Tender For S : Conversion Of Existing 11Kv Ht,Lt Over Head Line And Service Connection Wires Into Ug Cable To Avoid Any Untoward Incident During The Celebration Of Car Festivals In The Shri Mangalanathaswami Temple At Thiru Uthirakosamangai Village.
Tender Overview
Project Description
Tender for S : Conversion Of Existing 11Kv Ht,Lt Over Head Line And Service Connection Wires Into Ug Cable To Avoid Any Untoward Incident During The Celebration Of Car Festivals In The Shri Mangalanathaswami Temple At Thiru Uthirakosamangai Village.
BOQ
| Sl. No. | Item Description |
| 1 | Transportaion of the remains of the empty cable drums (iron materials)( to the stores for devolution including loading and unloading, leads and lifts, etc., complete. |
| 2 | Loading and unloading of HT Cable including coiling and recoiling |
| 3 | Laying of 11KV 3X120 sqmm XLPE cable including cost of all materials.labour lead lift etc complete. |
| 4 | Cutting the cable of required length and sealing the ends with suitable end caps for 11 KV XLPE cables, including cost of all materials, Tools and Plants,leads and lifts etc., complete. |
| 5 | Loading & Unloading ,Transporting,Excavation and Erection 400KG 9.0M PSC Pole (Material supplied by TNPDCL) |
| 6 | Loading & Unloading,Transporting, Excavation and Erection 300KG 9.0M PSC POLE (Material supplied by TNPDCL) |
| 7 | Erection HT TI fitting (Material supplied by TNPDCL) |
| 8 | Erection Tapping Channel cross arm (Material supplied by TNPDCL) |
| 9 | Erection of stay set complete with Guy insulator including excavation of pit (Material supplied by TNPDCL) |
| 10 | Erection of 11KV Polymer Composite Disc Insulator With Metal Parts (Material supplied by TNPDCL) |
| 11 | Loading and unloading of LT 4 x 240 sqmm Cable including coiling and recoiling (Material supplied by TNPDCL) |
| 12 | Loading & Unloading ,Excavation and Erection 200KG 8.0M PSC Pole (Material supplied by TNPDCL) |
| 13 | ERECTION OF BASE PLATE (Material supplied by TNPDCL) |
| 14 | ERECTION OF LT 3PH CROSS ARM WITH BACK CLAMP (Material supplied by TNPDCL) |
| 15 | ERECTION OF LT TI FITTINGS WITH STAY CLAMP (Material supplied by TNPDCL) |
| 16 | ERECTION OF LT SHACKLE INSULATOR WITH METAL PARTS (Material supplied by TNPDCL) |
| 17 | ERECTION OF STAY SET COMPLETE WITH GUY INSULATOR including excavation of PIT (Material supplied by TNPDCL) |
| 18 | Erection of 34No's of 4Way pillar 12 No's of 6 Way pillar box - 3 Feet Height using concrete only - including excavation of foundation pits as per standard specification 2 Nos pillar concrete walls, coping and earthing including cost of all materials, el. works, transportation, lead, lift etc., |
| 19 | Erection of Mini pillar box - 3 Feet Height using concrete only - including excavation of foundation pits as per standard specification 2 Nos pillar concrete walls, coping and earthing including cost of all materials, el. works, transportation, lead, lift etc., |
| 20 | Cleaning & painting with Aluminium paint 2 coats & numbering with fdr details with materials - 34No's of 4Way pillar 12 No's of 6 Way pillar box |
| 21 | Cleaning & painting with Aluminium paint 2 coats & numbering with fdr details with materials - Mini Pillar Box |
| 22 | Erection of Cable Joint loction marker (engraving TNPDCL cable Joint) |
| 23 | Loading and unloading of LT Cable including coiling and recoiling |
| 24 | Laying of LT 2 X 16 sq.mm cable (Material supplied by TNPDCL) |
| 25 | Laying of LT 4 X 25 sq.mm cable (Material supplied by TNPDCL) |
| 26 | Erection of Termination kit OD HS 11KV, 3X120 Sq mm |
| 27 | Erection of Spl. Type clamp for 11 KV cable |
| 28 | Erection PVC pipes 50mm DIA |
| 29 | Erection PVC bend 50mm DIA |
| 30 | Erection of OD Termination Kit ( Outdoor - HS Type) for LT 4x240sq mm |
| 31 | Erection of Outdoor Straight joint kit LT 4x240 sq mm |
| 32 | Erection of Alu. lug 120 Sq mm |
| 33 | Erection of \\"U\\" clamp for cable |
| 34 | Erection of GI pipe 40mm 10' length |
| 35 | Erection of of GI pipe 40mm bend |
| 36 | Erection of LUG ALU 16 SQMM |
| 37 | Erection of LUG ALU 25 SQMM |
| 38 | Dismantling of 9.0 Mtr Psc Pole |
| 39 | Dismantling of 1068 mm (3'-6\\") V Cross arm |
| 40 | Dismantling of Tapping channel cross arm |
| 41 | Dismantling of HT TI Fitting |
| 42 | Dismantling of 3 PHASE CROSS ARM |
| 43 | Dismantling of 11 KV DISC & METAL PARTS |
| 44 | Dismantling of 11 KV HT PIN & INSULATOR SCRAP |
| 45 | Dismantling of LT INSULATOR & PIN SCRAP |
| 46 | Dismantling of LT Shakcle & Metal parts |
| 47 | Dismantling of 7/3.35 ACSR Conductor |
| 48 | Dismantling of 7/2.59 ACSR Conductor |
| 49 | Dismantling of SINGLE PHASE CROSS ARM |
| 50 | Cutting open the black topped road surface for a width of 0.6m and a depth of 0.2m, including the cost of providing signal boards, lights, watch and ward to regulate the traffic, taking all precautions to protect the men, materials and the public from any possible accidents etc., using JCB / air compressor / drilling machines etc., whereever necessary at anytime throughout the day including taking all precautions to prevent any damage to the telecom and water lines. |
| 51 | Earth work excavation in all soils including slush and silt under water requiring the aid of basket and vessels and forming cable trench and cable duct including cost of providing sign boards, danger lights, indication arrangements wherever necessary and providing shoring and strutting arrangements wherever necessary, all lead, lift, labour, tools & plants, etc., complete. |
| 52 | Providing sand bedding with good quality of sand to a depth upto 300mm including cost of materials, labour, leads and lifts etc.., complete |
| 53 | Refilling with excavated earth, consolidating in layers and the top brought for line with the existing surface including cost of labour lead lift etc.., complete |
| 54 | Providing and laying plain cement concrete 1:3:6 using 40mm HBG metal including cost of all materials.labour lead lift curing hire charges for mixer machine etc complete. Without formwork |
| 55 | Providing RCC 1:1.5:3 using 20mm to 12mm down graded HBG metal including cost of all materials, labour lift, hire charges for mixer machine vibrator with form work but excluding cost of providing reinforcement for bottom raft |
| 56 | Providing and laying plain cement concrete 1:2:4 using 40mm HBG metal including cost of all materials.labour lead lift curing hire charges for mixer machine etc complete. With Formwork |
| 57 | Providing Precast slab RCC 1:1.5:3 using 20mm to 12mm down graded HBG metal of size 0.6m x 0.5m x 0.05m excluding cost of steel reinforcements, all materials, labour, lead, lift, hire charges for mixer machine vibrator with form work etc., complete, For placing above the cable in the trench |
| 58 | Supplying fabricating and placing in position of RTS/MS reinforcement including cost of steel , cutting bending tying in position cost of binding wire all lead lift etcgrills and placing them complete. |
| 59 | Laying of LT Aluminium cable 4x240 sqmm UG cable by means of winch over rollers provided by contractor. The rate includes the cost of pulling the steel wire rope from winch side to drum side providing labour as trefoil formation with nylon rope/etc., complete.required at site for tying the cable in trefoil formation with nylon rope/etc., complete. |
| 60 | Plastering with CM 1:3, mix 12mm thick for RCC side wall including all cost labour materials lead lift labour curing etc complete. |
| 61 | Laying the warning grid tape including cost of all materials, including cost of all materials, labour for cutting and pasting with adhesive, lead, lift, T&P etc complete |
| 62 | Colour washing with exterior emulsion over one coat of primer in out & inside wall including cost of all materials labour, lead, lift etc complete. |
| 63 | Providing MS barricading 1.5m height using MS sheet 4mm thick MS angle 50x50x8mm base channel 100x50 of all materials, leads, lifts, labour, welding and erection, transporting at site, placing in position, shifting to new location after completing works, tools & plants etc., complete Please Enable Macros to View BoQ information |
AI Tender Summary
Tender Timeline
Tender Published
Tender notice published.
CompletedBid Submission Deadline
Online submission via eProcurement portal.
Upcoming · 4 daysBid Opening Date