Bids Are invited for Excavation Of Earth For Attending To Ht And Lt Cable Fault And Laying Or Removing And Relaying
Tender Overview
Project Description
Bids Are invited for Work-1 - 1St Year Laying / Removing Of 10 To 25 Sq. Mm Lt Cable And Measured Running Meters For By Earth Excavation To A Depth Of 0.6M And Refilling The Same After Completion Of Work. , Work-2 - 1St Year Laying / Removing Of 10 To 25 Sq. Mm Lt Cable And Measured Running Meters For By Cutting Of Cement Road / Tar Road/ Cement Concrete To A Depth Of 0.6M And Refilling The Same After Completion Of Work. , Work-3 - 1St Year Laying / Removing Of 10 To 25 Sq. Mm Lt Cable And Measured Running Meters For By Removal Of Various Sizes Of Concrete Slab And Refilling The Same After Completion Of Work. , Work-4 - 2Nd Year Laying / Removing Of 10 To 25 Sq. Mm Lt Cable And Measured Running Meters For By Earth Excavation To A Depth Of 0.6M And Refilling The Same After Completion Of Work. , Work-5 - 2Nd Year Laying / Removing Of 10 To 25 Sq. Mm Lt Cable And Measured Running Meters For By Cutting Of Cement Road / Tar Road/ Cement Concrete To A Depth Of 0.6M And Refilling The Same After Completion Of Work. , Work-6 - 2Nd Year Laying / Removing Of 10 To 25 Sq. Mm Lt Cable And Measured Running Meters For By Removal Of Various Sizes Of Concrete Slab And Refilling The Same After Completion Of Work. , Work-7 - 1St Year Laying / Removing Of 50 To 95 Sq. Mm Lt Cable And Measured Running Meters By Earth Excavation To A Depth Of 0.6M And Refilling The Same After Completion Of Work. , Work-8 - 1St Year Laying / Removing Of 50 To 95 Sq. Mm Lt Cable And Measured Running Meters By Cutting Of Cement Road / Tar Road/ Cement Concrete To A Depth Of 0.6M And Refilling The Same After Completion Of Work. , Work-9 - 1St Year Laying / Removing Of 50 To 95 Sq. Mm Lt Cable And Measured Running Meters By Removal Of Various Sizes Of Concrete Slab And Refilling The Same After Completion Of Work. , Work-10 - 2Ndyear Laying / Removing Of 50 To 95 Sq. Mm Lt Cable And Measured Running Meters By Earth Excavation To A Depth Of 0.6M And Refilling The Same After Completion Of Work. , Work-11 - 2Ndyear Laying / Removing Of 50 To 95 Sq. Mm Lt Cable And Measured Running Meters By Cutting Of Cement Road / Tar Road/ Cement Concrete To A Depth Of 0.6M And Refilling The Same After Completion Of Work. , Work-12 - 2Ndyear Laying / Removing Of 50 To 95 Sq. Mm Lt Cable And Measured Running Meters By Removal Of Various Sizes Of Concrete Slab And Refilling The Same After Completion Of Work. , Work-13 - 1St Year Laying / Removing Of 120 To 185 Sq. Mm Lt Cable And Measured Running Meters By Earth Excavation To A Depth Of 0.6M And Refilling The Same After Completion Of Work. , Work-14 - 1St Year Laying / Removing Of 120 To 185 Sq. Mm Lt Cable And Measured Running Meters By Cutting Of Cement Road / Tar Road/ Cement Concrete To A Depth Of 0.6M And Refilling The Same After Completion Of Work. , Work-15 - 1St Year Laying / Removing Of 120 To 185 Sq. Mm Lt Cable And Measured Running Meters By Removal Of Various Sizes Of Concrete Slab And Refilling The Same After Completion Of Work. , Work-16 - 2Nd Year Laying / Removing Of 120 To 185 Sq. Mm Lt Cable And Measured Running Meters By Earth Excavation To A Depth Of 0.6M And Refilling The Same After Completion Of Work. , Work-17 - 2Nd Year Laying / Removing Of 120 To 185 Sq. Mm Lt Cable And Measured Running Meters By Cutting Of Cement Road / Tar Road/ Cement Concrete To A Depth Of 0.6M And Refilling The Same After Completion Of Work. , Work-18 - 2Nd Year Laying / Removing Of 120 To 185 Sq. Mm Lt Cable And Measured Running Meters By Removal Of Various Sizes Of Concrete Slab And Refilling The Same After Completion Of Work. , Work-19 - 1St Year Laying / Removing Of 240 To 500 Sq. Mm Lt Cable And Measured Running Meters By Earth Excavation To A Depth Of 0.6M And Refilling The Same After Completion Of Work. , Work-20 - 1St Year Laying / Removing Of 240 To 500 Sq. Mm Lt Cable And Measured Running Meters By Cutting Of Cement Road / Tar Road/ Cement Concrete To A Depth Of 0.6M And Refilling The Same After Completion Of Work. , Work-21 - 1St Year Laying / Removing Of 240 To 500 Sq. Mm Lt Cable And Measured Running Meters By Removal Of Various Sizes Of Concrete Slab And Refilling The Same After Completion Of Work. , Work-22 - 2Nd Year Laying / Removing Of 240 To 500 Sq. Mm Lt Cable And Measured Running Meters By Earth Excavation To A Depth Of 0.6M And Refilling The Same After Completion Of Work. , Work-23 - 2Nd Year Laying / Removing Of 240 To 500 Sq. Mm Lt Cable And Measured Running Meters By Cutting Of Cement Road / Tar Road/ Cement Concrete To A Depth Of 0.6M And Refilling The Same After Completion Of Work. , Work-24 - 2Nd Year Laying / Removing Of 240 To 500 Sq. Mm Lt Cable And Measured Running Meters By Removal Of Various Sizes Of Concrete Slab And Refilling The Same After Completion Of Work. , Work-25 - 1St Year Laying / Removing Of 185 To 240Sq. Mm Ht Cable And Measured Running Meters By Earth Excavation To A Depth Of 0.9M And Refilling The Same After Completion Of Work. , Work-26 - 1St Year Laying / Removing Of 185 To 240Sq. Mm Ht Cable And Measured Running Meters By Cutting Of Cement Road / Tar Road/ Cement Concrete To A Depth Of 0.9M And Refilling The Same After Completion Of Work. , Work-27 - 1St Year Laying / Removing Of 185 To 240Sq. Mm Ht Cable And Measured Running Meters By Removal Of Various Sizes Of Concrete Slab And Refilling The Same After Completion Of Work. , Work-28 - 2Nd Year Laying / Removing Of 185 To 240Sq. Mm Ht Cable And Measured Running Meters By Earth Excavation To A Depth Of 0.9M And Refilling The Same After Completion Of Work. , Work-29 - 2Nd Year Laying / Removing Of 185 To 240Sq. Mm Ht Cable And Measured Running Meters By Cutting Of Cement Road / Tar Road/ Cement Concrete To A Depth Of 0.9M And Refilling The Same After Completion Of Work. , Work-30 - 2Nd Year Laying / Removing Of 185 To 240Sq. Mm Ht Cable And Measured Running Meters By Removal Of Various Sizes Of Concrete Slab And Refilling The Same After Completion Of Work.
BOQ
| Sl. No. | Item Title | Item Description |
| 1 | Work-1 | 1st Year Laying / Removing of 10 to 25 Sq. mm LT cable and measured running meters for by earth excavation to a depth of 0.6M and refilling the same after completion of work. |
| 2 | Work-2 | 1st Year Laying / Removing of 10 to 25 Sq. mm LT cable and measured running meters for by cutting of Cement road / Tar road/ cement concrete to a depth of 0.6M and refilling the same after completion of work. |
| 3 | Work-3 | 1st Year Laying / Removing of 10 to 25 Sq. mm LT cable and measured running meters for by removal of various sizes of concrete slab and refilling the same after completion of work. |
| 4 | Work-4 | 2nd Year Laying / Removing of 10 to 25 Sq. mm LT cable and measured running meters for by earth excavation to a depth of 0.6M and refilling the same after completion of work. |
| 5 | Work-5 | 2nd Year Laying / Removing of 10 to 25 Sq. mm LT cable and measured running meters for by cutting of Cement road / Tar road/ cement concrete to a depth of 0.6M and refilling the same after completion of work. |
| 6 | Work-6 | 2nd Year Laying / Removing of 10 to 25 Sq. mm LT cable and measured running meters for by removal of various sizes of concrete slab and refilling the same after completion of work. |
| 7 | Work-7 | 1st year Laying / Removing of 50 to 95 Sq. mm LT cable and measured running meters by earth excavation to a depth of 0.6M and refilling the same after completion of work. |
| 8 | Work-8 | 1st year Laying / Removing of 50 to 95 Sq. mm LT cable and measured running meters by cutting of Cement road / Tar road/ cement concrete to a depth of 0.6M and refilling the same after completion of work. |
| 9 | Work-9 | 1st year Laying / Removing of 50 to 95 Sq. mm LT cable and measured running meters by removal of various sizes of concrete slab and refilling the same after completion of work. |
| 10 | Work-10 | 2ndyear Laying / Removing of 50 to 95 Sq. mm LT cable and measured running meters by earth excavation to a depth of 0.6M and refilling the same after completion of work. |
| 11 | Work-11 | 2ndyear Laying / Removing of 50 to 95 Sq. mm LT cable and measured running meters by cutting of Cement road / Tar road/ cement concrete to a depth of 0.6M and refilling the same after completion of work. |
| 12 | Work-12 | 2ndyear Laying / Removing of 50 to 95 Sq. mm LT cable and measured running meters by removal of various sizes of concrete slab and refilling the same after completion of work. |
| 13 | Work-13 | 1st year Laying / Removing of 120 to 185 Sq. mm LT cable and measured running meters by earth excavation to a depth of 0.6M and refilling the same after completion of work. |
| 14 | Work-14 | 1st year Laying / Removing of 120 to 185 Sq. mm LT cable and measured running meters by cutting of Cement road / Tar road/ cement concrete to a depth of 0.6M and refilling the same after completion of work. |
| 15 | Work-15 | 1st year Laying / Removing of 120 to 185 Sq. mm LT cable and measured running meters by removal of various sizes of concrete slab and refilling the same after completion of work. |
| 16 | Work-16 | 2nd year Laying / Removing of 120 to 185 Sq. mm LT cable and measured running meters by earth excavation to a depth of 0.6M and refilling the same after completion of work. |
| 17 | Work-17 | 2nd year Laying / Removing of 120 to 185 Sq. mm LT cable and measured running meters by cutting of Cement road / Tar road/ cement concrete to a depth of 0.6M and refilling the same after completion of work. |
| 18 | Work-18 | 2nd year Laying / Removing of 120 to 185 Sq. mm LT cable and measured running meters by removal of various sizes of concrete slab and refilling the same after completion of work. |
| 19 | Work-19 | 1st year Laying / Removing of 240 to 500 Sq. mm LT cable and measured running meters by earth excavation to a depth of 0.6M and refilling the same after completion of work. |
| 20 | Work-20 | 1st year Laying / Removing of 240 to 500 Sq. mm LT cable and measured running meters by cutting of Cement road / Tar road/ cement concrete to a depth of 0.6M and refilling the same after completion of work. |
| 21 | Work-21 | 1st year Laying / Removing of 240 to 500 Sq. mm LT cable and measured running meters by removal of various sizes of concrete slab and refilling the same after completion of work. |
| 22 | Work-22 | 2nd year Laying / Removing of 240 to 500 Sq. mm LT cable and measured running meters by earth excavation to a depth of 0.6M and refilling the same after completion of work. |
| 23 | Work-23 | 2nd year Laying / Removing of 240 to 500 Sq. mm LT cable and measured running meters by cutting of Cement road / Tar road/ cement concrete to a depth of 0.6M and refilling the same after completion of work. |
| 24 | Work-24 | 2nd year Laying / Removing of 240 to 500 Sq. mm LT cable and measured running meters by removal of various sizes of concrete slab and refilling the same after completion of work. |
| 25 | Work-25 | 1st year Laying / Removing of 185 to 240Sq. mm HT cable and measured running meters by earth excavation to a depth of 0.9M and refilling the same after completion of work. |
| 26 | Work-26 | 1st year Laying / Removing of 185 to 240Sq. mm HT cable and measured running meters by cutting of Cement road / Tar road/ cement concrete to a depth of 0.9M and refilling the same after completion of work. |
| 27 | Work-27 | 1st year Laying / Removing of 185 to 240Sq. mm HT cable and measured running meters by removal of various sizes of concrete slab and refilling the same after completion of work. |
| 28 | Work-28 | 2nd year Laying / Removing of 185 to 240Sq. mm HT cable and measured running meters by earth excavation to a depth of 0.9M and refilling the same after completion of work. |
| 29 | Work-29 | 2nd year Laying / Removing of 185 to 240Sq. mm HT cable and measured running meters by cutting of Cement road / Tar road/ cement concrete to a depth of 0.9M and refilling the same after completion of work. |
| 30 | Work-30 | 2nd year Laying / Removing of 185 to 240Sq. mm HT cable and measured running meters by removal of various sizes of concrete slab and refilling the same after completion of work. |
AI Tender Summary
Tender Timeline
Tender Published
Tender notice published.
CompletedBid Submission Deadline
Online submission via eProcurement portal.
Upcoming · 18 daysBid Opening Date
Technical bids will be opened and evaluated.
Upcoming · 19 daysTender Documents
Download All (ZIP) ↓We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender