Bids Are invited for Maintenance And Pigging Service For Oil And Gas Pipelines - Piped Natural Gas; Utility Pigs; Cleaning Pig - Purging For Commissioing Of New Underground Pipeline With Nitrogen Supply Of Nitrogen Gas, Equipment, Manpower, Engineeri
Tender Overview
Project Description
Bids Are invited for Maintenance And Pigging Service For Oil And Gas Pipelines - Piped Natural Gas; Utility Pigs; Cleaning Pig - Purging For Commissioing Of New Underground Pipeline With Nitrogen Supply Of Nitrogen Gas, Equipment, Manpower, Engineering Support, And Monitoring Services Required To Safely Displace Residual Hydrocarbons/Air From The Pipeline And To Maintain The Pipeline Under A Dry, Inert, Low-Oxygen Atmosphere For The Duration Of The Mothball Period, In Accordance With Recognized Industry Standards And The Owners Technical Specifications. , Inertization Intertization Of Enitre Pipeline Of Length Of 55 Km By Nitrogen Filling Considering Volume For Approx. 4 Km Pipeline Length Of 16 Dia Pipe With Pigging & By Supply, Transportation And Delivery Of Liquid Nitrogen Along With Atmospheric Vaporizer , All Required Manpower, Machinery Etc. To Remove Air From The Pipeline. A 500 M Column Of N2 Shall Be Released In Pipeline , Then Foam Pig Shall Be Inserted & N2 Shall Be Released In The Pipeline Till The Pig Received At Other End .Notes:-(1) Inertization And Re-Commissioning Of Pipeline Shall Not Be Done By Nitrogen Cylinder Truck.(2) Acceptance Criteria For Completion Of Job Under This Sor Item Shall Be Attaining 0% Lel By Contractor.(3) Contractor To Quote Accordingly And Arrange Adequate Quantity Of Nitrogen Required To Successfully Complete The Job In All Aspects. , Purging For Commissioning Of 16 Pipeline Section Of Length Approx. 55 Km , Barricading , Providing & Erecting In Position A Barricading Structure Of 2.0 M Height And 2.5 M Width (Approx.). Using 0.8Mm Thick Corrugated Galvanized Steel Sheets Supported On Frame Of Structural Steel Conforming To Is:2062, Coated With Red Oxide Zinc Chromate Shop Primer, Including Submission Of Design & Drawing To Be Reviewed By Owner, Before Execution Of Work At Pipeline Route, Particularly In Residential Area And High Movement Area And As Advised By Engineer In Charge, Removal Of Barricading Structure After Completion Of Work, Dressing & Trimming Of The Area. All Complete As Per Specification & Direction Of Engineer In Charge (All Materials To Be In Contractors Scope)Note:1. These Rates Shall Be Applied Only When Explicitly Permitted By Company.2. Rates Includes Moving And Reinstallation Of The Barricades From One Work Site To Another, Multiple Times.
BOQ
| Sl. No. | Item Title | Item Description |
| 1 | PURGING FOR COMMISSIOING OF NEW UNDERGROUND PIPELINE WITH NITROGEN Supply of nitrogen gas, equipment, manpower, engineering support, and monitoring services required to safely displace residual hydrocarbons/air from the pipeline and to maintain the pipeline under a dry, inert, low-oxygen atmosphere for the duration of the mothball period, in accordance with recognized industry standards and the Owner's technical specifications. | PURGING FOR COMMISSIOING OF NEW UNDERGROUND PIPELINE WITH NITROGEN Supply of nitrogen gas, equipment, manpower, engineering support, and monitoring services required to safely displace residual hydrocarbons/air from the pipeline and to maintain the pipeline under a dry, inert, low-oxygen atmosphere for the duration of the mothball period, in accordance with recognized industry standards and the Owner's technical specifications. |
| 2 | INERTIZATION Intertization of enitre pipeline of length of 55 km by Nitrogen filling considering volume for approx. 4 km pipeline length of 16\\" dia pipe with pigging & by supply, transportation and delivery of liquid nitrogen along with atmospheric vaporizer , all required manpower, machinery etc. to remove air from the pipeline. A 500 m column of N2 shall be released in pipeline , then foam pig shall be inserted & N2 shall be released in the pipeline till the pig received at other end .Notes:-(1) Inertization and re-commissioning of pipeline shall not be done by Nitrogen cylinder truck.(2) Acceptance criteria for completion of job under this sor item shall be attaining 0% LEL by contractor.(3) Contractor to quote accordingly and arrange adequate quantity of nitrogen required to successfully complete the job in all aspects. | INERTIZATION Intertization of enitre pipeline of length of 55 km by Nitrogen filling considering volume for approx. 4 km pipeline length of 16\\" dia pipe with pigging & by supply, transportation and delivery of liquid nitrogen along with atmospheric vaporizer , all required manpower, machinery etc. to remove air from the pipeline. A 500 m column of N2 shall be released in pipeline , then foam pig shall be inserted & N2 shall be released in the pipeline till the pig received at other end .Notes:-(1) Inertization and re-commissioning of pipeline shall not be done by Nitrogen cylinder truck.(2) Acceptance criteria for completion of job under this sor item shall be attaining 0% LEL by contractor.(3) Contractor to quote accordingly and arrange adequate quantity of nitrogen required to successfully complete the job in all aspects. |
| 3 | Purging for commissioning of 16\\" Pipeline section of length approx. 55 km | Purging for commissioning of 16\\" Pipeline section of length approx. 55 km |
| 4 | Barricading | Barricading |
| 5 | Providing & erecting in position a barricading Structure of 2.0 M height and 2.5 M width (approx.). Using 0.8mm thick corrugated galvanized steel sheets supported on frame of Structural Steel conforming to IS:2062, coated with Red oxide zinc chromate shop primer, including submission of design & drawing to be reviewed by owner, before execution of work at Pipeline route, particularly in residential area and high movement area and as advised by Engineer in charge, removal of barricading structure after completion of work, dressing & trimming of the area. All complete as per Specification & direction of Engineer in charge (All materials to be in contractors scope)Note:1. These rates shall be applied only when explicitly permitted by Company.2. Rates includes moving and reinstallation of the barricades from one work site to another, multiple times. | Providing & erecting in position a barricading Structure of 2.0 M height and 2.5 M width (approx.). Using 0.8mm thick corrugated galvanized steel sheets supported on frame of Structural Steel conforming to IS:2062, coated with Red oxide zinc chromate shop primer, including submission of design & drawing to be reviewed by owner, before execution of work at Pipeline route, particularly in residential area and high movement area and as advised by Engineer in charge, removal of barricading structure after completion of work, dressing & trimming of the area. All complete as per Specification & direction of Engineer in charge (All materials to be in contractors scope)Note:1. These rates shall be applied only when explicitly permitted by Company.2. Rates includes moving and reinstallation of the barricades from one work site to another, multiple times. |
AI Tender Summary
Tender Timeline
Tender Published
Tender notice published.
CompletedBid Submission Deadline
Online submission via eProcurement portal.
Upcoming · 10 daysBid Opening Date
Technical bids will be opened and evaluated.
Upcoming · 11 daysTender Documents
Download All (ZIP) ↓We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender