Tender For Replacement Of Various Drive Motors In Np And Off Site Area, Fact Cd
Tender Value
Ref. Documents
Estimated cost
Bid Submission
09 Dec 2026
13 days left
EMD
12000
Bank guarantee accepted
Document Fee
Ref. Documents
Non-refundable
Tender Type
Online
Tender Overview
Organization
Tender ID
Competition Type
NCB
Bidding Type
Tender
Location / State
Ernakulam → Kerala
EMD Exemption
Available
Quantity
Not Available
Website
Contact Person
Address
Project Description
Tender for Replacement Of Various Drive Motors In Np And Off Site Area, Fact Cd
BOQ
| Sl. No. | Item Description |
| 1 | Replacement of various Drive Motors in NP & Off site area, FACT CD. |
| 2 | Replacement of Motor of dryer A or B in N P Plant.Work involves: The required site arrangements shall be done for the replacement of motor of dryer A or B in NP plant. The tools and tackles shall be arranged. Foundation bolts of the existing motor shall be loosened / removed and lead / transported to electrical work shop. The new / spare motor shall be transported to site. The motor shall be kept in position and insert the foundation bolts, after cleaning the base plate. Rigging assistance shall be provided for the coupling / decoupling and alignment of motor. |
| 3 | Replacement of Motor of Product cooler A or B in N P Plant.Work involves: The required site arrangements shall be done for the replacement of motor of Product cooler A or B in NP plant. The tools and tackles shall be arranged. Foundation bolts of the existing Product cooler motor shall be loosened / removed and lead / transported to electrical work shop. The new / spare motor shall be transported to site. The motor shall be kept in position and insert the foundation bolts, after cleaning the base plate. Rigging assistance shall be provided for the coupling / decoupling and alignment of motor. |
| 4 | Replacement of Motor of Granulator A or B in N P Plant.Work involves: The required site arrangements shall be done for the replacement of motor of Granulator A or B in NP plant. The tools and tackles shall be arranged. Foundation bolts of the existing Granulator motor shall be loosened / removed and lead / transported to electrical work shop. The new / spare motor shall be transported to site. The motor shall be kept in position and insert the foundation bolts, after cleaning the base plate. Rigging assistance shall be provided for the coupling / decoupling and alignment of motor. |
| 5 | Replacement of Motor of vibrator screen, A or B stream in N P Plant.Work involves: The required site arrangements shall be done for the replacement of motor of vibrator screen A or B stream in NP plant. The tools and tackles shall be arranged. Foundation bolts of the existing motor shall be loosened / removed and lead / transported to electrical work shop. The new / spare motor shall be transported to site. The motor shall be kept in position and insert the foundation bolts, after cleaning the base plate. The foundation / jack bolts shall be tightened properly. |
| 6 | Replacement of Motor of Scrubber Seal Tank (SS Tank), A or B stream in N P Plant.Work involves: The required site arrangements shall be done for the replacement of motor of Scrubber Seal Tank (SS Tank), A or B stream in NP plant. The tools and tackles shall be arranged. Belt guard and belts shall be removed. Foundation bolts of the existing motor shall be loosened / removed and lead / transported to electrical work shop. The new / spare motor shall be transported to site. The motor shall be kept in position and insert the foundation bolts, after cleaning the base plate. The foundation / jack bolts shall be tightened properly. Rigging assistance shall be provided for the coupling / decoupling and alignment of motor. |
| 7 | Replacement of Motor of Reactor, A or B stream in N P Plant.Work involves: The required site arrangements shall be done for the replacement of motor of Reactor, A or B stream in NP plant. The tools and tackles shall be arranged. Foundation bolts of the existing motor shall be loosened / removed and lead / transported to electrical work shop. The new / spare motor shall be transported to site. The motor shall be kept in position and insert the foundation bolts, after cleaning the base plate. The foundation / jack bolts shall be tightened properly. Rigging assistance shall be provided for the coupling / decoupling and alignment of motor. |
| 8 | Replacement of Motor of Fume Fan, Cooler Fan and Dryer Fan, A or B stream in N P Plant.Work involves: The required site arrangements shall be done for the replacement of motor of Fume Fan, Cooler Fan and Dryer Fan, A or B stream in NP plant. The tools and tackles shall be arranged. Foundation bolts of the existing motor shall be loosened / removed and lead / transported to electrical work shop. The new / spare motor shall be transported to site. The motor shall be kept in position and insert the foundation bolts, after cleaning the base plate. The foundation / jack bolts shall be tightened properly. Rigging assistance shall be provided for the coupling / decoupling and alignment of motor. |
| 9 | Replacement of Motor of Phosphoric acid day tanks (A, B, C & D), in N P Plant.Work involves: The required site arrangements shall be done for the replacement of motor of Phosphoric acid day tanks (A, B, C & D), in NP plant. The tools and tackles shall be arranged. Foundation bolts of the existing motor shall be loosened / removed and lead / transported to electrical work shop. The new / spare motor shall be transported to site. The motor shall be kept in position and insert the foundation bolts, after cleaning the base plate. The foundation / jack bolts shall be tightened properly. Rigging assistance shall be provided for the coupling / decoupling and alignment of motor. |
| 10 | Replacement of Motor of Crusher, A or B stream in N P Plant.Work involves: The required site arrangements shall be done for the replacement of motor of Crusher, A or B stream in NP plant. The tools and tackles shall be arranged. Belt guard and belts shall be removed. Foundation bolts of the existing motor shall be loosened / removed and lead / transported to electrical work shop. The new / spare motor shall be transported to site. The motor shall be kept in position and insert the foundation bolts, after cleaning the base plate. The foundation / jack bolts shall be tightened properly. Rigging assistance shall be provided for the coupling / decoupling and alignment of motor. |
| 11 | Replacement of Motor of RC / DD/ Product Elevator in N P Plant.Work involves: The required site arrangements shall be done for the replacement of motor of RC / DD/ Product Elevator in NP plant. The tools and tackles shall be arranged. Foundation bolts of the existing motor shall be loosened / removed and lead / transported to electrical work shop. The new / spare motor shall be transported to site. The motor shall be kept in position and insert the foundation bolts, after cleaning the base plate. The foundation / jack bolts shall be tightened properly. Rigging assistance shall be provided for the coupling / decoupling and alignment of motor. |
| 12 | Replacement of Motor of RC / SF Conveyor in N P Plant.Work involves: The required site arrangements shall be done for the replacement of motor of RC / SF Conveyor in NP plant. The tools and tackles shall be arranged. Foundation bolts of the existing motor shall be loosened / removed and lead / transported to electrical work shop. The new / spare motor shall be transported to site. The motor shall be kept in position and insert the foundation bolts, after cleaning the base plate. The foundation / jack bolts shall be tightened properly. Rigging assistance shall be provided for the coupling / decoupling and alignment of motor. |
| 13 | Replacement of Motor of Scrubber Liquor Pumps and Slurry Pumps, A or B stream in N P Plant.Work involves: The required site arrangements shall be done for the replacement of motor of Scrubber Liquor Pumps and Slurry Pumps, A or B stream in N P Plant. The tools and tackles shall be arranged. Foundation bolts of the existing motor shall be loosened / removed and lead / transported to electrical work shop. The new / spare motor shall be transported to site. The motor shall be kept in position and insert the foundation bolts, after cleaning the base plate. The foundation / jack bolts shall be tightened properly. Rigging assistance shall be provided for the coupling / decoupling and alignment of motor. |
| 14 | Replacement of Motor of DH Fan in N P Plant.Work involves: The required site arrangements shall be done for the replacement of motor of DH Fan in NP plant. The tools and tackles shall be arranged. Foundation bolts of the existing motor shall be loosened / removed and lead / transported to electrical work shop. The new / spare motor shall be transported to site. The motor shall be kept in position and insert the foundation bolts, after cleaning the base plate. The foundation / jack bolts shall be tightened properly. Rigging assistance shall be provided for the coupling / decoupling and alignment of motor. |
| 15 | Replacement of motor of various product conveyors in N P - Off site area.Work involves: The required site arrangements shall be done for the replacement of motor of product conveyors [ N1A / N2 A, N1B / N2B, N1C / N2C, N1D / N2D, N3, N4, N5, N6, N7 , N8, N9, N10, N11, N12, N13, N14, N15, N16, slat conveyors and lorry loading conveyors] in N P - Off site area. The tools and tackles shall be arranged. Foundation bolts of the existing gear box / motor shall be loosened / removed and lead / transported to mechanical / electrical work shop. The new / spare motor shall be transported to site. The gear box / motor shall be kept in position and insert the foundation bolts, after cleaning the base plate. The foundation / jack bolts shall be tightened properly. Rigging assistance shall be provided for the coupling / decoupling and alignment of motor. |
| 16 | Replacement of Motor of various equipments in N P - Off site area.Work involves: The required site arrangements shall be done for the replacement of motor of various equipments [ Cooling Water Pump, NH3 Transfer Pump, ammonia compressor / IAC at NH3 Handling, P2O5 transfer pumps, pit pump at acid terminal, Fume scrubber pumps, Glycol Coolant Pump and Dryer furnace fan, ASL pump, furnace oil pump, EOT Motors at NP Plant etc. ] in N P - Off site area. The tools and tackles shall be arranged. Foundation bolts of the existing motor shall be loosened / removed and lead / transported to electrical work shop. The new / spare motor shall be transported to site. The motor shall be kept in position and insert the foundation bolts, after cleaning the base plate. The foundation / jack bolts shall be tightened properly. Rigging assistance shall be provided for the coupling / decoupling and alignment of motor. |
| 17 | Replacement of Motor of Ammonia CompressorsWork involves: The required site arrangements shall be done for the replacement of motor of ammonia compressors in Offsite area. The tools and tackles shall be arranged. Foundation bolts of the existing motor shall be loosened / removed and lead / transported to electrical work shop. The new / spare motor shall be transported to site. The motor shall be kept in position and insert the foundation bolts, after cleaning the base plate. The foundation / jack bolts shall be tightened properly. Rigging assistance shall be provided for the coupling / decoupling and alignment of motor. Please Enable Macros to View BoQ information |
AI Tender Summary
Tender Timeline
Nov 24, 2026
11:30 IST
Tender Published
Tender notice published.
CompletedDec 09, 2026
17:00 IST
Bid Submission Deadline
Online submission via eProcurement portal.
Upcoming · 13 daysDec 10, 2026
Bid Opening Date
Technical bids will be opened and evaluated.
Upcoming · 14 daysTender Documents
Download All (ZIP) ↓
Disclaimer
We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender