Tender For Special Repair Work At Hathwant Mustfabad Roat To Nagla Shish Road.
Tender Overview
Project Description
Tender for Special Repair Work At Hathwant Mustfabad Roat To Nagla Shish Road.
Corrigendum
| Sr No | Corrigendum Date | Corrigendum | Type | New Submission Date |
|---|---|---|---|---|
| 1 | 03-Nov-2026 | Date Change | Date | 10-Nov-2026 |
BOQ
| Sl. No. | Item Description |
| 1 | Construction of subgrade and earthen shoulders with approved material obtained from borrow pits with all lifts and leads, transporting to site, spreading, grading to required slope and compacted to meet requirement of Table 300.2 with lead upto 1000 m as per Technical Specification Clause 303.1. For patries |
| 2 | WBM (G-3) Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with smooth wheel roller 80-100 kN in stages to proper grade and camber, applying and brooming, stone screening to fill-up the interstices of coarse aggregate watering and compacting to the required density grading 3 as per technical specification clause-405 |
| 3 | Providing and applying tack coat with bitumen (VG-10) at the rate of 0.30 kg per sqm on the prepared granular surfaces treated with primer & cleaned with Hydraulic broom as per technical specification clause-503 |
| 4 | Providing, laying and rolling of open-graded premix carpet of 20 mm thickness composed of 13.2 mm to 5.6 mm aggregates either using penetration grade bitumen or emulsion to required line, grade and level to serve as wearing course on a previously prepared base, including mixing in a suitable plant, laying and rolling with a three wheel 80-100 kn static roller capacity, finished to required level and grades. as per Technical Specification clause-508 |
| 5 | Providing & laying seal coat sealing the voids in a bituminous surface laid to the specified levels, grade and cross fall using Type-C as per Technical Specification clause-510 |
| 6 | CEMENT CONCRETE PAVEMENT(C.C ROAD) Construction of un-reinforced, plain cement concrete pavement thickness as per drawing over a prepared sub base with 43 grade cement as per claus 1501.2.2 M 30 (grade) coarse and fine aggregate conforming to IS 383, maximum size of coarse aggregate not exceeding 25 mm, mixed in a concrete mixture of not less then 0.20cum capacity and appropriate weigh batcher using approved mix design, laid in approved fixed site form work (steel channel laying and fixing of 125 micorn thick polythine film wedges steel plates including leveling the form work as per drawing), spreading the concrete with shovels, rakes, compacted using needle, screed and plate viobrators and finished in countinous operations including provision of contraction and expansion, construction joints applying primer sealent, and construction joint, admixtures as approved curing of concrete slab for 14 days curing compound (where specified) and water finishing to ines and grade as per drawing and technical specification clause 1501. |
| 7 | Construction of unlined surface drain of avraage cross-sectional area 0.40 sqm in soil to specifed Lines, grades, levels and dimensions. Excavated material to be used in embankment with a lift upto 3m lead of 50 m (avraage lead 25 m) as per Technical Specification Clause 307. |
| 8 | Providing and laying cement concrete in 1:4:8 (1 Cement : 4 coarse sand : 8 graded stone aggregate 40 mm nominal size) and curing complete, Including cost of form work. in Foundation and floors. |
| 9 | Reinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers,abutments, posts and struts etc. including cost of centering, shuttering, finishing and excluding reinforcement :1:1.5:3 (1 cement : 1.5 coarse sand : 3 graded stone aggregate 20 mm nominal size) |
| 10 | Mild steel or iron work in plain work such as reinforced concrete or reinforced brick work (When not included in and an over all rates) brought to required shape as necessary including bending for proper completion of the work and excluding the supply of steel and its wastage Bend, hooks and authorized over lapping shall be measured upto floor to level. Please Enable Macros to View BoQ information |
AI Tender Summary
Tender Timeline
Tender Published
Tender notice published.
CompletedCorrigendum-1 Issued
Clarifications on tender conditions and amendments issued.
Upcoming · 2 daysBid Submission Deadline
Online submission via eProcurement portal.
Upcoming · 2 daysBid Opening Date
Technical bids will be opened and evaluated.
Upcoming · 2 daysTender Documents
Download All (ZIP) ↓We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender