Tender For Supply, Erection, Testing & Commissioning Of 110 Kv Dc Line On Dc Towers For Making Lilo Of S.R.Pudur-Kadayar-Ii Feeder At Proposed Kulasekaram 110/11Kv.
Tender Value
Ref. Documents
Estimated cost
Bid Submission
26 Nov 2026
9 days left
EMD
64500
Bank guarantee accepted
Document Fee
Ref. Documents
Non-refundable
Tender Type
Online
Tender Overview
Organization
Tender ID
Competition Type
NCB
Bidding Type
Tender
Location / State
Kanniyakumari → Tamil Nadu
EMD Exemption
Available
Quantity
Not Available
Website
Contact Person
Address
Project Description
Tender for Supply, Erection, Testing & Commissioning Of 110 Kv Dc Line On Dc Towers For Making Lilo Of S.R.Pudur-Kadayar-Ii Feeder At Proposed Kulasekaram 110/11Kv.
BOQ
| Sl. No. | Item Description |
| 1 | Supplying, fabricating, galvanising tower parts as per ISS or relavent standards and specification including cost of materials, galvansing charges, and transporting charges to site store, furnishing test certificate etc., complete.Mild steel |
| 2 | Supplying, fabricating, galvanising tower parts as per ISS or relavent standards and specification including cost of materials, galvansing charges, and transporting charges to site store, furnishing test certificate etc., complete.HT steel |
| 3 | Supply of Hot tipped GI Bolts & Nuts, Step bold & washers of various size as per ISI /relevent specification as per the requirement including cost of material lead lift labour etc complete. |
| 4 | Supplying of ACSR Panther condutor as per techinical specification including cost of materials, transport, lead, lift etc., complete |
| 5 | Supply of OPGW (48 fibres) with accessories |
| 6 | Supply of OFC cable (48 fibres) with splicing box, HDPE pipe and FODP Panel |
| 7 | Transporting and hoisting of 90KN suspension insulators of 7 units including cost of labour lead lift T & P etc complete |
| 8 | Supplying of 120 KN ordinary disc insulators of approved make and quality including cost of materials, transport, lead, lift etc., complete |
| 9 | Supplying of Single Suspension fittings for ACSR Panther fittings including cost of materials, transport charges, loading, unloading, head load, lead if any, lift, etc., complete. |
| 10 | Supplying of Single tension fittings for ACSR Panther including cost of materials, transport charges, loading, unloading, head load, lead if any, lift, etc., complete. |
| 11 | Supplying of SB damper for ACSR Pantherincluding cost of materials, transport charges, loading, unloading, head load, lead if any, lift, etc., complete. |
| 12 | Supply of Phase plate (set of three) |
| 13 | Supplying of Number plate |
| 14 | Supplying of Danger Board |
| 15 | Supplying of Circuit plate |
| 16 | Conducting reconnaissance survey including ranging rod alignment including cost of materials, transport of men & materials, hire charges for survey tools & plants, etc., complete. |
| 17 | Conducting detailed survey by conducting Total station alignment using GPS for coordinates and plotting the profile in the tracing sheet using Indian ink and lettering using stencils with suitable scale and preparing of tower schedule including cost of materials, labour, lead, lift, etc., complete. |
| 18 | Conducting detailed survey by conducting Total station alignment using GPS for coordinates and plotting the profile in the tracing sheet using Indian ink and lettering using stencils with suitable scale and preparing of tower schedule including cost of materials, labour, lead, lift, etc., complete. |
| 19 | Preparation and submission of profile roll and booklet with connected records |
| 20 | Conducting Check Survey in the already fixed route, fixing of tower locations and pit marking, jungle clearance, tree cutting etc, complete. |
| 21 | Earth work excavating and depositing on bank with initial lead of 10 m & initial lift of 2m in Hard stiff clay, stiff black cotton, hard red earth, shales, murram, gravel, stoney earth and earth mixed with small size boulders SS.20B |
| 22 | Earth work excavating and depositing on bank with initial lead of 10 m & initial lift of 2m in Soft disintegrated rock, laterite, soft rock or kankar, not requiring blasting. |
| 23 | Hard rock measured in solid including blasting & stacking |
| 24 | Dewatering using 3/5 HP diesel engine during excavation and concreting including fuel charges, lead and lift etc., complete. |
| 25 | Providing shoring & shuttering in foundation using wooden planks, scantling etc compete. |
| 26 | Transporting of template and stub sto site and assembling at site and shifting the template from Loc. to Loc. and back to store for QD Tower |
| 27 | Transporting of template and stub sto site and assembling at site and shifting the template from Loc. to Loc. and back to store for KCO Tower |
| 28 | Providing PCC 1:3:6 without formwork using 40mm size machine crushed HBG metal including cost of materials, labours, lead, lift, curing, etc. complete |
| 29 | RCC 1:1.5:3 using 20 mm metal with form work for foundation including cost of materials, labour, vibrater, lead, lift, curing, hire charges for T&P, etc., complete. but excluding the cost of steel reinforcement. |
| 30 | RCC 1:1.5:3 using 20 mm metal withform work for foundation including cost of materials, labour, vibrater, lead, lift, curing, hire charges for T&P, etc., complete. but excluding the cost of steel reinforcement. |
| 31 | Supplying and fabricatiion and placing in position of MS/RTS steel reinforcement for RCC works including labour, for cutting, bending, tying and fixing in position as per specification including cost of materials, lead, lift, labour, cost of binding wire etc complete. |
| 32 | PCC 1:2:4, using 20mm HBG metal for foundation with form work including cost of cement all materials, labour, lead, lift, curing, formwork charges, hire charges for T&P etc., complete. For Frustum & Chimney. |
| 33 | Refilling with excavated earth for pits including watering and consolidating in 150mm thick and spreading the balance earth around the location labour charge, lead and lift etc., complete. |
| 34 | Providing pipe type earthing including necessary excavation for fixing 3m long 25mm dia GI \\"B\\" class pipe and refilling with excavated earth mixed with soft charcoal and connect the earthstrip with the leg of the stub including cost of materials lead lift etc complete. |
| 35 | Labour charges for erection of towers including sorting out of tower parts tightening, punching of bolts and nuts and rectification of defects if any during erection cost of materials, labour, lead, lift, etc., complete. |
| 36 | Transporting and hoisting of 90KN suspension insulators of 7 units including cost of labour lead lift T & P etc complete |
| 37 | Transporting and hoisting of 120KN tension insulators of 8 units including cost of labour lead lift T & P etc complete |
| 38 | Arranging and Lowering the HT/LT Line during stringing and after restringing the same in original position including labour, lead, lift etc complete |
| 39 | Labour charges for fixing of number plates, danger board, phase plate, Circuit plate including labour transport, lead, lift, etc complete |
| 40 | Supplying and fixing of 16swg MS sheet 90cm x 30cm name board including cost of writing name of the line, MS sheet etc complete |
| 41 | Transport of Panther conductor, paying out, jointing, rough sagging, tensioning, clipping, providing vibration dampers for tension locations including giving jumber connection for power conductor including transport charges, loading unloading lead lift etc complete. 6 No. Panther conductor - Single span without LC |
| 42 | Transport of Panther conductor, paying out, jointing, rough sagging, tensioning, clipping, providing vibration dampers for tension locations including giving jumber connection for power conductor including transport charges, loading unloading lead lift etc complete. 6 No. Panther conductor - Single span with LC |
| 43 | Installation & stringing of 1No. OPGW 48 Fibres including fixing of hardware fittings and accessories etc., complete for the line (Stringing of OPGW is to be done using tension stringing equipment) |
| 44 | PCC 1:2:4 using 20mm HBG metal for muffing and coping with necessary form work including cost of all materials, labour, all lead lift etc., complete. |
| 45 | Plastering with C.M 1:3, 12mm thick including cost of all materials, labour, lead, lift curing, etc., complete. |
| 46 | Painting with anticorrosive paint two coats including cost of materials, lead, lift, etc., complete |
| 47 | Providing temporary guys including necessary excavation fixing of rails, back filling etc., complete. |
| 48 | Providing full welding of all bolts and nuts in the erected towers from ground level to the cross arm bottom level in the tower including painting of bolts and nuts with two coats of best quality of cold galvanised paint having atleast 90% zinic content and approved by the Engineer at site including cost of paint and all other materials hire charges for diesel generator and welding transformer all labour transport charges etc complete. |
| 49 | Removal of surplus earth wherever necessary including transport up to 200m away from the site, loading and unloading etc., complete |
| 50 | Providing earthing arrangements for terminal towers including necessary excavation for fixing 3m long 50mm dia GI B class pipe RCC collar and refilling iwith exccavated earth mixed with soft charcoal and connect the earth strip either leg of the stubst of all materials labnour lead lift etc., complete |
| 51 | Releasing and Lowering and restringingof 110 EHT line before stringing of new EHT line including labour, lead, lift, T&P etc. complete. with LC |
| 52 | SGST to be quoted in Percentage (value alone) Ex. 9%, it should be entered as 9 only |
| 53 | CGST to be quoted in Percentage (value alone) Ex. 9%, it should be entered as 9 only |
| 54 | Inter-state GST @18% for other than Tamil Nadu supplier. If the contractor is within Tamil Nadu may be quoted as \\"0\\" only Please Enable Macros to View BoQ information |
AI Tender Summary
Tender Timeline
Nov 11, 2026
11:30 IST
Tender Published
Tender notice published.
CompletedNov 26, 2026
17:00 IST
Bid Submission Deadline
Online submission via eProcurement portal.
Upcoming · 9 daysNov 27, 2026
Bid Opening Date
Technical bids will be opened and evaluated.
Upcoming · 10 daysTender Documents
Download All (ZIP) ↓
Disclaimer
We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender