Tender For Mill Plant- Unit-Iv - Overhauling Of Gravimetric Feeders And Clean Out Conveyor Of Mill 4A To 4F And Replacement Of Worn-Out Elliptical Feeder Discharge Chutes By Reconditioning Ss Elliptical Feeder Discharge Chutes In Mill 4A To 4D During
Tender Overview
Project Description
Tender for Mill Plant- Unit-Iv - Overhauling Of Gravimetric Feeders And Clean Out Conveyor Of Mill 4A To 4F And Replacement Of Worn-Out Elliptical Feeder Discharge Chutes By Reconditioning Ss Elliptical Feeder Discharge Chutes In Mill 4A To 4D During Aoh 2026-27.
BOQ
| Sl. No. | Item Description |
| 1 | Charges for overhauling of gravimetric feeder after dismantling all the Idle rollers pulleys, bearings, checking of clean out conveyors and changing of bearings in the clean out conveyor shaft, chain link and changing of Belt and other worn out parts and reassembling the same in complete shape and oil filling in the gear box. This includes transportation of materials from stores |
| 2 | Charges for draining the feeder gear box oil, removing the feeder gear box from position, dismantling the gear box, cleaning the gear box, inspection of bearings, gears, assembling the gear box, oil refilling and fixing in position as per the direction of Engineer in-charge, including cost of consumables. |
| 3 | Dismantling the existing eroded feeder discharge chute and assembling the reconditioned chute with the fabricated MS flange and fixing the Center feed pipe by welding. The work includes store drawl and devolution of scrap to stores |
| 4 | charges for transporting of required materials to work site, cleaning and dismantling the worn out centre feed pipe between mill top to raw coal feeder bottom]and lowering down to Om, repairing the pipe or replacement and assembling the centre feed pipe (406 x 12 mm) including lead, lifting and welding. |
| 5 | Cost of bearings 6211 |
| 6 | Cost of bearings 6212 |
| 7 | Cost of bearings 30216 |
| 8 | Cost of bearings 30313 |
| 9 | Cost of cutting gas |
| 10 | Cost of M.S Welding Electrodes Please Enable Macros to View BoQ information |
AI Tender Summary
Tender Timeline
Tender Published
Tender notice published.
CompletedBid Submission Deadline
Online submission via eProcurement portal.
Upcoming · 5 daysBid Opening Date
Technical bids will be opened and evaluated.
Upcoming · 6 daysTender Documents
Download All (ZIP) ↓We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender