbine & Its Auxiliaries In Unit-I To Iv For A Period Of One Year During 2026-27 As And When Required Basis.
BOQ
| Sl. No. | Item Description |
| 1 | Dismantling, overhauling and assembling of HP & IP control valve columns. Dismantling the control valve columns after loosening the bolts, dismantling its liners, spring assembly liner sliding pin, dismantling the roller bearings, cleaning the above items, inspection of liner key way and measuring the dimension, welding and grinding to the dimension required, greasing the bearing, assembling the dismantled parts and setting the roller clearance as per the direction of engineer in charge. |
| 2 | Dismantling, inspection, and changing of HP & IP control valves: Cutting the spindle leak off lines, heating the cap nut of steam chest by gas, dismantling the control valve assembly from steam chest, cleaning of all parts removal of steam strainer and cleaning spare valve and valve seat lapping and checking blue matching, steam chest flange lapping and blue matching, checking valve stem and liner clearance, valve stem DYE penetrant checking etc., a). Dismantling the control valve assembly from steam chest, cleaning of all parts, removal of steam strainer and cleaning spare valve and valve seat lapping and checking blue matching, Assembling the spare valve with steam chest and tightening the cap nut etc., checking Idle lift connecting the spindle leak off lines and welding as per the direction of the Engineer-in- charge. |
| 3 | b). Drilling the hole in the stem for providing spilt pin, providing the split pin, checking the washer clearance, checking valve lift etc. |
| 4 | Dismantling front pedestal cover, overhauling of main oil pump, intermediate pilot valve, Speed load control assembly, Differentiator, EGPV, turbine trip switch, CVSM feed pack pilot Control pilot & over speed striker. Dismantling of front bearing pedestal top cover, disconnecting the oil pipe lines, dismantling the gear coupling inspection & rectification dismantling of main oil pump, rotor float checking, side and top oil clearance checking. Inspection of impeller, wear ring clearance checking inspection of bearings and doing correction works, replacement of bearings, gear coupling if required. MOP & HP rotor alignment checking and correcting the same and assembling the gear coupling and MOP cover. Dismantling the MOP NRV, lapping and blue matching and assembling, Dismantling, cleaning, inspection and assembling of follow pilot, summation pilot, load/speed control pilot, speeder gear assembly, EGPV, intermediate pilot, differentiator, CVSM feedback pilot etc., Speed governor sleeve to nozzle, EGPV lever to over speed striker to rubber. |
| 5 | Dismantling the bearing cover, checking the bearing interference and assembling after C & I work: Dismantling the bearing cover by loosening the cap nuts, checking the bearing to cover Interference attending correction if any and assembling after cleaning the parting plane and after completion of C & I works. |
| 6 | Checking the hot governing characteristics and adjusting the valve openings as per the instruction of Engineer in-charge including tools and tackles. |
| 7 | Dismantling of oil inlet and outlet pipe lines to centrifuge, dismantling of motor, break drum, bowl assembly and pump assembly. Cleaning, inspection, Renewal of damaged spares, bearings, oil seals and assembling, successful commissioning of the Alfa Laval centrifuge. |
| 8 | Cleaning of Oil line, renewal of oil line gaskets and painting etc, in Alfa Laval centrifuge. |
| 9 | Charges for Dismantling of inlet and outlet oil lines connected to oil pumps and heater tank & cleaning etc., in Pennwalt centrifuge. |
| 10 | Charges for dismantling of Suction pump assembly, cleaning all internals, renewal of Bearings, oil seals, oil gaskets and assembling etc., in Pennwalt centrifuge. |
| 11 | Charges for dismantling of discharge pump assembly, cleaning all internals, renewal of Bearings, oil seals, oil gaskets and assembling etc., in Pennwalt centrifuge. |
| 12 | Charges for Dismantling Centrifuge Belt guard, centrifuge Bowl assembly, bottom feed nozzle assembly, idler arm assembly, bearing complete assembly, cleaning, inspection, renewal of bearings, gaskets, bushes and assembling work etc., in Pennwalt centrifuge. |
| 13 | Charges for renewal of existing oil line valves, gaskets and assembling of oil lines etc., in Pennwalt centrifuge. |
| 14 | Turbine Lub Oil Cooler - Attending Tube PunctureDismantling of top water box, cleaning of all tubes, lifting & hydraulic testing of tube nest, plugging of punctured tubes, cleaning of top and bottom water box, cleaning of all flange seating areas, providing new oil and water gaskets, assembling and tightening of all parts. |
| 15 | Draining of oil from TLOC, shifting oil barrels, top up oil to MOT through centrifuge etc. |
| 16 | Seal Oil Cooler - Attending Tube Puncture Draining of oil from SOC, shifting oil barrels, after attending hydraulic testing of tube nest top up oil to MOT through centrifuge etc. |
| 17 | Attending tube puncture in Seal oil coolers: Dismantling of top water box, brush cleaning of all tubes, hydraulic testing of tube nest, plugging of punctured tubes, cleaning of top and bottom water box, cleaning of all flange seating areas, providing new oil and water gaskets, assembling and tightening of all parts and charging of oil & water side etc. |
| 18 | Inspection and cleaning of ESV/IV Pilot valve includes checking the necessary clearances in the pilots with liners and assembling with renewal of worn-out spares. |
| 19 | Flushing of ESV/IV cooling water hoses and checking leakages if any. |
| 20 | Renewal of LPT diaphragm. Removal of old gasket, cutting new gasket to the existing contour and renewing the new gasket and complete tightening of outer rings. |
| 21 | Inspection of coupling, Bearing and mechanical seal in AC lub Oil/ DC/ AC/DC seal oil pumps. Dismantling of bearing and mechanical seal assembly and renewal if required and assembling. |
| 22 | Renewal of Serrated Gasket in HP/IP Transfer Pipe: a). Cutting & Removal of spindle leak off lines, dismantling of flange joint of steam transfer pipe to HP/ IP top control valve , removal of old gasket, providing of gasket, tightening of the flange joint, welding of spindle leak off lines. Drive End/Heater Drip Pump/ Model: NU 411 Please Enable Macros to View BoQ information |
AI Tender Summary
Tender Timeline
Nov 25, 2026
11:30 IST
Tender Published
Tender notice published.
CompletedDec 09, 2026
17:00 IST
Bid Submission Deadline
Online submission via eProcurement portal.
Upcoming · 11 daysDec 10, 2026
Bid Opening Date
Technical bids will be opened and evaluated.
Upcoming · 12 daysTender Documents
Download All (ZIP) ↓
Disclaimer
We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender