Tender For Cleaning, Dry Inspection Repair, Hydraulic Test, Fitting And Commissioning Of Vertical Boiler No Wbl/10149 And 9658 At South Samla No. 1 And 2 Pit Under Msam Colliery
Tender Value
3.63 Lakhs
Estimated cost
Bid Submission
04 Dec 2026
6 days left
EMD
4600
Bank guarantee accepted
Document Fee
Ref. Documents
Non-refundable
Tender Type
Online
Tender Overview
Organization
Tender ID
Competition Type
NCB
Bidding Type
Tender
Location / State
Paschim Bardhaman → West Bengal
EMD Exemption
Not Available
Quantity
Not Available
Website
Contact Person
Address
Project Description
Tender for Cleaning, Dry Inspection Repair, Hydraulic Test, Fitting And Commissioning Of Vertical Boiler No Wbl/10149 And 9658 At South Samla No. 1 And 2 Pit Under Msam Colliery
BOQ
| Sl. No. | Item Description |
| 1 | CLEANING, DRY INSPECTION REPAIR, HYDRAULIC TEST, FITTING & COMMISSIONING OF VERTICAL BOILER NO – WBL/10149 & 9658 AT SOUTH SAMLA NO. 1 & 2 PIT UNDER MSAM COLLIERY. (Inclusive of EPF/CMPF) |
| 2 | CLEARING OF ASH FROM THE BOTTOM OF THE BOILER |
| 3 | CLEARING OF ASH FROM THE BOTTOM OF THE BOILER |
| 4 | CLEANING OF ALL THE SCALE & RUST FROM THE BOILER SHELL PLATE AT FIRE SIDE & WASHING OF THE SAME |
| 5 | CLEANING OF ALL THE SCALE & RUST FROM THE BOILER SHELL PLATE AT FIRE SIDE & WASHING OF THE SAME |
| 6 | CLEANING OF SCALE FROM THE BOILER SHELL PLATE, SCRAPING, REMOVING OF ALL THE FOREIGN MATERIALS, WASHING OF THE SAME AT WATER SIDE |
| 7 | CLEANING OF SCALE FROM THE BOILER SHELL PLATE, SCRAPING, REMOVING OF ALL THE FOREIGN MATERIALS, WASHING OF THE SAME AT WATER SIDE |
| 8 | DISMANTLING OF ALL THE VALVES, FIRE BAR & ALL THE INSPECTION DOOR, CLEANING & DEPOSIT THE SAME AT COLLIERY WORKSHOP |
| 9 | DISMANTLING OF ALL THE VALVES, FIRE BAR & ALL THE INSPECTION DOOR, CLEANING & DEPOSIT THE SAME AT COLLIERY WORKSHOP |
| 10 | CONDUCTING THE DRY INSPECTION OF THE BOILER BY THE DY DIRECTOR OF BOILER DURGAPUR |
| 11 | TO BUILD UP THE PITTED PORTION OF BOILER SHELL CROWN BY ARC WELDING & GRIND SMOOTH AS MARKED OUT DURING INSPECTION |
| 12 | TO BUILD UP THE PITTED PORTION OF BOILER SHELL CROWN BY ARC WELDING & GRIND SMOOTH AS MARKED OUT DURING INSPECTION |
| 13 | TO BUILD UP THE PITTED PORTION OF BOILER SHELL CROWN BY ARC WELDING & GRIND SMOOTH AS MARKED OUT DURING INSPECTION |
| 14 | TO BUILD UP THE UPTAKE TUBE OF THE BOILER BY ELECTRIC ARC WELDING & DRESSING TO BE DONE BY GRINDING TO REGAIN ITS ORIGINAL CONTOUR |
| 15 | TO BUILD UP THE UPTAKE TUBE OF THE BOILER BY ELECTRIC ARC WELDING & DRESSING TO BE DONE BY GRINDING TO REGAIN ITS ORIGINAL CONTOUR |
| 16 | TO BUILD UP THE UPTAKE TUBE OF THE BOILER BY ELECTRIC ARC WELDING & DRESSING TO BE DONE BY GRINDING TO REGAIN ITS ORIGINAL CONTOUR |
| 17 | CHANGING THE DEFECTIVE BURN OUT FUSE PLUG; THREAD MAKING OF BORE HOLE OF SHELL CROWN PLATE ETC. |
| 18 | CHANGING THE DEFECTIVE BURN OUT FUSE PLUG; THREAD MAKING OF BORE HOLE OF SHELL CROWN PLATE ETC. |
| 19 | CHANGING THE DEFECTIVE BURN OUT FUSE PLUG; THREAD MAKING OF BORE HOLE OF SHELL CROWN PLATE ETC. |
| 20 | OVERHAULING, LAPPING & NECESSARY REPAIR OF ALL THE VALVES WITH SUPPLY & FITTING OF 2 SETS OF BUSH FOR GAUGE COLUMN COCK |
| 21 | OVERHAULING, LAPPING & NECESSARY REPAIR OF ALL THE VALVES WITH SUPPLY & FITTING OF 2 SETS OF BUSH FOR GAUGE COLUMN COCK |
| 22 | OVERHAULING, LAPPING & NECESSARY REPAIR OF ALL THE VALVES WITH SUPPLY & FITTING OF 2 SETS OF BUSH FOR GAUGE COLUMN COCK |
| 23 | TO BUILD UP THE MANHOLE CROSS TUBE DOOR & GRIND SMOOTH TO MAKE SPIGOT CLEARANCE |
| 24 | TO BUILD UP THE MANHOLE CROSS TUBE DOOR & GRIND SMOOTH TO MAKE SPIGOT CLEARANCE |
| 25 | TO BUILD UP THE MANHOLE CROSS TUBE DOOR & GRIND SMOOTH TO MAKE SPIGOT CLEARANCE |
| 26 | CHANGING OF ALL THE STUDS OF MUDHOLE DOOR BY GAS CUTTING & FITTING NEW HT STUDS BY ARC WELDING |
| 27 | CHANGING OF ALL THE STUDS OF MUDHOLE DOOR BY GAS CUTTING & FITTING NEW HT STUDS BY ARC WELDING |
| 28 | CHANGING OF ALL THE STUDS OF MUDHOLE DOOR BY GAS CUTTING & FITTING NEW HT STUDS BY ARC WELDING |
| 29 | COST OF NEW HT STUD (3/4\\" × 6\\") LONG WITH WASHER |
| 30 | SUPPLY OF BQ BOILER PLATE (250 × 4500 × 8 × 8) |
| 31 | SUPPLY OF MS ANGLE (65 × 65 × 6) |
| 32 | BINDING OF BQ PLATE AND MS ANGLE |
| 33 | BINDING OF BQ PLATE AND MS ANGLE |
| 34 | GAS CUTTING OF BOILER SHELL PLATE AND ANGLE FROM BOILER BODY |
| 35 | GAS CUTTING OF BOILER SHELL PLATE AND ANGLE FROM BOILER BODY |
| 36 | FABRICATION AND FITTING OF SHELL EXTENSION PLATE AND ANGLE OF BOILER |
| 37 | FABRICATION AND FITTING OF SHELL EXTENSION PLATE AND ANGLE OF BOILER |
| 38 | WELDING OF NEW BQ PLATE AND ANGLE WITH BOILER BODY |
| 39 | WELDING OF NEW BQ PLATE AND ANGLE WITH BOILER BODY |
| 40 | COST OF LOW HYDROGEN ELECTRODE, OXYGEN AND DA |
| 41 | SUPPLY & FITTING OF 3/4\\" GAUGE GLASS TUBE, 18\\" LONG |
| 42 | HYDRAULIC TEST OF V/BOILER WITH BLANKING & WATER FILLING & CONDUCTING THE INSPECTION |
| 43 | HYDRAULIC TEST OF V/BOILER WITH BLANKING & WATER FILLING & CONDUCTING THE INSPECTION |
| 44 | HYDRAULIC TEST OF V/BOILER WITH BLANKING & WATER FILLING & CONDUCTING THE INSPECTION |
| 45 | COMPLETE FITTING OF V/BOILER WITH ALL FITTINGS |
| 46 | COMPLETE FITTING OF V/BOILER WITH ALL FITTINGS |
| 47 | COMPLETE FITTING OF V/BOILER WITH ALL FITTINGS |
| 48 | FABRICATION OF FIRE BAR WITH DA/OXYGEN |
| 49 | FABRICATION OF FIRE BAR WITH DA/OXYGEN |
| 50 | FABRICATION OF FIRE BAR WITH DA/OXYGEN |
| 51 | SUPPLY OF F-NUTS, BOLTS, TAP JOINT, STEAM JOINT ETC. |
| 52 | COMMISSIONING OF BOILER WITH ALL PREPARATION FOR FIRING OF THE BOILER & 48 HOURS' OBSERVATION |
| 53 | COMMISSIONING OF BOILER WITH ALL PREPARATION FOR FIRING OF THE BOILER & 48 HOURS' OBSERVATION |
| 54 | Total impact of GST for the purpose of CTC Please Enable Macros to View BoQ information |
AI Tender Summary
Tender Timeline
Nov 24, 2026
11:30 IST
Tender Published
Tender notice published.
CompletedDec 04, 2026
17:00 IST
Bid Submission Deadline
Online submission via eProcurement portal.
Upcoming · 6 daysDec 05, 2026
Bid Opening Date
Technical bids will be opened and evaluated.
Upcoming · 7 daysTender Documents
Download All (ZIP) ↓
Disclaimer
We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender