Tender For Construction & Maintenance Of T02-Sakawrdai To N Khawdungsei (0.000-8.000) Kmp (Technologies Flexible Pavement)
Tender Value
11.80 Crore
Estimated cost
Bid Submission
23 Nov 2026
2 days left
EMD
11.80 Lakhs
Bank guarantee accepted
Document Fee
10000
Non-refundable
Tender Type
Online
Tender Overview
Organization
Tender ID
Competition Type
NCB
Bidding Type
Tender
Location / State
Aizawl → Mizoram
EMD Exemption
Not Available
Quantity
Not Available
Website
Contact Person
Address
Project Description
Tender For Construction & Maintenance Of T02-Sakawrdai To N Khawdungsei (0.000-8.000) Kmp (Technologies Flexible Pavement)
BOQ
| Sl. No. | Item Description |
| 1 | Road Furniture & Safety ➤ Traffic Signs |
| 2 | PMGSY informatory sign board with Logo as per MORD specifications and drawing |
| 3 | Citizen's Information Board with Logo of PMGSY as per MoRD Specifications |
| 4 | Traffic Signs ➤ A.Retro-reflectorised Traffic Signs ➤ [10.2] -1Providing and fixing of retro-reflectorised cautionary, mandatory and informatory sign as per IRC:67 made of encapsulated lens type reflective sheeting vide Clause 1701.2.3 fixed over aluminium sheeting, 1.5 mm thick supported on a mild steel angle iron post 75 mm x 75 mm x 6 mm firmly fixed to the ground by means of properly designed foundation with M15 grade cement concrete 450 mm x 450 mm x 600 mm, 600 mm below ground level as per drawings and Technical Specification Clause 801 |
| 5 | Direction and Place Identification signs upto 0.9 sqm size board ➤ A.Retro-reflectorised Traffic Signs ➤ [10.3] (i)Providing and erecting direction and place identification retro-reflectorised sign as per IRC:67 made of encapsulated lens type reflective sheeting vide Clause 1701.2.3, fixed over aluminium sheeting, 2 mm thick with area not exceeding 0.9 sqm supported on a mild steel single angle iron post 75 x 75 x 6 mm firmly fixed to the ground by means of properly designed foundation with M-15 grade cement concrete 450 x 450 x 600 mm, 600 mm below ground level as per approved drawing and Technical Specification Clause 1701 |
| 6 | Painting Two Coats on New Concrete Surfaces ➤ [10.5] Painting two coats including primer coat after filling the surface with synthetic enamel paint in all shades on new, plastered / concrete surfaces as per drawing and Technical Specification Clause 1701 |
| 7 | Kilometre Stone ➤ Reinforced cement concrete M15 grade kilometre stone/local stone of standard design as per IRC:8 fixing in position including painting and printing, etc as per drawing and Technical Specification Clause 1703 ➤ [10.10] i)5th Kilometre Stone (precast) |
| 8 | Kilometre Stone ➤ Reinforced cement concrete M15 grade kilometre stone/local stone of standard design as per IRC:8 fixing in position including painting and printing, etc as per drawing and Technical Specification Clause 1703 ➤ [10.10] ii)Ordinary Kilometer Stone (Precast) |
| 9 | Kilometre Stone ➤ Reinforced cement concrete M15 grade kilometre stone/local stone of standard design as per IRC:8 fixing in position including painting and printing, etc as per drawing and Technical Specification Clause 1703 ➤ [10.10] iii) 200 m stone (precast) |
| 10 | Boundary Pillar ➤ [10.11] Reinforced cement concrete M15 grade boundary pillars/local stone of standard design as per IRC:25, fixed in position including finishing and lettering but excluding painting as per drawing and Technical Specification Clause 1704 |
| 11 | Road Furniture & Safety ➤ Road Safety |
| 12 | Excavation for Structures ➤ Earthwork in excavation for structures as per drawing and technical specifications Clause 305.1 including setting out, construction of shoring and bracing, removal of stumps and other deleterious material and disposal upto a lead of 50 m, dressing of sides and bottom and backfilling in trenches with excavated suitable material. ➤ [11.1] II.Ordinary rock (not requiring blasting) - Upto 3 m depth |
| 13 | [13.19] Plastering with cement mortar (1:3) 15 mm thick on brickwork in parapet as per technical specifications Clauses 613.4 and 1208.4. - Rate same as in item 12.3 |
| 14 | Providing and laying parapet with PCC M 15 as per drawing & technical specifications Clauses 800 and 1208.4. ➤ [13.20] I. Nominal mix 1:2.5:5 (Hand mixing) - Rate same as in item 12.5 I (ii) |
| 15 | Pavement Works ➤ Clearing & Grubbing |
| 16 | Clearing and Grubbing Road Land ➤ Clearing and grubbing road land including uprooting wild vegetation, grass, bushes, shrubs, saplings and trees of girth upto 300 mm, removal of stumps of such trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned, upto a lead of 1000 m including removal and disposal of top organic soil not exceeding 150 mm in thickness as per Technical Specification Clause 201. ➤ (I)By Manual Means ➤ [2.2] (B)In area of thorny jungle |
| 17 | Cutting of Trees including Cutting of Trunks, Branches and Removal of Stumps ➤ Cutting of trees, including cutting of trunks, branches and removal of stumps & roots, refilling, compaction of backfilling and stacking of serviceable material by manual means with all lifts as per Technical Specification Clause 201. ➤ A.Lead upto 100 m ➤ [2.3] (i)Girth above 300 mm to 600 mm |
| 18 | Cutting of Trees including Cutting of Trunks, Branches and Removal of Stumps ➤ Cutting of trees, including cutting of trunks, branches and removal of stumps & roots, refilling, compaction of backfilling and stacking of serviceable material by manual means with all lifts as per Technical Specification Clause 201. ➤ A.Lead upto 100 m ➤ [2.3] (ii)Girth above 600 mm to 900 mm |
| 19 | Cutting of Trees including Cutting of Trunks, Branches and Removal of Stumps ➤ Cutting of trees, including cutting of trunks, branches and removal of stumps & roots, refilling, compaction of backfilling and stacking of serviceable material by manual means with all lifts as per Technical Specification Clause 201. ➤ A.Lead upto 100 m ➤ [2.3] (iii)Girth above 900 mm to 1800 mm |
| 20 | Setting Out ➤ The analysis of rate per km shall account for the following: ➤ (3) Construction of job pillars as per Fig. 1600.1 (d) ➤ [8.2] (1)Construction of reference pillars as per Fig. 1600.1 (b) as per drawing and Technical Specification Clause 1602.1 |
| 21 | Setting Out ➤ The analysis of rate per km shall account for the following: ➤ (3) Construction of job pillars as per Fig. 1600.1 (d) ➤ [8.2] (2)Construction of back piller as per Fig. 1600.1( c) as per drawing and Technical Specification Clause 1602.3 |
| 22 | Setting Out ➤ The analysis of rate per km shall account for the following: ➤ (3) Construction of job pillars as per Fig. 1600.1 (d) ➤ [8.2] (3)Construction of Job pillers as per Fig. 1600.1 (d) and Technical Specification Clause 1602.4 |
| 23 | Pavement Works ➤ Earthwork in Filling |
| 24 | Construction of Embankment with Material Obtained from Roadway Cutting ➤ [3.3] Construction of embankment with approved materials deposited at site from roadway cutting and excavation from drain and foundation of other structures graded and compacted to meet requirement of Tables 300.1 and 300.2 as per Technical Specification Clause 301.5 |
| 25 | Construction of Subgrade and Earthen Shoulders ➤ [3.14] Construction of subgrade and earthen shoulders with approved material obtained from borrow pits with all lifts and leads, transporting to site, spreading, grading to required slope and compacted to meet requirement of Table 300.2 with lead upto 1000 m as per Technical Specification Clause 303.1. |
| 26 | Pavement Works ➤ Earthwork in Excavation |
| 27 | Removal of Unsuitable Soil with Disposal upto 1000 m ➤ [3.7] Removal of unsuitable soil including excavation, loading and disposal upto 1000 m lead but excluding compaction ground supporting embankment subgrade replacement by suitable soil, which shall be paid separately as per Clause 303.5.2 as per Technical Specification Clause 302.3.11 |
| 28 | Earthwork in Hill Road ➤ (ii)Excavation in Hilly Areas in Soil by mechanical means ➤ [8.3] A)Excavation in soil in Hilly Area by mechanical means including cutting and trimming of side slopes and disposing of excavated earth with a lift upto 1.5 m and a lead upto 20 m as per Technical Specification Clause 1603.1 |
| 29 | Earthwork in Hill Road ➤ [8.3] (iv) Excavation in hilly area in ordinary rock not requiring blasting by mechanical means including cutting and trimming of slopes and disposal of cut material with a lift upto 1.5 m and lead upto 20 m as per Clause 1603.2. |
| 30 | Earthwork in Hill Road ➤ (v)Excavation in Hilly Areas in Hard Rock requiring blasting ➤ [8.3] A)Excavation in hilly areas in hard rock requiring blasting, by mechanical means, lift upto 1.5 m and disposal of excavated rock upto a lead of 20 m as per Clause 1603.2. |
| 31 | Pavement Works ➤ Compacting Original Ground |
| 32 | Compacting Original Ground ➤ (ii) Compacting original ground supporting subgrade ➤ [3.15] Loosening of the ground upto a level of 300 mm below the subgrade level, watered, graded and compacted in layers to meet requirement of Tables 300.1 and 300.2 for subgrade construction as per Technical Specification Clause 303.5.2. |
| 33 | Pavement Works ➤ Granular Sub-Base |
| 34 | Granular Sub-base with Well Graded Material (Table 400.1) ➤ (A) By Mix in Place Method ➤ Construction of granular sub-base by providing well graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with smooth wheel roller to achieve the desired density, complete as per Technical Specification Clause 401. ➤ [4.1] (i)For Grading I Material |
| 35 | Pavement Works ➤ WBM Grade-II |
| 36 | Water Bound Macadam with Crushable Screenings ➤ 2) WBM Grading 2 ➤ Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with three wheel 80-100 kN static roller in stages to proper grade and camber, applying and brooming, crushable screening to fill-up the interstices of coarse aggregate, watering and compacting to the required density Grading 2 as per Technical Specification Clause 405. ➤ [4.8] (A)By Manual Means |
| 37 | Pavement Works ➤ WBM Grade-III |
| 38 | Water Bound Macadam with Crushable Screenings ➤ 3) WBM Grading 3 ➤ Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with three wheel 80-100 kN static roller in stages to proper grade and camber, applying and brooming, crushable screening to fill-up the interstices of coarse aggregate, watering and compacting to the required density Grading 3 as per Technical Specification Clause 405. ➤ [4.8] (A)By Manual Means |
| 39 | Pavement Works ➤ Prime Coat |
| 40 | Prime Coat ➤ (i) Low porosity ➤ [5.1] Providing and applying primer coat with bitumen emulsion (SS-1) on prepared surface of granular base including cleaning of road surface and spraying primer at the rate of 0.70-1.0 kg/sqm using mechanical means as per Technical Specification Clause 502 |
| 41 | Pavement Works ➤ Tack Coat |
| 42 | Tack Coat ➤ [5.2] (iii)Providing and applying tack coat with Bitumen emulsion (RS-1) using emulsion distributor at the rate of 0.25 to 0.30 kg per sqm on the prepared granular surfaces treated with primer & cleaned with Hydraulic broom as per Technical Specification Clause 503. |
| 43 | Pavement Works ➤ Mix Seal Surfacing |
| 44 | Mix Seal Surfacing ➤ Providing, laying and rolling of close-graded premix surfacing material of 20 mm thickness composed of 11.2 mm to 0.9 mm (Type-A) or 13.2 mm to 0.9 mm (Type-B) aggregates using penetration grade bitumen to required line, grade and level to serve as wearing course on a previously prepared base, including mixing in a suitable plant, laying and rolling with a three wheel 8-10 kN static roller and finishing to required level and grades as per Technical Specification Clause 509 ➤ By Mechanical Means - Type A ➤ [5.11] (II)Bitumen (S-65) |
| 45 | Painting lines, Dashes, Arrows, etc. on Roads in Two Coats on Old Work ➤ [10.9] Painting lines, dashes, arrows, etc. on roads in two coats on old work with ready mixed road marking paint conforming to IS:164 on bituminous/concrete surface, including cleaning the surface of all dirt, dust and other foreign matter, demarcation at site and traffic control as per drawing and technical specification Clause 1702 - Assuming 100 cm width |
| 46 | Drainage Works ➤ Unlined Drain |
| 47 | Excavation for Structures ➤ Earthwork in excavation for structures as per drawing and technical specifications Clause 305.1 including setting out, construction of shoring and bracing, removal of stumps and other deleterious material and disposal upto a lead of 50 m, dressing of sides and bottom and backfilling in trenches with excavated suitable material. ➤ I.Ordinary soil ➤ [11.1] (i)Upto 3 m depth |
| 48 | Excavation for Structures ➤ Earthwork in excavation for structures as per drawing and technical specifications Clause 305.1 including setting out, construction of shoring and bracing, removal of stumps and other deleterious material and disposal upto a lead of 50 m, dressing of sides and bottom and backfilling in trenches with excavated suitable material. ➤ [11.1] III. Hard rock (requiring blasting) - Upto 3 m depth including 1.5 m depth in hard rock |
| 49 | Drainage Works ➤ Lined Drain |
| 50 | Excavation for Structures ➤ Earthwork in excavation for structures as per drawing and technical specifications Clause 305.1 including setting out, construction of shoring and bracing, removal of stumps and other deleterious material and disposal upto a lead of 50 m, dressing of sides and bottom and backfilling in trenches with excavated suitable material. ➤ I.Ordinary soil ➤ [11.1] (i)Upto 3 m depth |
| 51 | Stone masonry work in cement mortar in foundation complete as per drawing and technical specifications Clauses 702, 704, 1202 & 1203. ➤ I. Coursed rubble masonry (1st sort) ➤ [11.6] (ii)In 1:4 cement mortar |
| 52 | Protection Works ➤ Breast Wall |
| 53 | Excavation for Structures ➤ Earthwork in excavation for structures as per drawing and technical specifications Clause 305.1 including setting out, construction of shoring and bracing, removal of stumps and other deleterious material and disposal upto a lead of 50 m, dressing of sides and bottom and backfilling in trenches with excavated suitable material. ➤ I.Ordinary soil ➤ [11.1] (i)Upto 3 m depth |
| 54 | Providing concrete for plain/reinforced concrete in open foundations complete as per drawings and technical specifications Clause 802, 803, 1202 & 1203 ➤ I.P.C.C grade M 10 ➤ [11.4] (ii)Nominal mix 1:3.6 (Hand mixing) |
| 55 | Stone masonry work in cement mortar in foundation complete as per drawing and technical specifications Clauses 702, 704, 1202 & 1203. ➤ III. Random Rubble Masonry ➤ [11.6] (ii)In cement mortar 1:4 |
| 56 | [12.11] Providing and laying filter media with granular crushed aggregates as per specification to a thickness of not less than 600 mm with smaller size towards the soil and bigger size towards the wall and providing over the entire surface behind abutment, wing wall, return wall to the full height, compacted to firm condition complete as per drawing and technical specification Clause 1204.3.8 |
| 57 | [12.13] Providing PCC M-20 architectural coping on the top of wing wall, return wall etc. complete as per drawing and technical specification Clauses 615, 710 and 1204.3.11 |
| 58 | Protection Works ➤ Retaining Wall |
| 59 | Excavation for Structures ➤ Earthwork in excavation for structures as per drawing and technical specifications Clause 305.1 including setting out, construction of shoring and bracing, removal of stumps and other deleterious material and disposal upto a lead of 50 m, dressing of sides and bottom and backfilling in trenches with excavated suitable material. ➤ I.Ordinary soil ➤ [11.1] (i)Upto 3 m depth |
| 60 | Providing concrete for plain/reinforced concrete in open foundations complete as per drawings and technical specifications Clause 802, 803, 1202 & 1203 ➤ I.P.C.C grade M 10 ➤ [11.4] (ii)Nominal mix 1:3.6 (Hand mixing) |
| 61 | [12.3] Plastering with cement mortar (1:4), 15 mm thick on brickwork in substructure as per technical specification Clauses 613.4 & 1204 |
| 62 | Stone masonry in cement mortar for substructure complete as per drawing & technical specification Clauses 702, 704, 1202 and 1204 ➤ I.Coursed rubble masonry (1st sort) ➤ [12.4] (iii) In cement mortar (1:5) |
| 63 | [12.11] Providing and laying filter media with granular crushed aggregates as per specification to a thickness of not less than 600 mm with smaller size towards the soil and bigger size towards the wall and providing over the entire surface behind abutment, wing wall, return wall to the full height, compacted to firm condition complete as per drawing and technical specification Clause 1204.3.8 |
| 64 | [12.13] Providing PCC M-20 architectural coping on the top of wing wall, return wall etc. complete as per drawing and technical specification Clauses 615, 710 and 1204.3.11 |
| 65 | Stone masonry in cement mortar 1:3 for parapet complete as per drawing and technical specifications Clauses 700 and 1208.4 ➤ [13.17] I. Random rubble masonry - Rate same as in item 12.4 III (i) |
| 66 | CD Works ➤ 1.5m Span |
| 67 | Excavation for Structures ➤ Earthwork in excavation for structures as per drawing and technical specifications Clause 305.1 including setting out, construction of shoring and bracing, removal of stumps and other deleterious material and disposal upto a lead of 50 m, dressing of sides and bottom and backfilling in trenches with excavated suitable material. ➤ I.Ordinary soil ➤ [11.1] (i)Upto 3 m depth |
| 68 | Providing concrete for plain/reinforced concrete in open foundations complete as per drawings and technical specifications Clause 802, 803, 1202 & 1203 ➤ II.P.C.C grade M 15 ➤ [11.4] (i)Nominal mix (1:2.5:5) |
| 69 | [12.3] Plastering with cement mortar (1:4), 15 mm thick on brickwork in substructure as per technical specification Clauses 613.4 & 1204 |
| 70 | Stone masonry in cement mortar for substructure complete as per drawing & technical specification Clauses 702, 704, 1202 and 1204 ➤ II.Coursed Rubble masonry (2nd sort) ➤ [12.4] (ii) In 1:4 cement mortar |
| 71 | Backfilling behind abutment, wing wall and return wall complete as per drawings & technical specification Clause 1204.3.8 ➤ [12.10] I)Granular material |
| 72 | [12.13] Providing PCC M-20 architectural coping on the top of wing wall, return wall etc. complete as per drawing and technical specification Clauses 615, 710 and 1204.3.11 |
| 73 | Providing and laying reinforced cement concrete in superstructure as per drawing and technical specifications Clauses 800, 1205.4 and 1205.5 ➤ [13.1] II.R.C.C M 25 |
| 74 | [13.2] Supplying, fitting, and placing HYSD bar reinforcement in superstructure complete as per drawing and technical specifications Clauses 1002, 1010 and 1202 |
| 75 | Stone masonry in cement mortar 1:3 for parapet complete as per drawing and technical specifications Clauses 700 and 1208.4 ➤ [13.17] I. Random rubble masonry - Rate same as in item 12.4 III (i) |
| 76 | CD Works ➤ 2.0m Span |
| 77 | Excavation for Structures ➤ Earthwork in excavation for structures as per drawing and technical specifications Clause 305.1 including setting out, construction of shoring and bracing, removal of stumps and other deleterious material and disposal upto a lead of 50 m, dressing of sides and bottom and backfilling in trenches with excavated suitable material. ➤ I.Ordinary soil ➤ [11.1] (i)Upto 3 m depth |
| 78 | Providing concrete for plain/reinforced concrete in open foundations complete as per drawings and technical specifications Clause 802, 803, 1202 & 1203 ➤ II.P.C.C grade M 15 ➤ [11.4] (i)Nominal mix (1:2.5:5) |
| 79 | [12.3] Plastering with cement mortar (1:4), 15 mm thick on brickwork in substructure as per technical specification Clauses 613.4 & 1204 |
| 80 | Stone masonry in cement mortar for substructure complete as per drawing & technical specification Clauses 702, 704, 1202 and 1204 ➤ II.Coursed Rubble masonry (2nd sort) ➤ [12.4] (ii) In 1:4 cement mortar |
| 81 | Backfilling behind abutment, wing wall and return wall complete as per drawings & technical specification Clause 1204.3.8 ➤ [12.10] I)Granular material |
| 82 | [12.13] Providing PCC M-20 architectural coping on the top of wing wall, return wall etc. complete as per drawing and technical specification Clauses 615, 710 and 1204.3.11 |
| 83 | Providing and laying reinforced cement concrete in superstructure as per drawing and technical specifications Clauses 800, 1205.4 and 1205.5 ➤ [13.1] II.R.C.C M 25 |
| 84 | [13.2] Supplying, fitting, and placing HYSD bar reinforcement in superstructure complete as per drawing and technical specifications Clauses 1002, 1010 and 1202 |
| 85 | Stone masonry in cement mortar 1:3 for parapet complete as per drawing and technical specifications Clauses 700 and 1208.4 ➤ [13.17] I. Random rubble masonry - Rate same as in item 12.4 III (i) |
| 86 | CD Works ➤ Hume Pipe |
| 87 | Fillling in foundation trenches as per drawing and technical specification Clause 305.3.9 ➤ [11.2] II.Earth filling (For marshy soil) |
| 88 | Providing concrete for plain/reinforced concrete in open foundations complete as per drawings and technical specifications Clause 802, 803, 1202 & 1203 ➤ I.P.C.C grade M 10 ➤ [11.4] (ii)Nominal mix 1:3.6 (Hand mixing) |
| 89 | Stone masonry work in cement mortar in foundation complete as per drawing and technical specifications Clauses 702, 704, 1202 & 1203. ➤ I. Coursed rubble masonry (1st sort) ➤ [11.6] (ii)In 1:4 cement mortar |
| 90 | [12.3] Plastering with cement mortar (1:4), 15 mm thick on brickwork in substructure as per technical specification Clauses 613.4 & 1204 |
| 91 | Backfilling behind abutment, wing wall and return wall complete as per drawings & technical specification Clause 1204.3.8 ➤ [12.10] I)Granular material |
| 92 | [12.13] Providing PCC M-20 architectural coping on the top of wing wall, return wall etc. complete as per drawing and technical specification Clauses 615, 710 and 1204.3.11 |
| 93 | Stone masonry in cement mortar 1:3 for parapet complete as per drawing and technical specifications Clauses 700 and 1208.4 ➤ [13.17] I. Random rubble masonry - Rate same as in item 12.4 III (i) |
| 94 | Excavation for Structures ➤ [9.1] Earthwork in excavation for foundation of structures upto 3 m depth as per drawing and technical specification Clause 1104 includding setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom and backfilling with approved material. |
| 95 | Bedding for Pipe ➤ [9.2] (ii)Type B (First Class) Bedding - Laying (First Class) bedding on well compacted sand, moorum or approved granular material as per Clause 1105 (ii) |
| 96 | Providing and Laying Reinforced Cement Concrete Pipe NP3 as per design in Single Row ➤ Providing and laying reinforced cement concrete pipe NP3 for culverts on first class bedding of granular material in single row including fixing collar with cement mortar 1:2 but excluding excavation, protection works, backfilling, concrete and masonry works in head walls and parapets Clause 1106. ➤ [9.3] (B)1000 mm dia Please Enable Macros to View BoQ information |
AI Tender Summary
Tender Timeline
Nov 12, 2026
11:30 IST
Tender Published
Tender notice published.
CompletedNov 23, 2026
17:00 IST
Bid Submission Deadline
Online submission via eProcurement portal.
Upcoming · 2 daysNov 23, 2026
Bid Opening Date
Technical bids will be opened and evaluated.
Upcoming · 2 daysTender Documents
Download All (ZIP) ↓
Disclaimer
We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender