Tender For General-Annual Project 2025-26-Project No 192/26-27 Thodu Side Protection Near Muncipal Park. (Construction Of Side Protection Work For Stream Carring Water To Kozhippilly Drinking Water Supply Scheme)-General Civil Work
Tender Overview
Project Description
Tender for General-Annual Project 2025-26-Project No 192/26-27 Thodu Side Protection Near Muncipal Park. (Construction Of Side Protection Work For Stream Carring Water To Kozhippilly Drinking Water Supply Scheme)-General Civil Work
BOQ
| Sl. No. | Item Description |
| 1 | SIDE PROTECTION WORK |
| 2 | OD83722/2025-2026:Bailing out water Using 5HP Pump- Bailing out water with 5HP engine and pumpset including conveyance to site and erection,cost of fuel, lubrication oil and otherstores, pay of staff etc complete |
| 3 | 15.9.2:Demolishing stone rubble masonry manually / by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer -in- Charges:In cement mortar |
| 4 | OD83837/2025-2026:60.7.8 DR with Departmental. Stone - DRY RUBBLE MASONRY _ Dry rubble withoutconcrete levelling course using departmental rubble including packing tocompactness to lines and levels, labour charges etc. complete as per direction ofDepartmental officers at site |
| 5 | 2.8.1:Earth work in excavation by mechanical means (Hydraulic excavator) /manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m.All kinds of soil |
| 6 | OD267803/2025-2026:60.7.1. DRY RUBBLE MASONRY _ Dry rubble without concrete levelling course masonry with good quality blasted rubble including packing to compactness to lines and levels cost and conveyance of all materials labour charges etc. complete as per direction of Departmental officers at site |
| 7 | 5.9.1:Centering and shuttering including strutting, etc. and removal of form for:Foundations, footings, bases of columns, etc for mass concrete |
| 8 | 5.1.2:Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level:1:1:5:3 (1 cement 1.5 coarse sand :3 graded stone aggregate 20 mm nominal size derived from natural sources) |
| 9 | 5.22.6:Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more |
| 10 | 10.1:Structural steel work in single section, fixed with or without connecting plate, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer all complete. |
| 11 | 13.61.1:Painting with synthetic enamel paint of approved brand and manufacture to give an even shade:Two or more coats on new work |
| 12 | 50.2.26.1:Filling with contractor own earth (excluding rock) in open areas in layers not exceeding 20 cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift up to 1.5 m as per direction of site Engineer-in-charge. Please Enable Macros to View BoQ information |
AI Tender Summary
Tender Timeline
Tender Published
Tender notice published.
CompletedBid Submission Deadline
Online submission via eProcurement portal.
Upcoming · 14 daysBid Opening Date
Technical bids will be opened and evaluated.
Upcoming · 16 daysTender Documents
Download All (ZIP) ↓We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender