Tender For Improvement Road From Nh-66 To Heggara Magoda Nagara Bastikeri Road From Km.17.00 To Km.31.00 In Uttara Kannada District
Tender Value
3.26 Crore
Estimated cost
Bid Submission
14 Dec 2026
27 days left
EMD
4.89 Lakhs
Bank guarantee accepted
Document Fee
8850
Non-refundable
Tender Type
Online
Tender Overview
Organization
Tender ID
Competition Type
NCB
Bidding Type
Tender
Location / State
Uttara Kannada → Karnataka
EMD Exemption
Not Available
Quantity
Not Available
Website
Contact Person
Address
Project Description
Tender for Improvement Road From Nh-66 To Heggara Magoda Nagara Bastikeri Road From Km.17.00 To Km.31.00 In Uttara Kannada District
BOQ
| Sl. No. | Item Description |
| 1 | Clearing and grubbing road land including uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps of trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned up to a lead of 1000 meters including removal and disposal of top organic soil not exceeding 150 mm in thickness.including all labour, usage charges of all machinery etc., complete. (for new roads),In area of light jungle - By Mechanical Means using Dozer\\" NH Zone SR 2022-23 continued for the Year 2026-27 , Pg No.7, It no. 2.03(ii)Aas per the directions of the Engineer in charge. |
| 2 | construction of unlined surface drains of average cross sectional area 0.40 sqm in soil to specified lines, grades, levels and dimension to the requirement of clause 301 and 309. Excavated materail to be used in embackment within a laod of 1000 meters including all labours, load, unload, usage charges of all machinery etc., complete. Ref. to MoRT&H Specification 309 NH Zone SR 2022-23 continued for the Year 2026-27 (Page No 25 Item No 3.25 A)as per the directions of the Engineer in charge. |
| 3 | Earthwork excation for road way in soil by mechanical means using dozer including cutting and pushing the earth to site of embankment upto a distance of 1000meters including trimming bottom and side slope in accordence cross section, including all labours, all labours, load, unload usage charges of all machineries etc., complete. (cutting & filling )and as per the directions of the Engineer in charge. NH Zone SR 2022-23 continued for the Year 2026-27 , Pg No.15, It no.3.03 |
| 4 | Construction of granular sub-base by providing close graded Material, mixing in a mechanical mix plant at OMC, carriage of mixed Material to work site, spreading in uniform layers with motor grader on prepared surface and compacting with vibratory power roller to achieve the desired density, complete as per clause 401 including protection of edges of GSB layer, cost of all materials, labour, usage charges of all machinery, lighting, guarding, barricading, maintenance of diversion road, loading & unloading all lead, lifts etc., complete with including lead of mixed material (Compacted thickness) Grading-II Material (Close graded).and as per the directions of the Engineer in charge. NH Zone SR 2022-23 continued for the Year 2026-27 , Pg No.32 , It no. 4.01A ii |
| 5 | Providing, laying, spreading and compacting graded stone aggregate as per table 400-12 & 400-13, to wet mix macadam specification including premixing the Material with water at OMC in mechanical mix plant carriage of mixed Material by tipper to site, laying in uniform layers in sub- base / base course on well prepared surface and compacting with vibratory roller to achieve the desired density of 98% including protection of edges of WMM layer, cost of all materials, labour, usage charges of all machinery, lighting, guarding, barricading, maintenance of diversion road, loading & unloading all lead, lifts etc., complete, Including lead of mixed material (Compacted thickness).Laying Using Grader, and as per the directions of the Engineer in charge. NH Zone SR 2022-23 continued for the Year 2026-27 , Pg No.44, It no. 4.14B |
| 6 | Providing and applying primer coat with SS1 bitumen emulsion complying IS-8887 on prepared surface of granular Base including clearing of road surface and spraying primer at the rate of 0.70 kg/sqm using mechanical means.as per table-500-3, including cost of all materials, labour, usage charges of all machinery, loading & unloading etc., complete, Including lead for emulsion. and as per the directions of the Engineer in charge. NH Zone SR 2022-23 continued for the Year 2026-27 , Pg No.51, It no. 5.02 A i |
| 7 | Providing and applying tack coat with VG-10 grade bitumen using bitumen pressure distributor at the rate of 0.20 kg per sqm on the prepared bituminous surface cleaned with mechanical broom, & dusting by air compressor and spraying including cost of all materials, labour, usage charges of all machinery, loading & unloading etc., complete, execpt lead for bitumen. NH Zone SR 2022-23 continued for the Year 2023-24 & 2026-27 Page No 53 Item No 5.02 i c as per the directions of the Engineer in charge. |
| 8 | Providing and applying tack coat with VG 10 grade bitumen using bitumen pressure distributor at the rate of 0.25 kg per sqm on the prepared granular surface cleaned with mechanical broom & dusting by air compressor and spraying including cost of all materials, labour, usage charges of all machinery, loading & unloading etc., complete, including lead for bitumen. NH Zone SR 2022-23 continued for the Year 2026-27 , Pg No54 Item No 5.02.iii c as per the directions of the Engineer in charge. |
| 9 | Providing and laying dense graded bituminous macadam with higher capacity batch type HMP using crushed aggregates as per table 500-7 of specified grading premixed with bituminous binder VG-30 paving bitumen as per clause 504.3.1 complying with IS-73-2013 of specified grading, premixed with bituminous binder at 4.5 per cent by weight of total mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MoRTH specification clause No. 505 complete in all respects including cost of all materials all labour, usage charges of all machinery all lead, lifts, loading, unloading stacking transporting etc., complete, including lead for bitumen, with a lead of mixed material upto 1 km, excluding cost of primer/ tack coat- 50-75 mm compacted thickness. NH Zone SR 2022-23 continued for the Year 2026-27 , Pg No59 Item No 5.04 ii a as per the directions of the Engineer in charge. |
| 10 | Providing and laying bituminous concrete with higher capacity batch type hot mix plant using crushed aggregates as per table 500-7 of specified grading premixed with bituminous binder VG-30 paving bitumen as per clause 504.3.1 complying with IS-73-2013 of specified grading, premixed with bituminous binder @ 5.4 per cent of mix and filler @2% by weight of agregate, transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MORTH specification clause No. 507 complete in all respects including cost of all materials all labour, usage charges of all machinery all lead, lifts, loading, unloading stacking transporting etc., complete, including lead for bitumen, with a lead of mixed material upto 1 km, excluding cost of primer/ tack coat - 30-40 mm compacted thickness.NH Zone SR 2022-23 continued for the Year 2026-27 , Pg No61 Item No 5.05.ii a as per the directions of the Engineer in charge. |
| 11 | Construction of sub-grade and earthen shoulders with Material Deposited from Roadway Cutting transporting to site, spreading, grading to required slope and compacted to meet requirement of table No. 300-2 laid in layers not exceeding 250 mm thick and compacting it by mechanical means after adding water to its OMC, so as to achieve 97% compaction of maximum dry density and finish the surface to the required camber, grade and cross section etc., speading, grading by motor grador , consolidation by roller including all lead, lifts, loading, unloading, all labour, usage charges of all machinery etc., complete. NH Zone SR 2022-23 continued for the Year 2026-27 , Pg No23 Item No 3.20 as per the directions of the Engineer in charge. |
| 12 | Construction of sub-grade and earthen shoulders with approved material obtained from borrow pits, transporting to site, spreading, grading to required slope and compacted to meet requirement of table No. 300-2 laid in layers not exceeding 250 mm thick and compacting it by mechanical means after adding water to its OMC, so as to achieve 97% compaction of maximum dry density and finish the surface to the required camber, grade and cross section etc., speading, grading by motor grador, consolidation by roller including all lead, lifts, loading, unloading, all labour, usage charges of machinery etc., complete. (New road formation) NH Zone SR 2022-23 continued for the Year 2026-27 , Pg No22 Item No 3.18 as per the directions of the Engineer in charge. |
| 13 | Road marking with Hot applied Thermoplastic compound with Reflectorising glass beads on bituminous surface providing and laying of hot applied thermoplastic compound 2.5mm thick including reflectiorising glass beads at 250gms per sqm area, thickness of 2.5 mm is exclusive of surface applied glass beads as per IRC:35. The finished surface to be level, uniform and free from streaks and holes,including, barricading , traffic diversion as per IRC- 3, cleaning the surface of dirt, dust and other foriegnmatter, demarcation at site, traffuc control, cost of all materials all labour lead, lifts, loading, unloading transporting etc., complete.Ref. to MoRT&H Specification 507(2.5mm thick) NH Zone SR 2022-23 continued for the Year 2026-27 , Pg No109 Item No 8.13 as per the directions of the Engineer in charge. |
| 14 | Supplying & Fixing of Molded Shank Raised Pavement Markers / Cat's Eye made of polycarbonate and ABS moulded body and reflective panels with micro prismatic lens capable of providing total internal reflection of the light entering the lens face and shall support a load of 16000 kg tested in accordance to ASTM D 4280 Type H and complying to Specifications of Category A of MORTH Circular No RW/NH/33023/10-97 DO III Dt 11.06. 1997. The height, width and length shall not exceed 50 mm, 100 mm and 102 +/- 2 mm and with minimum reflective area of 13 cm2 on each side and the slope to the base shall be 35 +/- 5 degree. The strength of detachment of the integrated cylindrical shanks, (of diameter not less than 19 +/- 2 mm and height not less than 30+/- 2 mm) from the body is to be a minimum value of 500 Kg. Fixing will be by drilling holes on the road for the shanks to go inside, without nails and using epoxy resin based adhesive as per manufacturer's recommendation and complete as directed by the engineer.The contractor shall submit a two year warranty (PWD SR 2023-24) 8.43 Pg No : 73 |
| 15 | Providing and erecting Project Disply board of size 1.80 vertical x 1.6 M Horizontal made of Cold Rolled Coil Sheet 16 Guage (1.6 mm thickness) sheering sthrenghtened by welding to MS angle of size 35x 35x5 mm iron framework on all sides, extra cross vertical angle fixed using nuts and bolts, base of the board shall be cleaned, applying red oxide and black paint by sprayer on both side of the board and all MS iron framework, background of the facing side of the board painting in traffic yelloew, project information written in englisgh /kannada/ hindi , painting letters and numbers in black fixed on a mild steel angle iron post 75mm x75mm x 6mm, 2nos. firmly fixed to the ground by means of properly designed foundation with M15 grade cement concrete 45 cm x45cm x 60 cm, 60cm below ground level and the board 2.8 m from ground level as per apprved drawing ( excluding cost of lattering ) including cost of all materials all labours, lead, lifts, loading, unloading transporting etc., complete NH Zone SR 2022-23 continued for the Year 2026-27 , Pg No254 Item No 4 as per the directions of the Engineer in charge. |
| 16 | Network Survey Vehicle (NSV) attached with SUV Data collection of Longitudinal profiling (International roughness Index) . Transverse profiling (Rut depth) Pavement texture in terms of Mean profile depth , Road Geometry data, (Cross slope, gradient, curvature), GPS Coordinates (X, Y, Z) viz longitudinal, latitude & altitude, Video Imaging for Road side furnitures / Road assets and Video imaging for pavement surface Distress and reports. as per Direction of Engineer in charge.NH Zone SR 2022-23 continued for the Year 2026-27 , Pg No141 Item No 10.17 as per the directions of the Engineer in charge. |
| 17 | Excavation for Structures: Earth work in excavation of foundation of structures as per drawing and technical specification, including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom and backfilling with approved material. including cost of all labour, material, usage charges of all machinery, lead, lifts, loading, unlodaing, etc., Complete.i) Ordinary soil, B) Mechanical means (Depth upto 3m) NH Zone SR 2022-23 continued for the Year 2026-27 , Pg No;130 Item No 9.01, I-B (i) |
| 18 | Providing & laying Plain/Reinforced Cement Concrete 1:3:6 in foundation with crushed stone aggregates 40mm nominal size mechanically mixed, placed in foundation and compacted ny vibration including curing, cost of all materials, all labour, usage charges of machinery, lead, lifts, loading, unloading, transporting, etc., complete. NH Zone SR 2022-23 continued for the Year 2026-27 , Pg No; 131 Item No 9.03 as per the directions of the Engineer in charge. |
| 19 | Plain/Reinforced Cement Concrete in Open Foundation complete as per Drawing and Technical Specifications including cost of all materials, formwork, centring, vibrating, compacting, usage charges of machinery, lead, lift, loading, unloading, transporting, stacking, curing, finishing the exposed faces etc., complete (excluding cost of steel and fabrication charges) C-Case-II) RCC Grade M20 using batching plant transit mixer & manual placing NH Zone SR 2022-23 continued for the Year 2026-27 , Pg No;134 Item No; 9.06 C-case-II |
| 20 | Supplying, Fitting and Placing un-coated TMT Fe 500 grade bar reinforcement in Foundation including cost of all labour, materials, usage charges of machinery, fabrication charges, straightening bars, cutting, bending, hooking, binding with approved quality binding wire, after placing in position, tyeing, lapping and / or welding where ever required (laps, hooks and wastages shall not be measured and paid) with all lead, lifts, loading , unloading, Transporting, stacking neately etc., complete as per drawing and technical specifications NH Zone SR 2022-23 continued for the Year 2026-27 , Pg No;134 Item No; 9.07 as per the directions of the Engineer in charge. |
| 21 | Excavation for Structures: Earth work in excavation of foundation of structures as per drawing and technical specification, including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom and backfilling with approved material. including cost of all labour, material, usage charges of all machinery, lead, lifts, loading, unlodaing, etc., Complete.i) Ordinary soil, B) Mechanical means (Depth upto 3m) NH Zone SR 2022-23 continued for the Year 2026-27 , Pg No;130 Item No;9.01, I-B (i) as per the directions of the Engineer in charge. |
| 22 | Providing & laying Plain/Reinforced Cement Concrete 1:3:6 in foundation with crushed stone aggregates 40mm nominal size mechanically mixed, placed in foundation and compacted ny vibration including curing, cost of all materials, all labour, usage charges of machinery, lead, lifts, loading, unloading, transporting, etc., complete NH Zone SR 2022-23 continued for the Year 2026-27 , Pg No; 131 Item No; 9.03as per the directions of the Engineer in charge. |
| 23 | NP4/ Prestressed concrete Pipe 1000 mm dia for double row Providing & laying Reinforced cement concrete pipe NP4/ prestressed concrete pipe for culverts on first class bedding of granular material in double row, including fixing collar with with cement mortar 1:2, but excluding excation, protection works, backfilling, concrte and masonry works in headwall and parapetes, including cost of all materials all labour, usage charges of machinery, lead, lifts, loading, unloading transporting etc., complete. as per the directions of the Engineer in charge. |
| 24 | Plain/Reinforced Cement Concrete in Open Foundation complete as per Drawing and Technical Specifications including cost of all materials, formwork, centring, vibrating, compacting, usage charges of machinery, lead, lift, loading, unloading, transporting, stacking, curing, finishing the exposed faces etc., complete (excluding cost of steel and fabrication charges) C-Case-II) RCC Grade M20 using batching plant transit mixer & manual placing NH Zone SR 2022-23 continued for the Year 2026-27 , Pg No; 134 Item No; 9.06 C-case-II |
| 25 | Supplying, Fitting and Placing un-coated TMT Fe 500 grade bar reinforcement in Foundation including cost of all labour, materials, usage charges of machinery, fabrication charges, straightening bars, cutting, bending, hooking, binding with approved quality binding wire, after placing in position, tyeing, lapping and / or welding where ever required (laps, hooks and wastages shall not be measured and paid) with all lead, lifts, loading , unloading, Transporting, stacking neately etc., complete as per drawing and technical specifications NH Zone SR 2022-23 continued for the Year 2026-27 , Pg No; 134 Item No;9.07 as per the directions of the Engineer in charge. |
| 26 | Construction of embankment with approved material obtained from borrow pits laid in layers not exceeding 250 mm loose thickness, spreading, breaking clods, removal of roots and other organic materials to the required line, grade and cross section including watering, consolidation by roller to the desired field density not less than 95% of maximum dry density including all lead, lifts, loading, unloading, all labour, usage charges of all machinery etc., complete as per table 300-2. as per the directions of the Engineer in charge. |
| 27 | Construction of granular sub-base by providing close graded Material, mixing in a mechanical mix plant at OMC, carriage of mixed Material to work site, spreading in uniform layers with motor grader on prepared surface and compacting with vibratory power roller to achieve the desired density, complete as per clause 401 including protection of edges of GSB layer, cost of all materials, labour, usage charges of all machinery, lighting, guarding, barricading, maintenance of diversion road, loading & unloading all lead, lifts etc., complete with including lead of mixed material (Compacted thickness) Grading-II Material (Close graded).and as per the directions of the Engineer in charge. NH Zone SR 2022-23 continued for the Year 2026-27 , Pg No.32 , It no. 4.01A ii |
| 28 | Providing, laying, spreading and compacting graded stone aggregate as per table 400-12 & 400-13, to wet mix macadam specification including premixing the Material with water at OMC in mechanical mix plant carriage of mixed Material by tipper to site, laying in uniform layers in sub- base / base course on well prepared surface and compacting with vibratory roller to achieve the desired density of 98% including protection of edges of WMM layer, cost of all materials, labour, usage charges of all machinery, lighting, guarding, barricading, maintenance of diversion road, loading & unloading all lead, lifts etc., complete, Including lead of mixed material (Compacted thickness).Laying Using Grader, and as per the directions of the Engineer in charge. NH Zone SR 2022-23 continued for the Year 2026-27 , Pg No.44, It no. 4.14B |
| 29 | Providing and applying tack coat with VG 10 grade bitumen using bitumen pressure distributor at the rate of 0.25 kg per sqm on the prepared granular surface cleaned with mechanical broom & dusting by air compressor and spraying including cost of all materials, labour, usage charges of all machinery, loading & unloading etc., complete, execpt lead for bitumen. NH Zone SR 2022-23 continued for the Year 2026-27 , Pg No54 Item No 5.02.iii c as per the directions of the Engineer in charge. |
| 30 | Painting on concrete surface, Providing and applying 2 coats of water based cement paint to unplastered concrete surface after cleaning the surface of durt, dust, oil grease, efflorescence and applying paint @ the rate of 1 litre for 2 sqm. including cost of all labour, material, usage charges of machinery, lead, lifts, loading, unloading, transporting, etc., complete. as per the directions of the Engineer in charge. Please Enable Macros to View BoQ information |
AI Tender Summary
Tender Timeline
Nov 12, 2026
11:30 IST
Tender Published
Tender notice published.
CompletedDec 14, 2026
17:00 IST
Bid Submission Deadline
Online submission via eProcurement portal.
Upcoming · 27 daysDec 15, 2026
Bid Opening Date
Technical bids will be opened and evaluated.
Upcoming · 28 daysTender Documents
Download All (ZIP) ↓
Disclaimer
We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender