Power Boards / Undertakings / PSU Closing in 9 days TDR #58607298

Tender For Nctps Ii - M-I Circle - Bm Division - Unit-I -600Mw - Replacement Of 550 Nb Internally Damaged/Valve Passing Mssv-02 Valve (Rhs) With New One By Cutting The Existing Ms Line, Remove The Damaged Valve, Edge Preparation, Fit-Up The New Valve

Issued by Boards / Undertakings / PSU · Thiruvallur, Tamil Nadu
Tender Value
Ref. Documents
Estimated cost
Bid Submission
02 Dec 2026
9 days left
EMD
33700
Bank guarantee accepted
Document Fee
Ref. Documents
Non-refundable
Tender Type
Online

Tender Overview

Competition Type
NCB
Bidding Type
Tender
Location / State
Thiruvallur → Tamil Nadu
EMD Exemption
Available
Quantity
Not Available

Project Description

Tender for Nctps Ii - M-I Circle - Bm Division - Unit-I -600Mw - Replacement Of 550 Nb Internally Damaged/Valve Passing Mssv-02 Valve (Rhs) With New One By Cutting The Existing Ms Line, Remove The Damaged Valve, Edge Preparation, Fit-Up The New Valve, Alignment, Pre & Post Weld Heat Treatment, Argon Gas Purging, Welding The New 550 Nb Valve With Exiting Main Steam Line By Ibr Welder, Testing As Per P91 Material Higher Wall Thickness Statndards & Commissioning During Aoh 2026-27.

BOQ

Name of Work:- NCTPS II - M-I Circle – BM Division – Unit-I -600MW – Replacement of 550 NB internally damaged/Valve Passing MSSV-02 Valve (RHS) with new one by Cutting the existing MS line, Remove the damaged valve, Edge preparation, Fit-up the new valve, Alignment, Pre & Post weld Heat Treatment, Argon Gas Purging, Welding the new 550 NB valve with exiting Main Steam line by IBR welder, Testing as per P91 Material Higher Wall thickness Statndards & Commissioning during AOH 2026-27.
Sl. No. Item Description
1Dismantling and Re Assembling of Valve internals in existing damaged/Passing valve & New valve to facilitate for Leading, Lifting, Cutting, Fixing with new valve, Alignment, Argon gas Purging and welding worksProviding chain block arrangement, dismantling of electrical actuator and motor assembly of 550NB MSSV valve by loosening of all bolt and nuts. Dismantling of yoke assembly, of valve by loosening and releasing of heavy size -16 Nos HT bolt & nuts. using chain block arrangement lead, lift of material to 73mtr elevation of boiler including consumables, T&P's complete.
2Dismantling of totally gland bolts and gland collar, bonnet clamp bolts, heavy size bonnet clamp, bonnet arresting split rings by using 7 ton capacity chain block arrangement, special heavy duty fixtures and 2 X 100 Tons capacity hydraulic jacks by lifting, lead, lift complete at 73mtr elevation of boiler including consumables, T&P's.
3Dismantling of heavy size bonnet assembly with heavy size stem 100 mm Dia X 2 Mtr length with valve disc by using 7 ton capacity chain block arrangement, special heavy duty fixtures and 2 X 100 Tons capacity hydraulic jacks by lifting, lead, lift complete at 73mtr elevation of boiler including consumables, T&P's.
4Re-assembling of bonnet assembly such as grafoil gland rings, supporting ring,grafoil gasket in the bonnet assembly before assembling the bonnet assembly in side the valve, including sheet cutting of bonnet and valve body maching surface area by grinding, buffing and filling etc., assembling at 73mtr elevation of boiler including cost of consumables, machining charges, T&P's, leading, lifting etc.,
5Reassembling of valve internals such as gland bolts, bonnet clamp bolts, bonnet assembly, SS valve stem (Ø100mm X 2 mtr), valve disc- having 450mm dia and heavy weight, of 550NB MSSV valve . using chain block arrangement aligning, matching, checking seating position including leading, lifting and assembling at 73mtr elevation of boiler, consumables, T&P's.
6Re-assembling of yoke of 550NB MSSV valves by tightening of heavy size-18nos HT blolt & nuts. Re-assembling of electrical actuator and motor assembly of 450NB MSSV valve by tightening of all bolt and nuts using chain block arrangement and removing chain block arrangement including leading, lifting and assembling at 73mtr elevation of boiler, consumables, T&P's,
7Commissioning of new MSSV valves by manual operation of full open and full close and adjusting of gland packing tightness and adjusting valve stem upper and lower travel limit for calibration of limit switch level retightining of all bonnet bolts after conducting hydraulic test and again tightening after syncronising of unit at hot condition and lifting upto 73mtr elevation of boiler including consumbales with nessary T&P's, leading.
8Charges for dismantling of chain block arrangement and special type fixtures after completing the cutting, welding and attending the valves replacement works in 72 mtr elevation. Charges including consumables and T&P’s.
9Cutting, Removal and Re erection of MSSV Bypass Line (RHS Side) & MSSV Drain Line (RHS side) to facilitate the replacement of New MSV-02 valve @ 72 Mtr Elevation.Fixing of chain blocks arrangements and special type fixtures at 72 mtr locations for cutting and leading of existing of MSV bypass valve Line (P22: OD 88.9 x 20 mm thk) from working location and again leading, lifting & positioning its original position after completion of MSSV-02 Main valve erection work to facilitate the MSSV-02 replacement works by holding, moving and alignment. Charges inclusive of consumables and T&ps.
10Charges for cutting, removal and welding of the existing MSV 04 & MSV 06 Bypass valve line (P22: OD 88.9 x 20 mm thk) and MS drain Line (P22: OD 60.3 X 12.5 mm thk). This work including edge preparation by grinding after moving and lifting to the required position, holding, fit-up, checking alignment with existing line, preparation of temporary supports, clamps etc. Charges inclusive of consumables and T&ps.
11Charges for Conducting Ultrasonic Test before & after stress relieving in welded bypass valve line (P22: OD 88.9 x 20 mm thk) joints involve, applying the solution near welded surfaces, checking the strength of root and filler welding using special ultrasonic kit, identify the defect if any including Hire charges for T&P's and Consumables.
12Charges for Conducting Stress relieving in welding joints in bypass valve line (P22: OD 88.9 x 20 mm thk) by electric resistance heating in waterwall drain station line involves, Cleaning on welding surface free of grease and dust for avoid short circuit, Ceramic beaded heating coils wrapped all round weld area of MS bypass valves line, Ceramic blanket wrapped around heating coils to avoid temperature difference, Thermocouple attaching in the weldment area, starting the heat treatment cycle on an auto program by Programmable temperature control box, where in heating rate is maintained 110 deg per hour, soaking time starts when all thermocouple achieve the temperature of 625 deg and Soaking time 75 minutes, after attaining 300 deg power could turned off & on cooling the weld to below 150 deg the insulation / elements etc., could be removed completion of soaking time, including Hire charges for T&P's and Consumables.
13Charges for dismantling of chain block arrangement and special type fixtures after completing the cutting, welding and attending the valves replacement works in 72 mtr elevation. Charges including consumables and T&P’s.
14Erection of New 550 NB (10 Ton) MSSV-02 Valve and Execution of In-situ Argon Purging, Pre-heating, Post-Weld Heat Treatment (PWHT) by Induction Method, inter-stage Radiographic Testing (RT) for root pass checking and Advanced Volumetric NDT (PAUT + TOFD) for 550 NB P91 Main Steam Stop Valve (MSSV-02) Joint at @ 72 Mtr Elevation:Leading & Lifting of New 550 NB MSSV Valve Body, Internals from NCTPS-II store to working site @ 73 Mtr elevation (above 50 Mtr Elevation)
15Fabrication of special type heavy duty fixture for facilitating to dismantle the heavy size (10 Ton) 550 NB MSSV Valve body from heavy size MSSV line by insitue fabrication method. The work involves transporting, leading and lifting of required heavy steel materials from 0 Mtr to 72 meter elevation of boiler, designing of special type heavy duty fixture based on site condition, marking of fixture for the designed shape, Gas cutting and grinding of MS materials, welding of fixture to match with the site condition to facilate for releasing the old MSSV body material and fixing new MSSV body.
16Fixing of chain blocks arrangements and special type fixtures at 72 mtr locations for cutting of existing damaged MSV-02 valve and lifting & positioning the new valve with existing line (P91: OD 457 x 43 mm thk) to facilitate cutting, welding and to attend the replacement works by using special type fixture for holding, moving and alignment. Charges inclusive of consumables and T&ps.
17Charges for cutting & removing the existing MSSV-02 valve from exiting line (P91: OD 457 x 43 mm thk) using automated Hydraulic/Pneumatic Split-Frame Cold Cutting and Beveling Machine, edge preparation, fitup, Positioning and Welding the new valve with existing MSSV line by IBR welder. (Argon gas, welding generator, TIG set and special welding electrodes will be the scope of contractor) Charges inclusive of cost of consumables and T&Ps.
18Charges for conducting in-situ continuous Argon Gas Purging for the heavy-wall P91 valve joint to prevent root oxidation during welding. Scope involves fabrication and insertion of specialized high-temperature resistant silicone-lip thermal purging dams positioned inside the pipe on both sides of the weld joint, sealing the external root gap incrementally with high-temperature aluminum backing tape, deploying commercial-grade high-purity (99.99%) Argon gas cylinders to establish an initial high displacement flow rate of 15–20 Liters/Minute (LPM), utilizing a calibrated digital oxygen analyzer to monitor and verify that exhaust oxygen levels drop below 0.01% O₂ (<100 ppm) before authorizing weld initiation, maintaining a steady upkeep purge flow rate of 8–10 LPM continuously throughout the GTAW root and hot-pass welding cycles (approximately 12–14 hours), including labor, high-altitude gas handling, hire charges for oxygen meters, regulators, manifolds, safety setups @ 72 meter elevation, and all gas and tape consumables.
19Charges for conducting Pre-Heating and Stress Relieving process (Post-Weld Heat Treatment) by induction heating method and subsequent Metallurgical Hardness Survey on the in-situ heavy-wall P91 welded valve line joint: Scope involves applying insulation blankets and later-cooled copper coils near welded surfaces, maintaining a continuous pre-heat of 220°C during welding and a soaking temperature at 760°C ± 10°C for a minimum duration of 2.0 hours using a multi-channel digital kit, checking the metallurgical structural strength of the parent metal, HAZ, and weld center using a portable digital hardness tester to verify the acceptable hardness limits (190 to 250 HV/HB), identify any hardness deviations if any, including Hire charges for T&P's, induction machines, instruments, and Consumables.
20Charges for conducting inter-stage Radiographic Testing (RT) for root pass checking on the in-situ heavy-wall P91 welded valve line joint: Scope involves managing the inter-stage thermal hold down to 80°C–100°C for hydrogen release, applying high-temperature insulation barriers near welded surfaces, performing 100% volumetric radiography on the GTAW root run using an Iridium-192 source camera and remote winding gear to identify internal root defects or lack of penetration, evaluating films under high-intensity viewers, and monitoring the subsequent induction re-preheating cycle back to 220°C minimum before filler pass resumption, including Hire charges for T&P's, RT camera, source, survey meters, industrial films, and all chemical and high-altitude safety consumables at +72.00 meter elevation.
21Charges for conducting Advanced Volumetric Non-Destructive Testing (NDT) using integrated Phased Array Ultrasonic Testing (PAUT) and Time-of-Flight DiffrRedion (TOFD) techniques on the in-situ heavy-wall P91 valve joint after Post-Weld Heat Treatment (PWHT). Scope involves preparing and applying high-temperature couplant solution on power-grooved/ground surfaces up to 150 mm on both sides of the weld, setting up specialized multi-channel digital ultrasonic flaw detectors using 4–5 MHz linear array probes with 35° to 70° sectorial sweeps alongside broadband TOFD probe pairs, calibrating the system on a matching 43 mm P91 master block with EDM notches against the 200 mm physical reference punch marks, scanning the entire weld volume and Heat Affected Zone (HAZ) using encoded scanners to identify, map, and size any internal defects (such as lack of side-wall fusion, micro-cracks, or linear volumetric flaws), generating full digital raw data records (A/S/D-scans) for formal IBR dossier submission, including all labor, safety rigging @ 72 meter elevation, hire charges for specialized T&Ps, instruments, calibration blocks, and consumables.
22Charges for conducting pre-weld and post-weld Surface Non-Destructive Testing (NDT) on the in-situ heavy-wall P91 valve joint: Scope involves executing 100% Magnetic Particle Inspection (MPI) on the machined bevel root pass, interim filler layers, and the final post-PWHT weld face along with a 50 mm surrounding heat-affected zone (HAZ) using portable electromagnetic yokes and contrast media to detect surface stress fissures or micro-cracks, including labor, scaffolding/safety rigging at +72.00 meter elevation, hire charges for AC/DC electromagnetic yokes, UV lights, and chemical consumables.
23Charges for dismantling of chain block arrangement and special type fixtures after completing the cutting, welding and attending the valves replacement works in 72 mtr elevation. Charges including consumables and T&P’s.
24Leading & Lifting of Retrived 550 NB MSSV Valve Body, Valve Internals Stem, wedge, Yoke …etc and dismantled Iorn & Steel Materials of heavy duty fixure from working site @ 73 Mtr elevation to NCTPS-II store (above 50 Mtr Elevation)
25Dismantling & Re-erection of Iorn & Steel Structures in Various floors to facilitate leading and lifting of MSSV New valve from 0 Mtr to 73 Mtr & Dismantled valve from 72 Mtr to 0 Mtr.Above 20 Mtr EL upto 50 Mtr Elevation (03, 04, 05, 06, 07 th floor Grill, Shed, Pipe Line, Beams & supports)Dismantling of Iorn & Steel Structures in near by corner 01 from 20 Mtr elevation to 50 Mtr elevation (From 03 rd floor to 07 th floor) to facilitating the Leading & Lifting of the New / Retrived 550 NB (10 Ton) MSSV valve from 0 Mtr to 72 Mtr Elevation and 72 Mtr elevation to 0Mtr (Including Roof shed @ 49 Mtr Elevation & Scanner air fan Pipe line @ 49 Mtr elevation) (above 20 Mtr to 50 mtr Elevation)
26Fabrication and Re-erection of Iorn & Steel Structures in near by corner 01 from 20 Mtr elevation to 50 Mtr elevation (From 03 rd floor to 07 th floor) to facilitating the Leading & Lifting of the New / Retrived 550 NB (10 Ton) MSSV valve from 0 Mtr to 72 Mtr Elevation and 72 Mtr elevation to 0Mtr (Including Roof shed @ 49 Mtr Elevation & Scanner air fan Pipe line @ 49 Mtr elevation) (above 20 Mtr to 50 mtr Elevation)
27Above 50 Mtr Elevation (10 & 12 th floor Grill, Beams & supports)Dismantling of Iorn & Steel Structures in near by corner 01 from 50 Mtr elevation to 72 Mtr elevation (From 08 th floor to 12 th floor) to facilitating the Leading & Lifting of the New / Retrived 550 NB (10 Ton) MSSV valve from 0 Mtr to 72 Mtr Elevation and 72 Mtr elevation to 0Mtr (Including approching platform @ 72 Mtr elevation) (Above 50 Mtr Elevation)
28Fabrication and Re-erection of Iorn & Steel Structures in near by corner 01 from 50 Mtr elevation to 72 Mtr elevation (From 08 th floor to 12 th floor) to facilitating the Leading & Lifting of the New / Retrived 550 NB (10 Ton) MSSV valve from 0 Mtr to 72 Mtr Elevation and 72 Mtr elevation to 0Mtr (Including approching platform @ 72 Mtr elevation) (Above 50 Mtr Elevation)
29Erection of Temprory working Platform @ 72 Mtr Elevation to facilitate the valve erection work.Leading & Lifting of Iron & Steel Structures, Supports & Temporary Platform Materials from 0 mtr to 72 mtr elevation to fabrication & erection of working platform for replacement of new 550 NB (10 Ton) MSSV valve @ 72 Mtr elevation. (Above 50 Mtr Elevation)
30Fabrication and erection of Temporary supports & Platforms @ 72 Mtr elevation for facilitating cutting, welding, Argon gas Purging, Heat Treatment Processes, RT, UT & NDT testings and commisssioning of new 550 NB MSSV Valve (Above 50 Mtr Elevation)
31Dismantling of Temporary supports & Platforms @ 72 Mtr elevationafter completing cutting, welding, Argon gas Purging, Heat Treatment Processes, RT, UT & NDT testings and commisssioning work of new 550 NB MSSV Valve and lowering 72 mtr to to 0 Mtr elevation (Above 50 Mtr Elevation) Please Enable Macros to View BoQ information

AI Tender Summary

OUR REF NO 58607298
AUTHORITY Boards / Undertakings / PSU
TENDER VALUE Ref. Documents
LAST DATE 02-12-2026
Authority
Authority Name Tamil Nadu Generation And Distribution Corporation Limited
Work Description Tender for Nctps Ii - M-I Circle - Bm Division - Unit-I -600Mw - Replacement Of 550 Nb Internally Damaged/Valve Passing Mssv-02 Valve (Rhs) With New One By Cutting The Existing Ms Line, Remove The Damaged Valve, Edge Preparation, Fit-Up The New Valve, Alignment, Pre & Post Weld Heat Treatment, Argon Gas Purging, Welding The New 550 Nb Valve With Exiting Main Steam Line By Ibr Welder, Testing As Per P91 Material Higher Wall Thickness Statndards & Commissioning During Aoh 2026-27.
Basic Detail
Tender No NCTPS_II_UI_Spec_223_BM_MSSV
Bidding Type Tender
Location
City Thiruvallur
State Tamil Nadu
Key Dates
Publish Date 19 Nov 2026
Submission Date 02 Dec 2026
Open Date 03 Dec 2026
Finance
Tender Value Ref. Documents
Tender Fee Ref. Documents
EMD 33700
Exemption Available
Document List
4874a241-92e8-4d7d-b090-52787a4bba55.html
BOQ_873679.xls
Tendernotice_1.pdf

Unlock Full AI Tender Summary

Get instant access to the complete AI-generated analysis — scope, eligibility, timeline & more.

Instant Access Secure Free
Your details are secure and used only for document delivery.

Tender Timeline

Nov 19, 2026
11:30 IST

Tender Published

Tender notice published.

Completed
Dec 02, 2026
17:00 IST

Bid Submission Deadline

Online submission via eProcurement portal.

Upcoming · 9 days
Dec 03, 2026

Bid Opening Date

Technical bids will be opened and evaluated.

Upcoming · 10 days

Tender Documents

Download All (ZIP) ↓
html

4874a241-92e8-4d7d-b090-52787a4bba55.html

xls

BOQ_873679.xls

pdf

Tendernotice_1.pdf

Disclaimer

We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender