Tender For Installation And Energisation Of Ragadipada-I & Ii R/L Project Under Badamba Block In Kataka District Under Ridf 2026-27
Tender Overview
Project Description
Tender for Installation And Energisation Of Ragadipada-I & Ii R/L Project Under Badamba Block In Kataka District Under Ridf 2026-27
Corrigendum
| Sr No | Corrigendum Date | Corrigendum | Type | New Submission Date |
|---|---|---|---|---|
| 1 | 05-Nov-2026 | Corrigendum3845 | Other | 23-Nov-2026 |
BOQ
| Sl. No. | Item Description |
| 1 | RAGADIPADA-I Earth work in excavation of Foundation and plinth in hard soil including dressing and levelling of bed within initial lead of 50mtr.andlifi 1.5mtr etc complete as per the direction of the Engineer-in-charge. |
| 2 | Excavation in hard soil such as Hard stiff clay, stiff black cotton, hard red earth, shales, moorum ordinary gravels, within 50m. Initial lead and 1.5m. Initial lift including rough dressing and breaking clods and stacking rubble or spreading and leveling within the site as the case may be etc; complete.asper direction of the Engineer-in-charge.(Mechanical 60% & Mannual 40%) |
| 3 | Filling in foundation and plinth with sand including watering and ramming etc complete as per the direction of the Engineer-incharge. |
| 4 | Cement concrite(1:4:8) with 4cm size h.g.b. crusser broken metal of approved quality from approved quarry with ramming watering and curring etc.complete including cost , taxes, royality convence charges of all materials to work site,supply of cement T&P required etc.comelete as per the direction of the Engineer-incharge. |
| 5 | Cement concrite(1:2:4) with 12mm size black Crusher broken chips of approved quality from approved quarry with ramming watering and curring etc.complete including supply of all labours, cost.taxes,royality convence charges of all materials to work site,supply of cement T&P required etc.comelete as per the direction of the Engineer-incharge. |
| 6 | Brick work with Fly Ash Brick 25cm x 12cm x 8cm size having croshing strength not less than 75 kg/cm2 with dimensional tolerrance± 2% in cement morter (1:6) in foundation and plinth etc. complete as per the Engineer-incharge. |
| 7 | Brick work with Fly Ash Brick 25cm x 12cm x 8cm size having croshing strength not less than 75 kg/cm2 with dimensional tolerrance±2% in cement morter (1:6) in superstructure work etc. complete as per the Engineer-incharge. |
| 8 | 12mm thick cement plaster in cement morter(1:6)finished smooth to brick work after racking out joints including watering and curring etc.complete including cost.taxes,royality convence charges of all materials to work site,supply of cement T&P required etc.comelete as per the direction of the Engineer-in-charge. |
| 9 | Rigid smooth centering & shuttering for R.C.C. Works walls & fins including false work & dismateling them after 28 days of curing including cost of all materials complete as per direction of Egineer-In-Charge |
| 10 | R.C.C. work in C.C.(1:2:4) including hoisting, laying & curing for 28 days with 12mm size black Crusher broken chips of approved quality from approved quarry with ramming watering and curring etc.complete including supply of all labours, cost.taxes,royality convence charges of all materials to work site,supply of cement T&P required etc.comelete as per the direction of the Engineer-incharge. |
| 11 | Labour charge for M.S. reinforcement for R.C.C. work including cutting, bending & tying the grills & placing in position including cost of binding wire 18 to 20 gauge including cost of HYSD steel bar etc. complete. |
| 12 | Cement punning over plastering including watering & curing with cost, taxes, royality & conveyance charges of all materials & supply of all materials & T& P etc complte as per direction of Engineer- in - charge. |
| 13 | Filling in foundation and plinth with excavated materials including watering and ramming as directed by the Engineer-incharge. |
| 14 | Filling in F&P with excavated materials including well watered and rammed.(2/3 of respective earth work) |
| 15 | Writing charge of required information and data on both side of the transperancy pillar including supplying of approved paints and required material for writing etc. complete. |
| 16 | 2.5cm A.S. flooring with C.C.(1:2:4) including punning with 12mm size chips. |
| 17 | 2.5cm D.P.C. with C.C.(1:2:4) using 12mm size chips. |
| 18 | Cost of Single Pannel Door of size (1.0 mx2.0m) made out of M.S.Frame (35mmx35mmx5mm) with G.P.Sheet pannel of 1.20 mm thick and iron ventilator(size 0.45x0.30m) including fitting at site with all cost etc. complete as per direction of Engineer in charge. |
| 19 | Colour washing two coats over 2 coats white washing with shell lime including cost of paint & labour etc complete. |
| 20 | White wash two coats with shell lime |
| 21 | Painting of red oxide primer for priming over iron work including cost of red oxide & labour etc complete. |
| 22 | Painting two coats with enamel paint for priming over iron work including cost of paint & labour etc complete. |
| 23 | Cost of pump chamber wiring with all cost of wiring materials, labour etc complete. |
| 24 | Fitting of 200 mm outer dia High Density Polythylene Pipes of specified material grade & pressure rating by butt fusion welding method as per speciication & laying in tranches including testing & all cost etc fitting & fixing of required nos. of HDPE Teee for outlet & shaddle & G.I. raiser, nipple for fitting of air valve, equal Tee etc. complete including conveyance of pipe from factory to work site & testing of pipe line etc complete as per direction of Engineer - in-charge. |
| 25 | Fitting of 160 mm outer dia High Density Polythylene Pipes of specified material grade & pressure rating by butt fusion welding method as per speciication & laying in tranches including testing & all cost etc fitting & fixing of required nos. of HDPE Teee for outlet & shaddle & G.I. raiser, nipple for fitting of air valve, equal Tee etc. complete including conveyance of pipe from factory to work site & testing of pipe line etc complete as per direction of Engineer - in-charge. |
| 26 | Labour charges for Instalation of 10 HP pump Sets including fitting and fixing of base frame, fitting & fixing suction and delivery pipe to motor,NR Valve, Foot valve, Sluice valve and other fitting materials including cutting, welding and etc. including transportation to project site and site clearance etc. complete as per the direction of the Engineer-incharge. |
| 27 | Fabrication of special joint including cutting and welding of pipes out of M.S. pipe / 100mm dia G.I.pipe including welding charges etc. complete. |
| 28 | Laying & fitting of ARV/BFV/GI weldless Tee |
| 29 | Construction of outlet at Tank |
| 30 | Welding , Laying & fitting of 200 mm dia M.S. pipe including cutting & filling of river embankmentas per direction of Engineer-in-charge |
| 31 | Welding , Laying & fitting of 100 mm dia G.I. pipe including cutting & filling of river embankmentas per direction of Engineer-in-charge |
| 32 | 100mm dia nominal bore G.I.pipe having wall thickness 4.5mm electrical resistance welded of medium class confirming to IS- 1239(part-1/2004) with latest ammendments, screwed at both ends as per IS-554 with socketed at one end and the other end protected with plastic threaded protector including its transportation and unloading at L.I.P. site. The socket confirming to ISI 1239(part II/1992) with latest ammendments in random length of 4 to 7 mtr.Each pipe should bear IS certification and manufacturers name/trade mark. |
| 33 | 100mm dia G.I.Bend ( Medium Duty) conforming to IS No-1239 (part II/1992) with ISI mark of reputed company. |
| 34 | 100mm dia C.I. Screw boss Foot Valve of swing type friction less with single disc conforming to IS-4038/1979 of reputed brand with ISI mark of reputed company having wide dealership network. |
| 35 | 100mm dia G.I.Flange ( Medium Duty) conforming to IS No-6392/1971 with ISI mark of reputed company. |
| 36 | Monoblock pump set total head of 18 mtrs capable to discharge 1700 LPM with 10 HP/7.50 KW squirrel cage induction motor fitted with bronze impeller TB-2 of IS 318/1981, companion flanges & Class \\"F\\"insulation suitable for operation 415 volt +6%-15% 3 phase, 50Hz AC poweer supply suction/deliveery= 100mmx100mm with BEE Star rated energy efficiency Pump & as per IS-9079/2002 with overall efficiency 62 to 65% of reputed brand having wide dealership net work for easy availability of spares.The materials of construction as given below (a) Casing: FC 200 as per IS 210/1978 (b) Impeller: Bronze grade LTB-2 of IS 318/1981 |
| 37 | Supply of 200 mm Ø HDPE. Pipe PE - 80 ( PN-4) to deliver water at highest counter in complete shape and handed over to Pani Panchayat Chairman or Secretary. |
| 38 | Supply of 160 mm Ø HDPE. Pipe PE - 80 ( PN-4) to deliver water at highest counter in complete shape and handed over to Pani Panchayat Chairman or Secretary. |
| 39 | 219mm dia M.S.Pipe (6.30mm thickness) IS 3589:2001 with ISI mark of reputed company including all cost, conveyance, cess etc complete but excluding cost of GST (As per S/R 2022) |
| 40 | 100x100x25mm G.I. Tee with Plug |
| 41 | 100mm dia C.I.Double Flanged Non Return Valve swing type PN-1.0 (IS-5312(Part-I-2004) with bypass arrangement with ISI mark of reputed company. |
| 42 | 100mm dia C.I.Sluice Valve Flanged type PN-1.0 as per (IS-14846-2000 Standard) with ISI mark of reputed company. |
| 43 | 12mm thick M.S. flange 200mm dia ISI mark |
| 44 | 200mm HDPE elbow spigot design 6 Kg. of ISI mark |
| 45 | 200X200X160 mm Spigot moulded reducing HDPE Tee 10 kg |
| 46 | 200mm dia C.I. Butter Fly Valve BS:5155/15: Kirloskar or equivalent make13095-CI MOC Lever Operated PN-1.0 with ISI mark of reputed including all cost, conveyance, cess etc complete but excluding cost of GST (As per S/R 2022) |
| 47 | 50MM DIA Air release valve with saddle &Raiser pipe.The air release valve shall confirm to IS14845 with ISImark including all taxes &royality etc. |
| 48 | 200x160 mm HDPE reducer |
| 49 | Cost of 200 mm Ø HDPE Bend |
| 50 | Cost of 160 mm Ø HDPE Bend |
| 51 | 160X160X160 mm HDPE Tee spigot design 6 kg |
| 52 | 200X200X200 mm HDPE Tee spigot design 6 kg |
| 53 | 160 mm slipon flange |
| 54 | 200 mm slipon flange |
| 55 | Cost, supplying of 160mmx160mmx110mm dia Weldless G.I.Tee (3.6mm thickness) with bend, closing and opening arrangement of reputed brand including all cost, conveyance, cess etc complete but excluding cost of GST |
| 56 | Cost, supplying of 200mmx200mmx110mm dia Weldless G.I.Tee (3.6mm thickness) with bend, closing and opening arrangement of reputed brand including all cost, conveyance, cess etc complete but excluding cost of GST |
| 57 | 160 MM HDPE Tail piece 160 mm long |
| 58 | 200 MM HDPE Tail piece 160 mm long |
| 59 | 160mm HDPE End cap |
| 60 | 200mm HDPE End cap |
| 61 | 5/8 ' x12\\" Nut bolt & washer F.T. for foundation |
| 62 | 5/8 ' x3\\" Nut bolt F.T. |
| 63 | ⅛\\" thick Rubber Insertion |
| 64 | Control Pannel with Automatic Star delta Starter, sheet steel enclosure suitable for operation of Squirrel cage induction motor up to 10 HP with 16 Amp (AC -3) duty contractor at 415 Volt+6%-15%, 3 phase, 50 Hz AC supply with over load relay range 8.9 to 13.5 Amp & no volt coil with electronic timer suitable for operation at voltage range of 300 to 440 V. The Starter should provide dependable protection against over load and single phasing fitted with Volt Meter, Ameter, MCB in complete shape including Indicator Lamp. |
| 65 | Base frame for panel (size 0.40mx0.20m) made with 3 size M.S. channel having suitable holes for fitting of panel Board, coloured with one coat of red oxide primer and two coats of powder coated paint of approved quality & Base frame for motor (size 0.50mx0.27m) made with 3 size M.S. channel having suitable holes for fittings of different size and make 3 phase centrifugal monoblock pump set from 10 HP. to 15 H.P. coloured with one coat of red oxide primer & two coats of powder coated paint of approved quality. |
| 66 | Motor hood size (0.45mx0.45mx0.60m) made with 18 SWG (cold rolled M.S.Sheet with one coat of red axide primer and two coats of powder coated paint of approved quality on both side (inside & outside) suitable to cover centrifugal monoblock Pump Set from 10 HP to 15 HP and having provision for attachement with the groves on rear side of the pannel board. |
| 67 | 3x10 sqmm PVC insulated (HD) tropoder armoured Electric Cable with alluminum conductor for use in 3 phase power system of working voltage upto & including 1100 volts at 50Hz confirming to IS 7098(Pt-II) including cost of transportation to site. |
| 68 | Construction of 3 phase 11 KV HT line as per REC standard confirming to IE Rules 1956 with 300 kg 9 M long PSC Pole with 55 Sqmm Insulated Conductor average span length 40mtr with ,11 KV \\"V\\" Cross arm, with required No.of 11 KV T & C Disc. Polymer Insulators in tension point & 11 KV Pin Polymer insulators, Couping & Padding of Poles with all G.I.Channels. Danger Board at each Pole, Anti Climbing Devices, Stay Set at Bending point & double stay at end point with 18 mm G.I.H.T.Stay, concreting of Stay with Anchor plate, guarding at Road crossings etc if required including cost of all materials, labour transportation,inspection & commissioning etc. complete. |
| 69 | Construction of 3 Phase L.T line as per REC standard confirming to RE rule 1956 with 300Kg 9 Mtr long PSC pole support in 0.33M span length with 3x35mm² +1x25 mm ² LT, XLPE AB cable with coil earthing device, LT dead end clam, Suspension clamp with G I hook , stay accessories such as wire insulator , clamp etc. nut bolts, alongwith concreting copping & padding of poles and stayset as per direction of Engineer in Charge. |
| 70 | Construction and erection of 11 /0.4 KV, 25 KVA Double Pole mounted Substation with 5mtrx3mtrx1.5mtr height mesonary toe wall /G.I. Flat fencing boundary wall with Flat with Polymer insulator ,L.T Dist Box with MCCB , Aluminim bus bar of single bay with kitkat fuse , sand filling and metal spearding with M.S.Grill gate ,all Channel matrials should be G.I , 7 Nos earthing with chamber with 3mtr G.I pipe of 40mm dia with connecting of 25mmx 5mm G.I flat to all earthing including 25KVA BIS Leble-II Star rated Transformer confirming to RE Rules 1956, mounted on 2.44 Mtr. Long structure, supported in 300 kg 9 mtr long PSC pole,transformer hard channel & top channel made of 2.8 M long 100 X 50 X 6 mm G.I.Channel, Transformer belting on 2.80 M long 50mm X 50mm X 5 mm G.I.Angle, (all REC SPN Std.F-3) with all accessories like 3 pole 11 KV HG Fuse(F-5)& A.B.Switches(F-9) both mounted on 2.8 M long 75mm X 40mm X 6 mm G.I.Channel and supported by 1.0 M long 50 X 50 X 5 mm G.I.Angle, with 3 No. 11 KV Lightening Arrestors and Danger board at each Pole, Anti climbing Devices & all other necessary fittings i.e required size Nuts & Bolts, Brackets, Cable, Cable Sockets as per TPCOCL specification etc. including cost of all materials, labour , transportation complete with liasioning for testing inspection & commissioning as per specification of TPCODL etc complete. |
| 71 | 90 degree cut point |
| 72 | Online DP for River crossing |
| 73 | Electrical installation with electrical materials such as PVC tape, Ampere tape, 7/20 PVC copper wire, 3/20 PVC copper wire, GI flexible conduite pipe, No. 6 GI wire, Copper cable socket, GI socket and flange and petty materials required for electrical installation.All materials should be as per IS |
| 74 | Electrical earthing including all materials as per the direction of the Engineer-incharge |
| 75 | RAGADIPADA-II Earth work in excavation of Foundation and plinth in hard soil including dressing and levelling of bed within initial lead of 50mtr.andlifi 1.5mtr etc complete as per the direction of the Engineer-in-charge. |
| 76 | Excavation in hard soil such as Hard stiff clay, stiff black cotton, hard red earth, shales, moorum ordinary gravels, within 50m. Initial lead and 1.5m. Initial lift including rough dressing and breaking clods and stacking rubble or spreading and leveling within the site as the case may be etc; complete.asper direction of the Engineer-in-charge.(Mechanical 60% & Mannual 40%) |
| 77 | Filling in foundation and plinth with sand including watering and ramming etc complete as per the direction of the Engineer-incharge. |
| 78 | Cement concrite(1:4:8) with 4cm size h.g.b. crusser broken metal of approved quality from approved quarry with ramming watering and curring etc.complete including cost , taxes, royality convence charges of all materials to work site,supply of cement T&P required etc.comelete as per the direction of the Engineer-incharge. |
| 79 | Cement concrite(1:2:4) with 12mm size black Crusher broken chips of approved quality from approved quarry with ramming watering and curring etc.complete including supply of all labours, cost.taxes,royality convence charges of all materials to work site,supply of cement T&P required etc.comelete as per the direction of the Engineer-incharge. |
| 80 | Brick work with Fly Ash Brick 25cm x 12cm x 8cm size having croshing strength not less than 75 kg/cm2 with dimensional tolerrance± 2% in cement morter (1:6) in foundation and plinth etc. complete as per the Engineer-incharge. |
| 81 | Brick work with Fly Ash Brick 25cm x 12cm x 8cm size having croshing strength not less than 75 kg/cm2 with dimensional tolerrance±2% in cement morter (1:6) in superstructure work etc. complete as per the Engineer-incharge. |
| 82 | 12mm thick cement plaster in cement morter(1:6)finished smooth to brick work after racking out joints including watering and curring etc.complete including cost.taxes,royality convence charges of all materials to work site,supply of cement T&P required etc.comelete as per the direction of the Engineer-in-charge. |
| 83 | Rigid smooth centering & shuttering for R.C.C. Works walls & fins including false work & dismateling them after 28 days of curing including cost of all materials complete as per direction of Egineer-In-Charge |
| 84 | R.C.C. work in C.C.(1:2:4) including hoisting, laying & curing for 28 days with 12mm size black Crusher broken chips of approved quality from approved quarry with ramming watering and curring etc.complete including supply of all labours, cost.taxes,royality convence charges of all materials to work site,supply of cement T&P required etc.comelete as per the direction of the Engineer-incharge. |
| 85 | Labour charge for M.S. reinforcement for R.C.C. work including cutting, bending & tying the grills & placing in position including cost of binding wire 18 to 20 gauge including cost of HYSD steel bar etc. complete. |
| 86 | Cement punning over plastering including watering & curing with cost, taxes, royality & conveyance charges of all materials & supply of all materials & T& P etc complte as per direction of Engineer- in - charge. |
| 87 | Filling in foundation and plinth with excavated materials including watering and ramming as directed by the Engineer-incharge. |
| 88 | Filling in F&P with excavated materials including well watered and rammed.(2/3 of respective earth work) |
| 89 | Writing charge of required information and data on both side of the transperancy pillar including supplying of approved paints and required material for writing etc. complete. |
| 90 | 2.5cm A.S. flooring with C.C.(1:2:4) including punning with 12mm size chips. |
| 91 | 2.5cm D.P.C. with C.C.(1:2:4) using 12mm size chips. |
| 92 | Cost of Single Pannel Door of size (1.0 mx2.0m) made out of M.S.Frame (35mmx35mmx5mm) with G.P.Sheet pannel of 1.20 mm thick and iron ventilator(size 0.45x0.30m) including fitting at site with all cost etc. complete as per direction of Engineer in charge. |
| 93 | Colour washing two coats over 2 coats white washing with shell lime including cost of paint & labour etc complete. |
| 94 | White wash two coats with shell lime |
| 95 | Painting of red oxide primer for priming over iron work including cost of red oxide & labour etc complete. |
| 96 | Painting two coats with enamel paint for priming over iron work including cost of paint & labour etc complete. |
| 97 | Cost of pump chamber wiring with all cost of wiring materials, labour etc complete. |
| 98 | Fitting of 200 mm outer dia High Density Polythylene Pipes of specified material grade & pressure rating by butt fusion welding method as per speciication & laying in tranches including testing & all cost etc fitting & fixing of required nos. of HDPE Teee for outlet & shaddle & G.I. raiser, nipple for fitting of air valve, equal Tee etc. complete including conveyance of pipe from factory to work site & testing of pipe line etc complete as per direction of Engineer - in-charge. |
| 99 | Fitting of 160 mm outer dia High Density Polythylene Pipes of specified material grade & pressure rating by butt fusion welding method as per speciication & laying in tranches including testing & all cost etc fitting & fixing of required nos. of HDPE Teee for outlet & shaddle & G.I. raiser, nipple for fitting of air valve, equal Tee etc. complete including conveyance of pipe from factory to work site & testing of pipe line etc complete as per direction of Engineer - in-charge. |
| 100 | Labour charges for Instalation of 10 HP pump Sets including fitting and fixing of base frame, fitting & fixing suction and delivery pipe to motor,NR Valve, Foot valve, Sluice valve and other fitting materials including cutting, welding and etc. including transportation to project site and site clearance etc. complete as per the direction of the Engineer-incharge. |
| 101 | Fabrication of special joint including cutting and welding of pipes out of M.S. pipe / 100mm dia G.I.pipe including welding charges etc. complete. |
| 102 | Laying & fitting of ARV/BFV/GI weldless Tee |
| 103 | Construction of outlet at Tank |
| 104 | Welding , Laying & fitting of 200 mm dia M.S. pipe including cutting & filling of river embankmentas per direction of Engineer-in-charge |
| 105 | Welding , Laying & fitting of 100 mm dia G.I. pipe including cutting & filling of river embankmentas per direction of Engineer-in-charge |
| 106 | 100mm dia nominal bore G.I.pipe having wall thickness 4.5mm electrical resistance welded of medium class confirming to IS- 1239(part-1/2004) with latest ammendments, screwed at both ends as per IS-554 with socketed at one end and the other end protected with plastic threaded protector including its transportation and unloading at L.I.P. site. The socket confirming to ISI 1239(part II/1992) with latest ammendments in random length of 4 to 7 mtr.Each pipe should bear IS certification and manufacturers name/trade mark. |
| 107 | 100mm dia G.I.Bend ( Medium Duty) conforming to IS No-1239 (part II/1992) with ISI mark of reputed company. |
| 108 | 100mm dia C.I. Screw boss Foot Valve of swing type friction less with single disc conforming to IS-4038/1979 of reputed brand with ISI mark of reputed company having wide dealership network. |
| 109 | 100mm dia G.I.Flange ( Medium Duty) conforming to IS No-6392/1971 with ISI mark of reputed company. |
| 110 | Monoblock pump set total head of 18 mtrs capable to discharge 1700 LPM with 10 HP/7.50 KW squirrel cage induction motor fitted with bronze impeller TB-2 of IS 318/1981, companion flanges & Class \\"F\\"insulation suitable for operation 415 volt +6%-15% 3 phase, 50Hz AC poweer supply suction/deliveery= 100mmx100mm with BEE Star rated energy efficiency Pump & as per IS-9079/2002 with overall efficiency 62 to 65% of reputed brand having wide dealership net work for easy availability of spares.The materials of construction as given below (a) Casing: FC 200 as per IS 210/1978 (b) Impeller: Bronze grade LTB-2 of IS 318/1981 |
| 111 | Supply of 200 mm Ø HDPE. Pipe PE - 80 ( PN-4) to deliver water at highest counter in complete shape and handed over to Pani Panchayat Chairman or Secretary. |
| 112 | Supply of 160 mm Ø HDPE. Pipe PE - 80 ( PN-4) to deliver water at highest counter in complete shape and handed over to Pani Panchayat Chairman or Secretary. |
| 113 | 219mm dia M.S.Pipe (6.30mm thickness) IS 3589:2001 with ISI mark of reputed company including all cost, conveyance, cess etc complete but excluding cost of GST (As per S/R 2022) |
| 114 | 100x100x25mm G.I. Tee with Plug |
| 115 | 100mm dia C.I.Double Flanged Non Return Valve swing type PN-1.0 (IS-5312(Part-I-2004) with bypass arrangement with ISI mark of reputed company. |
| 116 | 100mm dia C.I.Sluice Valve Flanged type PN-1.0 as per (IS-14846-2000 Standard) with ISI mark of reputed company. |
| 117 | 12mm thick M.S. flange 200mm dia ISI mark |
| 118 | 200mm HDPE elbow spigot design 6 Kg. of ISI mark |
| 119 | 200X200X160 mm Spigot moulded reducing HDPE Tee 10 kg |
| 120 | 200mm dia C.I. Butter Fly Valve BS:5155/15: Kirloskar or equivalent make13095-CI MOC Lever Operated PN-1.0 with ISI mark of reputed including all cost, conveyance, cess etc complete but excluding cost of GST (As per S/R 2022) |
| 121 | 50MM DIA Air release valve with saddle &Raiser pipe.The air release valve shall confirm to IS14845 with ISImark including all taxes &royality etc. |
| 122 | 200x160 mm HDPE reducer |
| 123 | Cost of 200 mm Ø HDPE Bend |
| 124 | Cost of 160 mm Ø HDPE Bend |
| 125 | 160X160X160 mm HDPE Tee spigot design 6 kg |
| 126 | 200X200X200 mm HDPE Tee spigot design 6 kg |
| 127 | 160 mm slipon flange |
| 128 | 200 mm slipon flange |
| 129 | Cost, supplying of 160mmx160mmx110mm dia Weldless G.I.Tee (3.6mm thickness) with bend, closing and opening arrangement of reputed brand including all cost, conveyance, cess etc complete but excluding cost of GST |
| 130 | Cost, supplying of 200mmx200mmx110mm dia Weldless G.I.Tee (3.6mm thickness) with bend, closing and opening arrangement of reputed brand including all cost, conveyance, cess etc complete but excluding cost of GST |
| 131 | 160 MM HDPE Tail piece 160 mm long |
| 132 | 200 MM HDPE Tail piece 160 mm long |
| 133 | 160mm HDPE End cap |
| 134 | 200mm HDPE End cap |
| 135 | 5/8 ' x12\\" Nut bolt & washer F.T. for foundation |
| 136 | 5/8 ' x3\\" Nut bolt F.T. |
| 137 | ⅛\\" thick Rubber Insertion |
| 138 | Control Pannel with Automatic Star delta Starter, sheet steel enclosure suitable for operation of Squirrel cage induction motor up to 10 HP with 16 Amp (AC -3) duty contractor at 415 Volt+6%-15%, 3 phase, 50 Hz AC supply with over load relay range 8.9 to 13.5 Amp & no volt coil with electronic timer suitable for operation at voltage range of 300 to 440 V. The Starter should provide dependable protection against over load and single phasing fitted with Volt Meter, Ameter, MCB in complete shape including Indicator Lamp. |
| 139 | Base frame for panel (size 0.40mx0.20m) made with 3 size M.S. channel having suitable holes for fitting of panel Board, coloured with one coat of red oxide primer and two coats of powder coated paint of approved quality & Base frame for motor (size 0.50mx0.27m) made with 3 size M.S. channel having suitable holes for fittings of different size and make 3 phase centrifugal monoblock pump set from 10 HP. to 15 H.P. coloured with one coat of red oxide primer & two coats of powder coated paint of approved quality. |
| 140 | Motor hood size (0.45mx0.45mx0.60m) made with 18 SWG (cold rolled M.S.Sheet with one coat of red axide primer and two coats of powder coated paint of approved quality on both side (inside & outside) suitable to cover centrifugal monoblock Pump Set from 10 HP to 15 HP and having provision for attachement with the groves on rear side of the pannel board. |
| 141 | 3x10 sqmm PVC insulated (HD) tropoder armoured Electric Cable with alluminum conductor for use in 3 phase power system of working voltage upto & including 1100 volts at 50Hz confirming to IS 7098(Pt-II) including cost of transportation to site. |
| 142 | Construction of 3 phase 11 KV HT line as per REC standard confirming to IE Rules 1956 with 300 kg 9 M long PSC Pole with 55 Sqmm Insulated Conductor average span length 40mtr with ,11 KV \\"V\\" Cross arm, with required No.of 11 KV T & C Disc. Polymer Insulators in tension point & 11 KV Pin Polymer insulators, Couping & Padding of Poles with all G.I.Channels. Danger Board at each Pole, Anti Climbing Devices, Stay Set at Bending point & double stay at end point with 18 mm G.I.H.T.Stay, concreting of Stay with Anchor plate, guarding at Road crossings etc if required including cost of all materials, labour transportation,inspection & commissioning etc. complete. |
| 143 | Construction of 3 Phase L.T line as per REC standard confirming to RE rule 1956 with 300Kg 9 Mtr long PSC pole support in 0.33M span length with 3x35mm² +1x25 mm ² LT, XLPE AB cable with coil earthing device, LT dead end clam, Suspension clamp with G I hook , stay accessories such as wire insulator , clamp etc. nut bolts, alongwith concreting copping & padding of poles and stayset as per direction of Engineer in Charge. |
| 144 | Construction and erection of 11 /0.4 KV, 25 KVA Double Pole mounted Substation with 5mtrx3mtrx1.5mtr height mesonary toe wall /G.I. Flat fencing boundary wall with Flat with Polymer insulator ,L.T Dist Box with MCCB , Aluminim bus bar of single bay with kitkat fuse , sand filling and metal spearding with M.S.Grill gate ,all Channel matrials should be G.I , 7 Nos earthing with chamber with 3mtr G.I pipe of 40mm dia with connecting of 25mmx 5mm G.I flat to all earthing including 25KVA BIS Leble-II Star rated Transformer confirming to RE Rules 1956, mounted on 2.44 Mtr. Long structure, supported in 300 kg 9 mtr long PSC pole,transformer hard channel & top channel made of 2.8 M long 100 X 50 X 6 mm G.I.Channel, Transformer belting on 2.80 M long 50mm X 50mm X 5 mm G.I.Angle, (all REC SPN Std.F-3) with all accessories like 3 pole 11 KV HG Fuse(F-5)& A.B.Switches(F-9) both mounted on 2.8 M long 75mm X 40mm X 6 mm G.I.Channel and supported by 1.0 M long 50 X 50 X 5 mm G.I.Angle, with 3 No. 11 KV Lightening Arrestors and Danger board at each Pole, Anti climbing Devices & all other necessary fittings i.e required size Nuts & Bolts, Brackets, Cable, Cable Sockets as per TPCOCL specification etc. including cost of all materials, labour , transportation complete with liasioning for testing inspection & commissioning as per specification of TPCODL etc complete. |
| 145 | 90 degree cut point |
| 146 | Online DP for River crossing |
| 147 | Electrical installation with electrical materials such as PVC tape, Ampere tape, 7/20 PVC copper wire, 3/20 PVC copper wire, GI flexible conduite pipe, No. 6 GI wire, Copper cable socket, GI socket and flange and petty materials required for electrical installation.All materials should be as per IS |
| 148 | Electrical earthing including all materials as per the direction of the Engineer-incharge Please Enable Macros to View BoQ information |
AI Tender Summary
Tender Timeline
Tender Published
Tender notice published.
CompletedCorrigendum-1 Issued
Clarifications on tender conditions and amendments issued.
Upcoming · 4 daysBid Submission Deadline
Online submission via eProcurement portal.
Upcoming · 4 daysTender Documents
Download All (ZIP) ↓We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender