Tender For Restoration Of Rain Damages On Pragpur To Lag Baliana Road Km.0/0 To 4/00 (Sh:- providing and laying Cement Concrete Pavement At Rd. 0/950 To 1/016).Under Pdna-2025
Tender Value
5.08 Lakhs
Estimated cost
Bid Submission
28 Nov 2026
2 days left
EMD
10200
Bank guarantee accepted
Document Fee
350
Non-refundable
Tender Type
Online
Tender Overview
Organization
Tender ID
Competition Type
NCB
Bidding Type
Tender
Location / State
Kangra → Himachal Pradesh
EMD Exemption
Not Available
Quantity
Not Available
Website
Contact Person
Address
Project Description
Tender for Restoration Of Rain Damages On Pragpur To Lag Baliana Road Km.0/0 To 4/00 (Sh:- providing and laying Cement Concrete Pavement At Rd. 0/950 To 1/016).Under Pdna-2025
BOQ
| Sl. No. | Item Description |
| 1 | Scarifying the existing bituminious road surface to a depth of 150 mm and disposal of scarified material complete as per drawing & Technical Specification Clause-301.4 and the entire satisfaction and direction of Engineer – in- Charge including carriage of materials within all leads, lifts and other incidental. The rates inclusive of octori, royality, Malkhana, toll taxes and any other taxes imposed excluding GST by the Government. |
| 2 | Construction of embankment with approved material obtained from borrow pits with all lift transporting to site, spreading, grading to required slope and compacting to meet requirement of Tables 300.1 and 300.2 with all lead as per Technical Specification Clause 301.5 and as per the entire satisfactions and directions of Engineer-in-Charge, including carriage of material within all leads, lifts and other incidentals. The rates inclusive of octori, royality, Malkhana, toll taxes and any other taxes imposed excluding GST by the Government. |
| 3 | Excavation in foundation, trenches etc. in earth work in all classification of soil such as pick work, jumper work, pick jumper work, blasting work, jumper blasting work, soft and hard blasting and saturated soil, de-watering, including wedging out rocks where blasting work is prohibited, chiseling or any other mixed variety of soil, including shoring, shuttering and pumping out water upto any depth or any quontam of water including slush which may be arise during de-watering removal of slush and stacking the serviceable and un-serviceable material clear from the edge of excavation as direction of Engineer-In-Charge and retuning the stacked soil in 15cm (Fifteen centimeter) layers, when required into plinths, sides of foundation etc; consolidating each deposited layer by ramming, watering and then disposing of all excavated earth as directed by the Engineer-in-Charge, within all leads, lifts of materials and other incidentals as per approved drawing, design and as directed by the Engineer-in-Charge. The rates inclusive of octori, royality, Malkhana, toll taxes and any other taxes imposed excluding GST by the Government. |
| 4 | Providing and laying mechanically mixed and vibrated cement concrete 1:4:8 (one cement isto four sand isto eight graded crushed stone aggregate 40mm (forty millimeter) nominal size) for plain cement concrete, in or under water in open foundation for all types of structures, including pumping or bailing out water/ dewatering (surface/sub-soil water) and including removal of slush which may arise at the time of laying under water for all heights/depth and any quantum of water including cost of form work and curing complete as per drawing and MORD technical specification 802, 803, 1202 & 1203 and as per the direction and the entire satisfaction of Engineer-in-Charge, including carriage of material with in all leads lifts and other incidentals. The rates inclusive of octori, royality, Malkhana, toll taxes and any other taxes imposed excluding GST by the Government. |
| 5 | Providing and laying mechanically mixed and vibrated plain/reinforced cement concrete pavement Grade-M-25 (M-Twenty five) design mix with minimum cement contents of 404 Kg (Four hundred four Kilogram) in open foundation as per drawing and MORD technical specification clause 802, 803, 1202 and 1203 including the cost of form work and curing complete but excluding cost of reinforcement for reinforced concrete work as per satisfaction and direction of Engineer-in-Charge, including carriage of materials up to all leads, lifts. The rates inclusive of octori, royality, Malkhana, toll taxes and any other taxes imposed excluding GST by the Government. |
| 6 | Providing and laying mechanically mixed and vibrated concrete for plain cement concrete nominal mix 1:3:6 (One cement isto three sand isto six graded crushed stone aggregate 20mm (twenty millimeter) nominal size), on ground or under water for all type of structure, in drain,edge wall and the like etcetera complete including pumping or bailing out water, dewatering (surface/sub soil water)including removal of slush which may arise at time of laying concrete for all heights/depths including cost of form work and curing complete for 14 (fourteen) days as per drawing and MORD Technical specification section 800, 900, 1200 and 1600 as per entire satisfaction and directions of Engineer-in-charge, including carriage of materials within all leads, lifts and other incidentals. The rates inclusive of octori, royality, Malkhana, toll taxes and any other taxes imposed excluding GST by the Government. Please Enable Macros to View BoQ information |
AI Tender Summary
Tender Timeline
Nov 23, 2026
11:30 IST
Tender Published
Tender notice published.
CompletedNov 28, 2026
17:00 IST
Bid Submission Deadline
Online submission via eProcurement portal.
Upcoming · 2 daysNov 28, 2026
Bid Opening Date
Technical bids will be opened and evaluated.