Tender For Tender For Prop. 11/0.4 Kv,63 Kva S/Stn. At Village Kuthera Kherla , Replacement Of Existing Lengthy Services With Bare Conductor To Improve A Low Voltage From Existing 63 Kva S/Stn. (Jr), Replacement Of Existing Lengthy Services With Bare
Tender Overview
Project Description
Tender for Tender For Prop. 11/0.4 Kv,63 Kva S/Stn. At Village Kuthera Kherla , Replacement Of Existing Lengthy Services With Bare Conductor To Improve A Low Voltage From Existing 63 Kva S/Stn. (Jr), Replacement Of Existing Lengthy Services With Bare Conductor To Improve A Low Voltage From Existing 63 Kva S/Stn. Np) ( Nehrian Pathar),Prov. 11/0.4 Kv, 100 Kva S/Stn. , providing 3 Ph Lt Line At Nehrian Bazar & New 3 Ph. Lt Line From 63 Kva S/Stn. At Vill. Kuthera Kherla Ward No- 1 & providing Additional Poles For Strengthing In Lt Line In Various S/Stn. In (E) Section Nehrian & Panjoa Under Esd Hpsebl Nehrian ( Bid No.- Aed/123/2025-26). T.S No.- 131,132,133/2025-26 & 46,49,50&52/2026-27.
BOQ
| Sl. No. | Item Description |
| 1 | ERECTION PART of LT line (Prop. 100 KVA S/Stn. Nehri Bazar) . |
| 2 | Erection of LT line. Digging of pit, errection of PCC pole 8 mtr.long, errection of C.I X-arm, Shakle insulators, D-iron and filling of pit and remming etc complete in all respect. |
| 3 | Erection of stay Set.:- Digging of pit of stay, fixing of stay rod, noziling and tightening and filling of pit ramming etc.complete in all respect. |
| 4 | Earthing:- Digging of pit, fixing of G.I wire to the earthing system and filling of pit and raiming etc.complete in all respect. |
| 5 | Laying of conductor:- Laying of conductor, striging, sagging and biding with insulator with 7/3.15 mm Conductor line length =1.195 kms .complete in all respect., |
| 6 | G.I Wire:- Laying of GI wire stringing and sagging and biding with hock etc. complete in all respect. |
| 7 | Add Inspection Charges of HT/LT/Dtr. |
| 8 | Mannual carriage of material at destination site. |
| 9 | Sub- Total |
| 10 | Supply Part of LT Line |
| 11 | Prov. STP Pole 8 mtr long ( Qty.:- 3, Unit :- No. Provided by HPSEBL) |
| 12 | Prov. RCC Muffs (2000mm) with concerete filling ( Qty.:- 3 , Unit :- No. Provided by HPSEBL) |
| 13 | Prov. AAAC Conductor 7/3.15 mm i/c 3% cutting, wastage & sagging. ( Qty.:- 0.700, Unit :- Kms Provided by HPSEBL) |
| 14 | Prov. G.I.Wire No.8 SWG for earth ( 1.02 kms ). |
| 15 | Prov.M S C.I- X-Arm ( 75X40X 6) 1.50 Mtr. long |
| 16 | Prov.MS Half Clamp (M.S FLATE 50X6mm) |
| 17 | Prov.MS Full Clamp (M.S FLATE 50X6mm) |
| 18 | Prov.Nut-Bolts in kg. |
| 19 | Prov.Shackle Insulators 16 kn with M.S.D-Iron |
| 20 | Prov. Egg. Insulator. |
| 21 | Prov.Earth Knob. |
| 22 | Prov.L.T. Stay Set complete in all respect |
| 23 | Stay Wire (7/3.15 mm) (6.0 kg Per Stay Set) |
| 24 | Prov.L.T. Earthing set complete in all respect. |
| 25 | Prov.PVC Spacer |
| 26 | Prov. Aluminium Paint |
| 27 | ERECTION PART of LT line ( Replacement of Lengthy Services existing 63 KVA S/Stn. Jowar) |
| 28 | Erection of LT line. Digging of pit, errection of PCC pole 8 mtr.long, errection of C.I X-arm, Shakle insulators, D-iron and filling of pit and remming etc complete in all respect. |
| 29 | Erection of stay Set.:- Digging of pit of stay, fixing of stay rod, noziling and tightening and filling of pit ramming etc.complete in all respect. |
| 30 | Earthing:- Digging of pit, fixing of G.I wire to the earthing system and filling of pit and raiming etc.complete in all respect. |
| 31 | Laying of conductor:- Laying of conductor, striging, sagging and biding with insulator with 7/3.15 mm Conductor line length =0.536 kms .complete in all respect., |
| 32 | G.I Wire:- Laying of GI wire stringing and sagging and biding with hock etc. complete in all respect. |
| 33 | Add Inspection Charges of HT/LT/Dtr. |
| 34 | Mannual carriage of material at destination site. |
| 35 | Supply Part of LT Line |
| 36 | Prov. STP Pole 8 mtr long ( Qty.:- 4, Unit :- No. Provided by HPSEBL) |
| 37 | Prov. RCC Muffs (2000mm) with concerete filling . |
| 38 | Prov. AAAC Conductor 7/3.15 mm i/c 3% cutting, wastage & sagging. ( Qty.:- 0.536, Unit :- Kms Provided by HPSEBL) |
| 39 | Prov. G.I.Wire No.8 SWG for earth ( 1.02 kms ). |
| 40 | Prov.M S C.I- X-Arm ( 75X40X 6) 1.50 Mtr. long |
| 41 | Prov.MS Half Clamp (M.S FLATE 50X6mm) |
| 42 | Prov.MS Full Clamp (M.S FLATE 50X6mm) |
| 43 | Prov.Nut-Bolts in kg. |
| 44 | Prov.Shackle Insulators 16 kn with M.S.D-Iron |
| 45 | Prov. Egg. Insulator. |
| 46 | Prov.Earth Knob. |
| 47 | Prov.L.T. Stay Set complete in all respect |
| 48 | Stay Wire (7/3.15 mm) (6.0 kg Per Stay Set) |
| 49 | Prov.L.T. Earthing set complete in all respect. |
| 50 | Prov.PVC Spacer |
| 51 | Prov. Aluminium Paint |
| 52 | ERECTION PART of LT line ( Nehrian Patehar) |
| 53 | Erection of LT line. Digging of pit, errection of PCC pole 8 mtr.long, errection of C.I X-arm, Shakle insulators, D-iron and filling of pit and remming etc complete in all respect. |
| 54 | Erection of stay Set.:- Digging of pit of stay, fixing of stay rod, noziling and tightening and filling of pit ramming etc.complete in all respect. |
| 55 | Earthing:- Digging of pit, fixing of G.I wire to the earthing system and filling of pit and raiming etc.complete in all respect. |
| 56 | Laying of conductor:- Laying of conductor, striging, sagging and biding with insulator with 7/3.15 mm Conductor line length =1.195 kms .complete in all respect., |
| 57 | G.I Wire:- Laying of GI wire stringing and sagging and biding with hock etc. complete in all respect. |
| 58 | Add Inspection Charges of HT/LT/Dtr. |
| 59 | Mannual carriage of material at destination site. |
| 60 | Supply Part of LT Line |
| 61 | Prov. STP Pole 8 mtr long ( Qty.:- 4, Unit :- No. Provided by HPSEBL) |
| 62 | Prov. RCC Muffs (2000mm) with concerete filling . |
| 63 | Prov. AAAC Conductor 7/3.15 mm i/c 3% cutting, wastage & sagging. ( Qty.:- 0.536, Unit :- Kms Provided by HPSEBL) |
| 64 | Prov. G.I.Wire No.8 SWG for earth ( 1.02 kms ). |
| 65 | Prov.M S C.I- X-Arm ( 75X40X 6) 1.50 Mtr. long |
| 66 | Prov.MS Half Clamp (M.S FLATE 50X6mm) |
| 67 | Prov.MS Full Clamp (M.S FLATE 50X6mm) |
| 68 | Prov.Nut-Bolts in kg. |
| 69 | Prov.Shackle Insulators 16 kn with M.S.D-Iron |
| 70 | Prov. Egg. Insulator. |
| 71 | Prov.Earth Knob. |
| 72 | Prov.L.T. Stay Set complete in all respect |
| 73 | Stay Wire (7/3.15 mm) (6.0 kg Per Stay Set) |
| 74 | Prov.L.T. Earthing set complete in all respect. |
| 75 | Prov.PVC Spacer |
| 76 | Prov. Aluminium Paint |
| 77 | ERECTION PART of LT line 63 KVA DTr Kuthera Kherla |
| 78 | Erection of LT line. Digging of pit, errection of PCC pole 8 mtr.long, errection of C.I X-arm, Shakle insulators, D-iron and filling of pit and remming etc complete in all respect. |
| 79 | Erection of stay Set.:- Digging of pit of stay, fixing of stay rod, noziling and tightening and filling of pit ramming etc.complete in all respect. |
| 80 | Earthing:- Digging of pit, fixing of G.I wire to the earthing system and filling of pit and raiming etc.complete in all respect. |
| 81 | Laying of conductor:- Laying of conductor, striging, sagging and biding with insulator with 7/3.15 mm Conductor line length =1.195 kms .complete in all respect., |
| 82 | G.I Wire:- Laying of GI wire stringing and sagging and biding with hock etc. complete in all respect. |
| 83 | Add Inspection Charges of HT/LT/Dtr. |
| 84 | Mannual carriage of material at destination site. |
| 85 | Supply Part of LT Line |
| 86 | Prov. STP Pole 8 mtr long ( Qty.:- 1, Unit :- No. Provided by HPSEBL) |
| 87 | Prov. RCC Muffs (2000mm) with concerete filling. |
| 88 | Prov. AAAC Conductor 7/3.15 mm i/c 3% cutting, wastage & sagging. ( Qty.:- 0.200, Unit :- Kms Provided by HPSEBL) |
| 89 | Prov. G.I.Wire No.8 SWG for earth ( 1.02 kms ). |
| 90 | Prov.M S C.I- X-Arm ( 75X40X 6) 1.50 Mtr. long |
| 91 | Prov.MS Half Clamp (M.S FLATE 50X6mm) |
| 92 | Prov.MS Full Clamp (M.S FLATE 50X6mm) |
| 93 | Prov.Nut-Bolts in kg. |
| 94 | Prov.Shackle Insulators 16 kn with M.S.D-Iron |
| 95 | Prov. Egg. Insulator. |
| 96 | Prov.Earth Knob. |
| 97 | Prov.L.T. Stay Set complete in all respect |
| 98 | Stay Wire (7/3.15 mm) (6.0 kg Per Stay Set) |
| 99 | Prov.L.T. Earthing set complete in all respect. |
| 100 | Prov.PVC Spacer |
| 101 | Prov. Aluminium Paint |
| 102 | ERECTION PART of LT line Additional Poles |
| 103 | Erection of STP of LT line. Digging of pit, errection of PCC pole 8 mtr.long, errection of C.I X-arm, Shakle insulators, D-iron and filling of pit and remming etc complete in all respect. |
| 104 | Erection of stay Set.:- Digging of pit of stay, fixing of stay rod, noziling and tightening and filling of pit ramming etc.complete in all respect. |
| 105 | Earthing:- Digging of pit, fixing of G.I wire to the earthing system and filling of pit and raiming etc.complete in all respect. |
| 106 | Mannual carriage of material at destination site. |
| 107 | Supply Part of LT Line |
| 108 | Prov. STP Pole 8 mtr long ( Qty.:- 4, Unit :- No. Provided by HPSEBL) |
| 109 | Prov. RCC Muffs (2000mm) with concerete filling |
| 110 | Prov.M S C.I- X-Arm ( 75X40X 6) 1.50 Mtr. long |
| 111 | Prov.MS Half Clamp (M.S FLATE 50X6mm) |
| 112 | Prov.MS Full Clamp (M.S FLATE 50X6mm) |
| 113 | Prov.Nut-Bolts in kg. |
| 114 | Prov.Shackle Insulators 16 kn with M.S.D-Iron |
| 115 | Prov. Egg. Insulator. |
| 116 | Prov.Earth Knob. |
| 117 | Prov.L.T. Stay Set complete in all respect |
| 118 | Stay Wire (7/3.15 mm) (6.0 kg Per Stay Set) |
| 119 | Prov.L.T. Earthing set complete in all respect. |
| 120 | Prov.PVC Spacer |
| 121 | ERECTION PART (Sub-Station).1 Nos Kuthera Kherla 50/2026-27. |
| 122 | Erection of 11/0.4 KV , 63 KVA S/Stn. Str.:-Digging of Pit for S/T Pole and earthing, drilling of holes in X-arm, preparation of plate form str. Member CI, AI i.e X-arml, Knee bracing set, errection of D-pole,errection of plate form, errcetion of x-Arm, drop out, fuse unit, linghting arrestor, MCCB Switch of LT Box, Energy Meter, Errection of T/F, and earthing conn. to T/F G.O Switch lightning etc. errection of Stay Set, Errection of Jumper, Pipe earthing 3 Nos., Errection of LT cable, brabed wire and painting, 3 Nos. earthing to S/Stn. by prov. 50Kg Salt charcole in each earthing i/c construction of trench for earthing as per REC Board Standard complete in all respect , complete in all respect. |
| 123 | Add Inspection Charges of HT/LT/Dtr. |
| 124 | Mannual carriage of material at destination site. |
| 125 | Sub- Total |
| 126 | Sub-Station Supply Material |
| 127 | Prov. Distribution Transformer (Ordinary), 11/0.4 kV, 63 KVA ( Qty.:- 1 , Unit :- No. Provided by HPSEBL) |
| 128 | Prov. Steel Tubular Poles (9 m, Working Load > 200 kgf/m²) ( Qty.:- 2 , Unit :- No. Provided by HPSEBL) |
| 129 | Prov. RCC Muffs (2000mm) with concerete filling . |
| 130 | X-Arm: [Channel Iron (100x50x6 mm), Length : 2800 mm X 2 Nos] |
| 131 | MS Angle Iron (50X50x6 mm), Length: 2800 x1 Nos for LA's |
| 132 | X-Arm: [Channel Iron (75x40x6 mm), Length : 2800 mm X 4 Nos] for supporting DO fuse unit & GO switch |
| 133 | Transformer Bed, Belting & Knee Bracing |
| 134 | X-Arm: [Channel Iron (100x50x6 mm), Length : 2800 mm X 2 Nos] for Transformer Bed |
| 135 | X-Arm [Channel Iron (100x50x6 mm), Length : (460 mm) x 2 Nos for supporting Main Channel of Transformer] |
| 136 | MS Angle Iron (50X50x6 mm), Length : (2800 mm) x 2 Nos |
| 137 | MS Angle Iron (35X35x5 mm), Length : 460 x 2 Nos |
| 138 | MS Angle Iron (50X50x6 mm), Length : 950 mm x 2 Nos for Bed Knee Bracing |
| 139 | Transformer LT Dist Box and GO Switch fixing Assembly |
| 140 | MS Angle Iron (50X50x6 mm), Length : (2800 mm) x 2 Nos |
| 141 | MS Angle Iron (50X50x6 mm), Length : (450 mm) x 1 Nos |
| 142 | GO Switch Handle Supporting: [Channel Iron (75x40x5 mm), Length : 460 mm |
| 143 | GO AB Switch Unit (11kV, 400A, 25 KA ) Tripple pole O/D type |
| 144 | D.O Fuse Unit |
| 145 | Surge Arrester, 9 kV Station Class (Porcelain Type) |
| 146 | Discs insulator sets (comprising 1 No. Disc: ^^(Porcelain, BS, 12 kV, 90 kN) including Dead End Clamps etc.) |
| 147 | Stay set complete |
| 148 | Stay Wire (7/3.15 mm) (7.0 kg Per Stay Set) |
| 149 | Pipe Earthing Set |
| 150 | 6 SWG GI wire For Earthing |
| 151 | LT Distribution Panel Box with MCCB(50A, 25 kA, 4P) |
| 152 | Half Clamp (M.S. Flat 50X6 mm) |
| 153 | Full Clamps (M.S. Flat 50X6 mm) |
| 154 | Nuts and Bolts of Various Sizes (Galvanised / Coated) [Preferably 16 mm Φ or more (with flat and spring washers)] |
| 155 | Aluminium Thimble |
| 156 | Copper Thimble 200 Amp |
| 157 | Danger Plate |
| 158 | Barbed Wire |
| 159 | LT Cable (3.5 Core) 70 mm² |
| 160 | LT Cable (3.5 Core) 95 mm² |
| 161 | Aluminium Paint. |
| 162 | Chain link gate fencing |
| 163 | ERECTION PART (Sub-Station).1 Nos Kuthera Kherla 133/2025-26. |
| 164 | Erection of 11/0.4 KV , 63 KVA S/Stn. Str.:-Digging of Pit for S/T Pole and earthing, drilling of holes in X-arm, preparation of plate form str. Member CI, AI i.e X-arml, Knee bracing set, errection of D-pole,errection of plate form, errcetion of x-Arm, drop out, fuse unit, linghting arrestor, MCCB Switch of LT Box, Energy Meter, Errection of T/F, and earthing conn. to T/F G.O Switch lightning etc. errection of Stay Set, Errection of Jumper, Pipe earthing 3 Nos., Errection of LT cable, brabed wire and painting, 3 Nos. earthing to S/Stn. by prov. 50Kg Salt charcole in each earthing i/c construction of trench for earthing as per REC Board Standard complete in all respect , complete in all respect. |
| 165 | Add Inspection Charges of HT/LT/Dtr. |
| 166 | Mannual carriage of material at destination site. |
| 167 | Sub- Total |
| 168 | Sub-Station Supply Material |
| 169 | Prov. Distribution Transformer (Ordinary), 11/0.4 kV, 63 KVA ( Qty.:- 1 , Unit :- No. Provided by HPSEBL) |
| 170 | Prov. Steel Tubular Poles (9 m, Working Load > 200 kgf/m²) ( Qty.:- 2 , Unit :- No. Provided by HPSEBL) |
| 171 | Prov. RCC Muffs (2000mm) with concerete filling . |
| 172 | X-Arm: [Channel Iron (100x50x6 mm), Length : 2800 mm X 2 Nos] |
| 173 | MS Angle Iron (50X50x6 mm), Length: 2800 x1 Nos for LA's |
| 174 | X-Arm: [Channel Iron (75x40x6 mm), Length : 2800 mm X 4 Nos] for supporting DO fuse unit & GO switch |
| 175 | Transformer Bed, Belting & Knee Bracing |
| 176 | X-Arm: [Channel Iron (100x50x6 mm), Length : 2800 mm X 2 Nos] for Transformer Bed |
| 177 | X-Arm [Channel Iron (100x50x6 mm), Length : (460 mm) x 2 Nos for supporting Main Channel of Transformer] |
| 178 | MS Angle Iron (50X50x6 mm), Length : (2800 mm) x 2 Nos |
| 179 | MS Angle Iron (35X35x5 mm), Length : 460 x 2 Nos |
| 180 | MS Angle Iron (50X50x6 mm), Length : 950 mm x 2 Nos for Bed Knee Bracing |
| 181 | Transformer LT Dist Box and GO Switch fixing Assembly |
| 182 | MS Angle Iron (50X50x6 mm), Length : (2800 mm) x 2 Nos |
| 183 | MS Angle Iron (50X50x6 mm), Length : (450 mm) x 1 Nos |
| 184 | GO Switch Handle Supporting: [Channel Iron (75x40x5 mm), Length : 460 mm |
| 185 | GO AB Switch Unit (11kV, 400A, 25 KA ) Tripple pole O/D type |
| 186 | D.O Fuse Unit |
| 187 | Surge Arrester, 9 kV Station Class (Porcelain Type) |
| 188 | Discs insulator sets (comprising 1 No. Disc: ^^(Porcelain, BS, 12 kV, 90 kN) including Dead End Clamps etc.) |
| 189 | Stay set complete |
| 190 | Stay Wire (7/3.15 mm) (7.0 kg Per Stay Set) |
| 191 | Pipe Earthing Set |
| 192 | 6 SWG GI wire For Earthing |
| 193 | LT Distribution Panel Box with MCCB(50A, 25 kA, 4P) |
| 194 | Half Clamp (M.S. Flat 50X6 mm) |
| 195 | Full Clamps (M.S. Flat 50X6 mm) |
| 196 | Nuts and Bolts of Various Sizes (Galvanised / Coated) [Preferably 16 mm Φ or more (with flat and spring washers)] |
| 197 | Aluminium Thimble |
| 198 | Copper Thimble 200 Amp |
| 199 | Danger Plate |
| 200 | Barbed Wire |
| 201 | LT Cable (3.5 Core) 70 mm² |
| 202 | LT Cable (3.5 Core) 95 mm² |
| 203 | Aluminium Paint. |
| 204 | Chain link gate fencing |
| 205 | ERECTION PART (Sub-Station).1 Nos at Nehrian Bazar |
| 206 | Erection of 11/0.4 KV , 100 KVA S/Stn. Str.:-Digging of Pit for S/T Pole and earthing, drilling of holes in X-arm, preparation of plate form str. Member CI, AI i.e X-arml, Knee bracing set, errection of D-pole,errection of plate form, errcetion of x-Arm, drop out, fuse unit, linghting arrestor, MCCB Switch of LT Box, Energy Meter, Errection of T/F, and earthing conn. to T/F G.O Switch lightning etc. errection of Stay Set, Errection of Jumper, Pipe earthing 3 Nos., Errection of LT cable, brabed wire and painting, 3 Nos. earthing to S/Stn. by prov. 50Kg Salt charcole in each earthing i/c construction of trench for earthing as per REC Board Standard complete in all respect , complete in all respect. |
| 207 | Add Inspection Charges of HT/LT/Dtr. |
| 208 | Mannual carriage of material at destination site. |
| 209 | Sub- Total |
| 210 | Sub-Station Supply Material |
| 211 | Prov. Distribution Transformer (Ordinary), 11/0.4 kV, 100 KVA ( Qty.:- 1 , Unit :- No. Provided by HPSEBL) |
| 212 | Prov. Steel Tubular Poles (9 m, Working Load > 200 kgf/m²) ( Qty.:- 2 , Unit :- No. Provided by HPSEBL) |
| 213 | Prov. RCC Muffs (2000mm) with concerete filling . |
| 214 | X-Arm: [Channel Iron (100x50x6 mm), Length : 2800 mm X 2 Nos] |
| 215 | MS Angle Iron (50X50x6 mm), Length: 2800 x1 Nos for LA's |
| 216 | X-Arm: [Channel Iron (75x40x6 mm), Length : 2800 mm X 4 Nos] for supporting DO fuse unit & GO switch |
| 217 | Transformer Bed, Belting & Knee Bracing |
| 218 | X-Arm: [Channel Iron (100x50x6 mm), Length : 2800 mm X 2 Nos] for Transformer Bed |
| 219 | X-Arm [Channel Iron (100x50x6 mm), Length : (460 mm) x 2 Nos for supporting Main Channel of Transformer] |
| 220 | MS Angle Iron (50X50x6 mm), Length : (2800 mm) x 2 Nos |
| 221 | MS Angle Iron (35X35x5 mm), Length : 460 x 2 Nos |
| 222 | MS Angle Iron (50X50x6 mm), Length : 950 mm x 2 Nos for Bed Knee Bracing |
| 223 | Transformer LT Dist Box and GO Switch fixing Assembly |
| 224 | MS Angle Iron (50X50x6 mm), Length : (2800 mm) x 2 Nos |
| 225 | MS Angle Iron (50X50x6 mm), Length : (450 mm) x 1 Nos |
| 226 | GO Switch Handle Supporting: [Channel Iron (75x40x5 mm), Length : 460 mm |
| 227 | GO AB Switch Unit (11kV, 400A, 25 KA ) Tripple pole O/D type |
| 228 | D.O Fuse Unit |
| 229 | Surge Arrester, 9 kV Station Class (Porcelain Type) |
| 230 | Discs insulator sets (comprising 1 No. Disc: ^^(Porcelain, BS, 12 kV, 90 kN) including Dead End Clamps etc.) |
| 231 | Stay set complete |
| 232 | Stay Wire (7/3.15 mm) (7.0 kg Per Stay Set) |
| 233 | Pipe Earthing Set |
| 234 | 6 SWG GI wire For Earthing |
| 235 | LT Distribution Panel Box with MCCB(50A, 25 kA, 4P) |
| 236 | Half Clamp (M.S. Flat 50X6 mm) |
| 237 | Full Clamps (M.S. Flat 50X6 mm) |
| 238 | Nuts and Bolts of Various Sizes (Galvanised / Coated) [Preferably 16 mm Φ or more (with flat and spring washers)] |
| 239 | Aluminium Thimble |
| 240 | Copper Thimble 200 Amp |
| 241 | Danger Plate |
| 242 | Barbed Wire |
| 243 | LT Cable (3.5 Core) 70 mm² |
| 244 | LT Cable (3.5 Core) 95 mm² |
| 245 | Aluminium Paint. |
| 246 | Chain link gate fencing Please Enable Macros to View BoQ information |
AI Tender Summary
Tender Timeline
Tender Published
Tender notice published.
CompletedBid Submission Deadline
Online submission via eProcurement portal.
Upcoming · 1 dayBid Opening Date
Technical bids will be opened and evaluated.
Upcoming · 1 dayTender Documents
Download All (ZIP) ↓We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender