Tender For Ph Works For Construction Of Hwc Sub-Centre Building At Kochiakoili Of Bahanaga Block In The District Of Baleshwar
Tender Value
6.12 Lakhs
Estimated cost
Bid Submission
23 Nov 2026
8 days left
EMD
6200
Bank guarantee accepted
Document Fee
4000
Non-refundable
Tender Type
Online
Tender Overview
Organization
Tender ID
Competition Type
NCB
Bidding Type
Tender
Location / State
Baleshwar → Odisha
EMD Exemption
Available
Quantity
Not Available
Website
Contact Person
Address
Project Description
Tender for Ph Works For Construction Of Hwc Sub-Centre Building At Kochiakoili Of Bahanaga Block In The District Of Baleshwar
BOQ
| Sl. No. | Item Description |
| 1 | Earth work in all kinds of soil in excavation of foundation trenches within 50 m initial lead including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding o.30 in depth and as per direction of E.I.C .-- Initial lift up to 1.50m |
| 2 | 2nd depth upt 3.00 mtr |
| 3 | Supplying all materials, labour T&P and filling in F&P with river sand well watered and rammed including conveyance of all materials to worksite payment of royalty, taxes etc. all complete as per direction of E.I.C. |
| 4 | Supplying all materials, labour T&P and providing c.c (1:3:6) using 4cm h.g. metal including watering, curing, coveyance of all materials to worksite payment of royalty, taxes etc. all complete as per specification and direction of E.I.C. |
| 5 | Supplying all materials, labour T&P and providing c.c (1:1.5:3) using 12 mm h.g. chips including watering, curing, coveyance of all materials to worksite payment of royalty, taxes etc. all complete as per specification and direction of E.I.C. |
| 6 | 1st floor |
| 7 | Supplying all materials, labour, T&P and providing brick work with Fly Ash bricks 25cmx12cmx8cm size having cs. not less than 75kg / cm2 with dimensional tolerance ± 8% in including watering,curing conveyance of all materials to worksite, payment of royalty taxes etc. all complete as per specification and direction of EIC. - In Foundation & Plinth in CM (1:4) |
| 8 | Supplying all materials, labour, T &P and providing C.C (1:1.5 :3 ) using 12mm h.g. chips for R.C.C. works including hoisting, laying, watering, curing, conveyance of all materials to worksite, curing, conveyance of all materials to worksite, payment of royalty, taxes etc, all complete as per specification and direction of E.I.C. |
| 9 | Supplying all materials, labour, T&P and providing M.S. reinforcement for R.C.C. works including cutting, bending, binding and tying the grills and placing in position including cost of binding wire 18 to 20 gauge, conveyance of all materials to worksite etc. complete as per directio n of E.I.C. |
| 10 | Supplying all materials, labour, T&P and providing rigid & smooth centering & shuttering for R.C.C.works including false work and dismantling them after casting including conveyance of all material, to worksite, payment of royalty, taxes etc. all complete as per direction of E..I.C.-- R.C.C.Slab |
| 11 | Supplying all materials, labour, T&P and providing cement plaster on brick/stone work including watering, curing, conveyance of all materials to worksite, payment of royalty, taxes etc. all complete as per specification and direction of E.I.C.-- 12mm thick C.P with C.M. (1:4) |
| 12 | 20mm thick C.P with C.M. (1:4) |
| 13 | Supplying all materials, labour, T&P and providing cement punning including watering, curing, conveyance of all materials to worksite, payment of royality, taxes etc. all complete as per specification and direction of E.I.C. |
| 14 | Supplying all materials, labour, T&P and providing cement flush pointing to brick masonary (1:3) including watering, curing conveyance of all materials to work site, payment of royality, taxes etc. all complete as per direction of E.I.C. |
| 15 | Supplying all labour, materials T&P and fixing of R.C.C. Baffle wall pre-cast with C.C. (1:1.5:3) using 12 mm b.h.g. chips and fitted to septic tank as per P.H. Specification and direction of E.I.C. |
| 16 | Supply all materials ,labour,T&P providing fitting and fixing PVC. Tee in wall including filling the necessary with cement concrete (1:2:4) with 12mm size h.g. chips all complete including watering curring,conveyance of all \\"materials to work site .payment of royality .taxes its all complete as per specification and direction of E.I.C.-11OmmXI 10mm X110mm PVC Tee |
| 17 | Supplying all materials labour T& P and providing 500 x 500 x 100mm thick RCC precast M.H cover in C.C (1:1.5:3) using 12mm h.g. chips and placing the cover on the MH/S tank & finishing smooth all complete as per specification and direction of E.I.C |
| 18 | Supplying all materials, labour, T&P and making M.S. Step Iron in 12mm Dia M.S Steel bars and fixing into walls of Manhole/ Septic Tanks duly embeded in C.C(1:2:4) etc all complete as per P.H specification and direction of the E.I.C. |
| 19 | Filling F&P with excavated materials, including watering and ramming as per direction of E.I.C. |
| 20 | Supplying all materials, labour T&P and fixing Ceramic Tiles in floors on 25mm thick bed of cement mortar (1:1) joined with neat cement slurry mixed with pigments to match the shades of the tiles including rubbing and polishing complete as per specification and direction of EIC- Ground Floor |
| 21 | First floor |
| 22 | Supplying all materials, labour T&P and fixing porcelain glazed tiles in dados skirting, on 12mm thick C.P. (1:3) jointed with neat cement slurry mixed with pigments to match the shades of the tiles including rubbing and polishing complete as per direction of Engineer-in-Charge.[Gr. Floor] |
| 23 | First floor |
| 24 | Wall painting two coats with weather coat of approved shade on wall surface Over a coat of Primer including cost of weather coat and primer inclusing supply of all materials labour T & P etc complete. |
| 25 | Supplying all labour, materials, T&P, fitting and fixing of door frame made out PVC Profiles joined to the horizontal after inserting MS/FIBER ‘L’ angles of size 200mm x 100mm and self tapping screw and one mtr. reinforcement providing along the sheet of the frame where the door is to be hanged. It is to be fixed to the wall with steel screw and rawal plugs all complete as per specification and direction of E.I.C. |
| 26 | Supplying all labour, materials, T&P, fitting and fixing of plastic door shutters to be made of selective PVC Profiles, The styles & rails are made of section measuring 24mm x 59mm. A lock rail is provided horizontally at the required place for strength and firmness measuring 24mm x 100mm. The panel are provided a size measuring 200mm x 20mm. All the four corners are provided with MS/Fibre ‘L’ angles of size 200mm x 100mm and fitted with steel screw. The door to be hanged to the frame with the help of 100mm S.S. hinges and self tapping screw three nos. steel handle two nos. and 150mm long steel tower bolt two nos. all complete as per specification and direction of E.I.C.(Joint less Single Piece) |
| 27 | Supplying all materials, labour T&P and fixing Water closet, (Orissa pattern squating pan) duly embeded in C.C. (1:5:10) using 4cm h.g. metal all complete as per direction of E.I.C.- 580mm Orissa pan (Cerra/Parry ware/ Hindware) |
| 28 | Supplying all materials, labour T&P and fixing Wash Down Water Closet(European type W.C. pan) with Integral ‘S’ or ‘P’ trap to the floor with wooden plug and C.P.screws including jointing the trap with soil pipe in C.M.(1:1) etc. all complete as per specification & direction of E.I.C-- E.W.C. with ‘S’ trap Plain(Cerra/ Parry ware/ Hindware) |
| 29 | Supplying all materials, labour, T&P fitting and fixing Plastic Seat and cover for E.W.C. with chromium plated brass hinges and rubber buffers all complete as perr specification and direction of E.I.C. (Cerra/Parry ware/ Hindware) |
| 30 | Supplying all materials, labour T&P and fitting & fixing SWR ventilating pipes and fittings of the following O.D conforming to ISI No. 13592/1992 to walls with nails, bobbins and wooden plugs or laying in trenches including jointing with supply of approved rubber lubricant by non-heat application method as per manufacturer’s specification, testing, e.w. in excavation in all kinds of soil and refilling of trenches as per direction of E.I.C.- 110 mm dia PVCSWR Pipes |
| 31 | 110 mm dia PVC SWR P’ Trap |
| 32 | 110 mm dia PVC SWR Door Tee |
| 33 | 110 mm dia PVC SWR Door CrossTee |
| 34 | 110 mm dia PVC SWR Door Bend |
| 35 | 110 mm dia PVC SWR Plain Bend |
| 36 | 110 mm dia PVC SWR Plain Tee |
| 37 | 110 mm dia PVC SWR Offset |
| 38 | 110 mm dia PVC SWR Cowl |
| 39 | 125 mm dia C.P.grating |
| 40 | 75 mm dia SWR Pipes |
| 41 | 75 mm dia PVC SWR Plain bend |
| 42 | 75 mm dia PVC SWR Door bend |
| 43 | 110 mm dia PVC SWR Nahani trap without Jally |
| 44 | 100x75 mm dia PVC R/S |
| 45 | Supplying all materials, labour T&P and cutting holes through brick/stone masonary walls for taking PVC pipes and fittings including making good the damages etc. all complete as per P.H. specification and direction of E.I.C. - 250 mm to 375mm thick wall |
| 46 | Supplying all materials, labour T&P and fixing wash basins with hole for pillar taps with C.I/M.S brackets painted white including holes in walls and making good the damages etc. all complete as per P.H specification and direction of E.I.C.-- 550mm x 400mm WHB with all Fittings with C.P. Waste, PVC Waste Pipe & Connection Pipe. (Cera/ Parry ware/ Hindware) |
| 47 | Supplying all materials, labour T&P and fixing padestrial for wash basin complete recessed at the back for the reception of pipe and fitting etc. all complete as per specification and direction of E.I.C. (Parrywear/Cera/Hindware) |
| 48 | Supplying all materials, labour T&P and fixing mirror of superior glass mounted on 6mm thick plywood sheet and fixed to wooden plugs with C.P screws and washers complete as per P.H specification and direction of E.I.C.-- 600mm x 450mm B.E. Mirror (fixed type) |
| 49 | Supplying all materials, labour T&P and fixing standard size C.P. towel rail / ring complete with c.p. brass brackets fixed to wooden plugs with c.p screws as per P.H specification and direction of E.I.C. -- 20 mm x 600 mm long C.P Towel rail |
| 50 | C.P. Towel Ring (St.) |
| 51 | Supplying all materials, labour T&P and fixing standard size C.P. soap holder complete with c.p brass brackets fixed to wooden plugs with cp screws as per PH specification and direction of E.I.C C.P.Soap Holder. |
| 52 | Supplying all , labour T&P and fitting, fixing of standard size Glass shelf with CP brass bracket and guard rails complete fixed to wooden plugs with CP screw as per specification and direction of E.I.C -- 450x125mm size Plate Acrylic Shelf |
| 53 | Supplying all labour, T&P, materials & fixing wash Kitchen sink with M.S brackets painted white including holes in walls and making good the damages etc. all complete as per P.H specification and direction of E.I.C. -- 600mm x 450mm x 200mm Stainless Steel sink.[Including C.P. Waste & PVC Waste Pipe] |
| 54 | Supplying all materials, labour T&P and costructing gully trap chamber of the following inside size with 8cm thick R.C.C. precast cover slab in c.c. (1:1 1.5:3) using 12 mm size h.g. chips foundation concrete (1:3:6) using 40 mm size h.g. metal on bed and arround trap Fly Ash brick work in c.m. (1:6) in F&P and inside 12mm thick c.p (1:3) finished with a floating coat of neat cement including fixing 100mm size H.C.I gully trap and grating etc. all complete as per approved drawing, specification and direction of E.I.C. Inside size 250mm x 250mm gully trap Chamber |
| 55 | Supplying all materials, labour T&P and constructing Inspection chamber of the following sizes with c.c (1:3:6) using 40mm size h.g. metal on bed, Ist class Fly Ash brickwork in c.m (1:6), moulding and shaping the channel inside and benching with c.c. (1:11/2:3) using 12mm size h.g. chips 12mm thick c.p. (1:3) with punning to inside cement flush pointing (1:3) to outside R.C.C. cover slab in c.c. (1:11/2:3) using 12 mm size h.g. chips with R.C.C. m.h. cover, e.w. in excavation in all kinds of soil and refilling the cavity arround the chamber including watering, curing, conveyance of all materials to site payment of royalty, taxes etc. all complete as per approved specification and direction of the E.I.C. Inside size 760mm x 760mm x 460mm I.C. |
| 56 | Supplying all materials, labour, T&P and laying 110 mm dia SWR pipes of the following O.D conforming to IS No. 13592 and aligning to requisite gradient inside the trench encasing all round of the pipe with c.c (1:3:6) using 4 CM size h.g. metal and CC(1:3:6) with 4CM size h.g. metal in the bed of the trench including lowering the pipes to the bed of the trench, earth excavation in trenches in all kinds of soil, refilling the same in layer of 0.3 mtrs with watering and ramming, removing of surplus earth, testing of sewerage line including use of T&P as per PH Specification and direction of E.I.C.- 110 mm dia SWR Pipe Sewerage line with all round encasing (conforming to IS No. 13592) |
| 57 | Supplying all materials, labour T&P and constructing soak way pit of the following sizes with dry brick walling form bottom up to invert of inlet pipe and 1st class Fly Ash brickwork in c.m(1:6) for the remaining height at top, 12 mm thick c.p(1:4) inside and outside over masonary brickwork gravel packing in the rear of well steining R.C.C. cover slab in c.c (1:11/2:3) using 12mm size h.g. chips fitted with iron lifting handles including e.w. in open well excavation in stoney earth and refilling the cavity around the pit & painting the iron works, watering , curing, conveyance of all materials to worksite, payment of royalty, taxes etc. all complete as per approved drawing, specification and direction of E.I.C.- 1.20mtrs.dia x 2.0mtr.deep soak way pit |
| 58 | Supplying all materials, labour, T&P and constructing soak way pit of the following sizes with precast R.C.C rings joined loose gravel backing in the rear of well steining, precast R.C.C cover slab in c.c.(1:1.5:3) using 12mm size h.g. chips fitted with iron lifting handles including e.w. in open well excavation in all kinds of soil and refilling the cavity around the pit & painting the iron works, watering ,curing, conveyance of all materials to worksite, payment of royality, taxes etc. all complete as per approved drawing, specification and direction of E.I.C.- 1.20 mtr dia x 2.00 mtr. deep RCC Ring Pit |
| 59 | Supplying all materials, labour, T&P and fixing rotational moulded polyethylene cylindrical vertical waterstorage tank confirming to IS 12701- 1996 including cutting hole through the tank and fixing MS tubes and fittings and providing extra sockets and jam nuts, fixing ball valve etc. including hoisting the tank and placing the tank to the required position including all complete as per specification and direction of EIC.(including cost of FG Over Head Tank) -- 1000 Ltrs. Capacity F.G.Over Head Tank. (on roof of 1st floor) |
| 60 | Supplying all materials, labour, T&P and Construction of masonary stagging with providing 1st class Fly Ash brick work in c.m, (1:6) of 0.46m. height in staging and in circular protection wall to support the tank in roof of ground floor using 25cm x 12cm x 8cm size Fly Ash bricks having crushing strength not less than 75 kg/cm2 12mm thick c.p.(1:4) over brick work, R.C.C. Slab of size 1.60mtr xl.60mtr x0.l0mtr thick, R.C.C. beam of size 0.25m x 0.30m and 2.60m average length in c.c.(1:1.5:3) using 12mm size h.g. chips including centering and shuttering, watering, curing conveyance of all materials to work site etc. all complete as per specification and direction of E.I.C -- For 1000 Ltr. Capacity Over Head Tank(on roof of 1st floor) |
| 61 | Supplying all materials, labour, T&P and providing and fixing to wall or ceiling and floor PVC Pipes conforming to ASTM-D-1785/89(sch-80) and pipe fittings of the following nominal bore with clamps including making good the wall, ceiling and floor testing all complete as per specification and direction of E.I.C - 20 mm dia PVC (ASTM) Pipe [Internal] |
| 62 | 25 mm dia PVC (ASTM) Pipe [Internal] |
| 63 | 25 mm dia PVC (ASTM) Pipe) [External] |
| 64 | 32 mm dia PVC (ASTM) Pipe) [External] |
| 65 | 32 mm dia HDPE Pipe [External Including E/W] |
| 66 | 32 mm dia HDPE Pipe [Inside Tube Well] |
| 67 | Supplying all materials,labourT&P and cutting holes through brick/stone masonary walls for taking water supply pipes and fittings including making good the damages etc.all complete as per P.H specification and direction of Engineer in charge |
| 68 | Supplying all materials, labour, T&P and cutting grooves in pucca floors and walls for taking G.I./P.V.C. pipes and making good the damages as per direction of the E.I.C. . |
| 69 | Supplying ail materials,labour,T&P and fitting & fixing brass/C.P fittings of the following nominal bore with supply of all jointing materials etc. complete as per P.H specification and direction of E.I.C.- 15mm dia. C.P Bibcock (Short body) [Plaza/ Amber Deluxe] |
| 70 | 15mm dia. C.P Bibcock (long body) [Plaza / Amber Deluxe] |
| 71 | 20mm dia.C.P Conceal stopcock [Plaza / Amber Deluxe] |
| 72 | 15mm dia.C.P Angle stopcock [[Plaza / Amber Deluxe] |
| 73 | 15mm dia C.P Pillar cock Swan Neck [Plaza / Amber Deluxe] |
| 74 | 15mm CP Two Way Bib cock[Plaza / Amber Deluxe] |
| 75 | 15mm dia C.P. Health Faucet [Plaza / Amber Deluxe] |
| 76 | 15mm dia C.P. Elbow Action Bib Cock [Plaza / Amber Deluxe] |
| 77 | 15mm dia C.P Flange |
| 78 | 15mm dia C.P Extension piece. |
| 79 | 25mm dia. PVC Ball valve [Metal Ball] |
| 80 | 32mm dia. PVC Ball valve [Metal Ball] |
| 81 | Supplying all materials, labour, T&P and fitting and fixing C.P. shower with 15 mm or 20 mm inlet with C. P. shower arm including polishing all complete as per P.H. specification and direction of E.I.C. |
| 82 | Supplying all materials, labour T&P and fitting & fixing 10 Litres capacity low level cistern with a pair of cast iron of m.s. brackets complete with fittings such as siphonic arrangements 15mm nominal size brass/pvc ball valve with polythene float, c.p. brass handle, unions and couplings for connection with inlet, outlet and overflow pipe. 32 mm C.P flush bend 15mm PVC inlet connection pipe including cutting holes and making good the same and connecting the flush bend with cistern and closet and connecting inlet pipe with supply main etc. all complete as per specification and direction of E.I.C (Cerra/ Parry ware/ Hindware) |
| 83 | Sinking of 125x50mm Tubewell through Hand Boring Method- Supplying all materials, labour, T&P and setting up boring equipments including irrection of suitable stagging for installation of the required size of tube-well. Dismantling & removing the same after completion of the work including transportation of boring equipments clearing & leveling the site, excavation of mud pit channels etc., leveling of site all complete as per direction of E.I.C(Labour) including cost of transportation of materials etc. complete. |
| 84 | Supplying all labour, T&P & transportation of boring pipes, top casing, grouping pipes, PVC pipes and fitting, PVC well screens, cement, betonite etc. including loading and unloading etc. complete as per direction of the E.I.C.(Labour) |
| 85 | Supplying all labour, T&P and drilling pilot bore not less than 102mm dia without casing pipes in all kinds of soil and rocks for the following depths excluding supply of necessary boring pipes including supply of necessary cutting equipments extra sockets etc.and withdrawing the boring pipes washing & keeping the bore clear for logging if required all complete as per the direction of EIC-- Pilot bore 100mm dia (00 mtr. to 360 mtr.) |
| 86 | Supplying all labour, T&P & reaming the pilot bore to the following sizes and depths without casing pipes including withdrawing the boring pipes, washing the bore by means of pipe cylinder etc. all complete as per direction of E.I.C. -100 mm ot 150 mm dia( 00 mtr to 360 mtr) |
| 87 | 150 mm to 200 mm dia( 00 mtr to 360 mtr) |
| 88 | 200 mm to 250 mm dia( 00 mtr to 360 mtr) |
| 89 | Supplying all labour, Tools and plant and lowering the 300mm dia top casing pipe into position and removing the same after use as per the direction of Engineer-in-charge. |
| 90 | Supplying all labour, T&P and jointing materials and lowering the PVC casing pipes fitting and well screens in position including fitting of centralizer cutter plugs and washing the bore as per the direction of E.I.C.(Including cost of Materials) 125 mm dia PVC Pipe (Schedule-80) |
| 91 | 50 mm dia PVC Pipe (Schedule-80) |
| 92 | 50 mm dia PVC strainer |
| 93 | 125x50 mm dia PVC R/S |
| 94 | 50 mm dia C.I.Plug Cutter |
| 95 | Lowering of 125/100mm dia PVC Pipe |
| 96 | Lowering of 50mm dia PVC Pipe |
| 97 | Supplying all labour, T & P and packing the bore with washed gravel ( size-P-6) around the pipes in good quality including cost of gravel etc. all complete as per direction of Engineer-in-Charge- |
| 98 | Cost of Gravel |
| 99 | Supplying all labour, T&P materials and providing sanitary sealing by cement slurry grouting around the uppermost 3.00 mtrs. of 125 mm dia PVC casing pipe . including cost of cement all complete as per direction of E.I.C (including cost of 2 bags of Cement) |
| 100 | Cleaning the developing the tube well using compressor continuously to get clear and adequate discharge from the tube well including the supply and use of all necessary equipment and labour as per direction of E.I.C(Labour Charges) |
| 101 | Supplying of ISI Mark 1.00 HP Single Phase Vertical Submersible Pump Set with Discharge of 900-1000 liter/hour and a head of 50-60 mtr of reputed make like KSB/Texmo & Equivalent including all cost, conveyance and taxes etc. all complete as per direction of Engineer-in-charage. |
| 102 | Supplying all labour, T&P and fitting and fixing of 1.00 HP Single phase vertical Submersible Pump Set with commissioning and testing etc. all complete as per direction of Engineer-in-charge. |
| 103 | Supplying and fitting and fixing of ISI Mark DOL Starter of reputed make like BCH or Equivalent for 1.00 HP Single Phase Submersible Pump including all cost, conveyance and taxes etc. all complete as per direction of Engineer-in-charge. |
| 104 | Supplying and fitting and fixing of three core flat cable (1.5mm2) of ISI Make of reputed company line BCH/Finolex or Equivalent and connecting the pump and starter including all cost, conveyance and taxes etc. all complete as per direction of Engineer-in-charge. |
| 105 | Supplying and fitting & fixing of Plastic rope, M.S. Well Cover, M.S. Clamp, Stainless Steel Short piece, Bend & Socket including all const, conveyance and taxes etc. all complete as per direction of engineer-in-charge. Please Enable Macros to View BoQ information |
AI Tender Summary
Tender Timeline
Nov 13, 2026
11:30 IST
Tender Published
Tender notice published.
CompletedNov 23, 2026
17:00 IST
Bid Submission Deadline
Online submission via eProcurement portal.
Upcoming · 8 daysNov 25, 2026
Bid Opening Date
Technical bids will be opened and evaluated.