Tender For Maintenance Of Pantoon Bridge On Ganga River Between Gahmar & Firojpur (2026-27)
Tender Value
32 Lakhs
Estimated cost
Bid Submission
12 Nov 2026
5 days left
EMD
3.20 Lakhs
Bank guarantee accepted
Document Fee
854
Non-refundable
Tender Type
Online
Tender Overview
Organization
Tender ID
Competition Type
NCB
Bidding Type
Tender
Location / State
Ghazipur → Uttar Pradesh
EMD Exemption
Available
Quantity
Not Available
Website
Contact Person
Address
Project Description
Tender for Maintenance Of Pantoon Bridge On Ganga River Between Gahmar & Firojpur (2026-27)
BOQ
| Sl. No. | Item Description |
| 1 | Supply of wooden anchors made of Uquiliptis ballies of standerd design of size of 2.80x1.80x1.80 m. with different size of ballies, mallahi, nails and cost of cartage, labour and T&P etc complete |
| 2 | Supply of 28 mm. dia garware Garphy poly propline ISI mark rope for anchoring of pantoons i/c cost of materials its loading , unloading cartage upto Gahmar ghat store ..(as per schedule pg 28 item 39) |
| 3 | S/O sand filled plastic E.C. bags (Valume 1 Cft ) i/c cost of sand , bags labour stiching with sutly complete and cartage upto place of anchoring . (as per schedule pg 27 item no.2) |
| 4 | S/O narial rope of good quality i/c cost of materials cartage up to site etc . complete. (as per schedule pg 27 item no12) |
| 5 | S/O malahi nails 15cm to 30cm long of approved make and good quality . (as per schedule pg 27 item no 11) |
| 6 | S/O Euqiliptis ballies of dia150mm i/c cost of materials cartage upto site and loading , unloading etc. at Bachchalpur ghat store .(as per schedule pg 28 item no 35(a)) |
| 7 | same as above but 120mm dia |
| 8 | same as above but 100mm dia |
| 9 | S/O nut bolts of following size i/c cost of all materials cartage upto site etc. complete .as per page no.27 item no.6,7,8 300x30mm |
| 10 | 150x30mm |
| 11 | 300x16mm |
| 12 | Supply of railing wire clamp i/c cost of all materials cartage upto site etc complete. (as per schedule pg 27 item no 10) |
| 13 | S/O wire rope (Steel coated) i/c cost of all materials cartage upto site etc. complete for railing post .(as per schedule pg 28 item no 40) 20 mm. |
| 14 | 10 mm. |
| 15 | S/O U clamp for clamping chequred plates i/c cost of all materials cartage upto site etc. complete .(as per schedule pg 27 item no 9) |
| 16 | Carrying of pantoon pairs from the place of anchoring (down steram side of the bridge) top the alignment of bridge in water and fixing the same with other pantoon pair and refixing the same and bridge alignment.(as per schedule pg 25 item no 3a) |
| 17 | Cartage of the following items from Gahmar ghat store to bridge site and laying fixing them on bridge and approaches .(as per schedule pg 29 item no 9) R.S. Joints |
| 18 | Nut bolts |
| 19 | Coir rope / PP rope |
| 20 | Chequered plates |
| 21 | Railing post |
| 22 | Carrying of wooden anchor from store to site.(as per schedule pg 25 item no 12) |
| 23 | Laying of wooden anchor in the river on the up stream and down stream side of pantoon bridge i/c their weaving and packing with sand filled bags average 90 bags before laying and fixing the pantoon with sisal / coire rope as directed by E/I. (as per schedule pg 25 item no 6) |
| 24 | Levelling and dressing (4 cm.) deep of road before laying chequred plate. |
| 25 | Relaying of chequrd plates after making camber by spreading of local sand (as per schedule pg 25 item no 13) |
| 26 | Cartage the following items from Gahmar ghat store to Gahmar ghat pantoon bridge and laying / fixing indecking of bridge etc. complete .(as per schedule pg 25 item no 9) Sal sleeper |
| 27 | Sal edging |
| 28 | Clamping of Chequared plates with U clamp and nut bolts all as directed by E/I. Labour Only |
| 29 | Fixing of 10 mm. wire rope in railing post . |
| 30 | Two coat enamal painting on railing post i/c cost of materials labour T&P etc. complete . |
| 31 | Painting and lettering of sign board with all materials labour T&P etc. complete of size 3\\"x4\\" |
| 32 | Earth work in cutting or embankment in ordinary soil excavated to be in the form regulers pits not exceeding 50 cm. in depth work and earth work in 20 cm. layers i/c ramming dressing the surface to be required levels and slopes and also i/c 1.20 ft. and 30 leads as per direction of E/I. |
| 33 | Disposal of local sand / earth from Firojpur side i/c loading unloading 2 km. cartage and duly stacked along chequred plate as per direction by E/I. |
| 34 | Extraction of railing wire from railing post and making rolles etc. (as per schedule pg 29 item no 3) |
| 35 | Dismanteling and carrying railing post fixed in position i/c opening of 300 x 16 mm. nut bolts loading unloading cartege and dully stacked at store yard of Bachchalpur ghat Pantoon Bridge aprox lead 3 km. (as per schedule pg 29 item no 5) |
| 36 | Dismanteling and carrying sal edging fix over sleepers i/c loading unloading cartege and duly stacked at store yard of Bachchalpur ghat Pantoon Bridge approx lead 3 km. (as per schedule pg 29 item no 6) |
| 37 | Dismanteling of sal sleepers in decking over the bridge i/c cleaning of kapsa soil and kansa loading unloading carrige and duly stacked at store yard of Bachchalpur ghat Pantoon Bridge aprox lead 3 km. (as per schedule pg 29 item no 7) |
| 38 | Carrying the R.S. joists (Spliced) 5-10 m. between two pantoon after dismentelint of pantoon paires i/c loading unloading cartege and duly stacked at store yard of Bachchalpur ghat Pantoon Bridge approx lead 3 km. (as per schedule pg 29 item no 8) |
| 39 | Dismanteling of chequared plates from the bridge and approch i/c loading in truck and cartage unloading and dully stacked at store yard of Bachchalpur ghat Pantoon Bridge approx lead 3 km. |
| 40 | Carrying the pantoon paires after dismenteling to the safe bank of the river in water and anchoring them properly all as directed by E.I. (as per schedule pg 25 item no 3a) |
| 41 | Cartege of different materials after dismenteling such as nut bolts, rope and railing wire etc. aprox lead 3 km. (as per schedule pg 29 item no 11) |
| 42 | Supply of 28 mm. dia wire Garphy poly propline ISI mark rope for anchoring of pantoons i/c cost of materials its loading unloading cartege upto Bachchalpur ghat Pantoon store (as per schedule pg 28 item no 29) |
| 43 | Opening of U claimp from chequred plate (as per schedule pg 27 item no 19) Please Enable Macros to View BoQ information |
AI Tender Summary
Tender Timeline
Nov 06, 2026
11:30 IST
Tender Published
Tender notice published.
CompletedNov 12, 2026
17:00 IST
Bid Submission Deadline
Online submission via eProcurement portal.
Upcoming · 5 daysNov 12, 2026
Bid Opening Date
Technical bids will be opened and evaluated.
Upcoming · 5 daysTender Documents
Download All (ZIP) ↓
Disclaimer
We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender