Power Boards / Undertakings / PSU Closing in 2 days TDR #58172451

Tender For Shifting Of Electrical Assets (Poles With Lines And Transformers) Coming Between The Canal Covering From Call Tax To Saurab Hotel, Haldwani Under Edd (Town) Haldwani

Issued by Boards / Undertakings / PSU · Nainital, Uttarakhand
Tender Value
Ref. Documents
Estimated cost
Bid Submission
12 Nov 2026
2 days left
EMD
75000
Bank guarantee accepted
Document Fee
2360
Non-refundable
Tender Type
Online

Tender Overview

Competition Type
NCB
Bidding Type
Tender
Location / State
Nainital → Uttarakhand
EMD Exemption
Available
Quantity
Not Available

Project Description

Tender for Shifting Of Electrical Assets (Poles With Lines And Transformers) Coming Between The Canal Covering From Call Tax To Saurab Hotel, Haldwani Under Edd (Town) Haldwani

Corrigendum

Sr No Corrigendum Date Corrigendum Type New Submission Date
1 31-Oct-2026 Date Extenson 1 Date 12-Nov-2026

BOQ

Name of Work:- Shifting of Electrical assets (poles with lines and transformers) coming between the canal covering from Call Tax to Saurab Hotel, Haldwani under EDD (Town) Haldwani
Sl. No. Item Description
1Total amount of the \\"Rate Schedule\\" sheet Schedule of Quantity and Rate for Work of Shifting of Electrical assets (poles with lines and transformers) coming between the canal covering from Call Tax to Saurab Hotel, Haldwani under EDD (Town) Haldwanii. Against E-Tender Specification No. 59/EDC(H)/2026-27 Name of The Bidder's Firm: 0.0 Sl. No. Description of Work Unit Qty Rate Amount Part [A] (Supply Portion)
2Holding Clamp for SP-55 with N/B
3LT CLAMP WITH N&B ST POLE SP-55
4Stay Clamp for SP-55 With Nut & Bolt
5MS CLAMP WITH N&B FOR DISTRIBUTION BOX
6SHACKLE INSULATOR 75X90 mm WITH NUT BOLT
7STAY INSULATOR
8BRACING CLAMP FOR ST POLE WITH N&B
9ACSR DOG (INSULATED/COVERED)
10LT DISTRUBITON BOX 3 PHASE
11Al. Lug Long Barrel 120 sq. mm.
12Al. Lug Long Barrel 240 sq. mm.
13Al. Lug Long Barrel 400 sq. mm. Total - Part [A] 0.0 Part [B] (Labour Portion)
14Chemical Earthing:Earthing of distribution transformer including digging of pit of size 2.5 Mtr depth and make hole of size 150 mm. Placing of earthing electrode (to be supplied by contractor as per drawing No. A) as drawing B, connecting the same with G.I. Strip (to be supplied by contractor ) of size 35x6 mm as per drawing C for a minimum lenght 6 m. treatment of soil with highly condctive substance as per IS 30343 complete in all respect, result of earthing resistance to be recroded in M.B. before and after installation of earthing. The earth resistance after earthing should be less than 1 Ohm.
15Erection & Earthing of support with M.S. Earth rod of 2.5 meter long by hammaring of M.S. Rod to proper depth and conecting the earth electrode with the helpof G.I. Wire as per construction mannual
16Fabrication of M.S. Channel Angle iron after cutting in required sizes with drilling of holes upto good finish for top channel, bracing and special type bracket etc. as per RESSPO sehedule and local approved drawing.
17RE-ALIGNMENT OF TPMO
18EXCAVATION OF PIT FOR STAY SET
19Grouting of stay in size 0.6x0.6x0.3 in CC ratio 1:4:8 (1 cement : 4 graded stone 20mm nominal size : 8 coarse sand ) block including cost of cement, sand and stone ballast back filling of soil and boulders in pit and ramming and proper alignment, leveling as per RESPO Manuel .
20Excavation of earth for pole pit of size 0.9x0.6x1/6 of full length of pole for erection of pole in all type of soil including proper dressing of sides and ramming of bottom including getting out the excavated soil and disposal of surplus excavated soil as directed complete work
21Erection of following Single support pole in proper level and alignment alongwith fixing of all accessories, like top channel & clamps as per RESSPO construction Manual. i ERECTION OF SINGLE SP-55 POLE NOS 52.0 ii ERECTION OF SINGLE SP-72 POLE NOS 1.0
22Erection of SP-55 Double support pole in proper level and alignment alongwith fixing rjf dil accessories, like top channel, X-bracing & clamps as per RESSPO construction Manual.
23ERECTION OF SP-55(11KV/33 KV) FOUR POLE
24Grouting of pole in size 0.45x0.45x1/5 of the support in CC ratio 1:4:8 (1 cement: 4 graded stone 20mm nominal size : 8 coarse sand ) block including cost of Cement,sand and stone ballast back filling of soil and boulders in pit and ramming and proper alignment, leveling as per RESSPO construction Manual.
25Muffing of poles size 0.45 cm x 0.60 cm radious with cc 1:3:6 (1 cement: 3 coarse sand : 6 graded stone 10mm nominal size) block size 45cm height from ground level including cost of cement, stone and sand etc.
26DISMANTLING OF SP-55 SINGLE POLE
27DISMANTLING OF SP-55 DOUBLE POLE
28DISMANTLING OF SP-55 FOUR POLE
29DISMANTLING OF 11 KV LINE(RABBIT)
30DISMANTLING OF LT LINE 3 P 5 W(WEASEL)
31DISMANTLING OF 25 KVA DTR
32DISMANTLING OF 63 KVA DTR
33DISMANTLING OF 100 KVA DTR
34DISMANTLING OF 250 KVA DTR
35DISMANTLING OF 400 KVA DTR
36DISMANTLING OF GUARDING IN 11 KV LINE
37INSTALLATION OF LT PRMC
38EXCAVATION OF EARTH FOR DTR PLINTH
39CEMENT CONCRETING WORK DTR PLINTH
40BRICK WORK IN 1:4 RATIO DTR PLINTH
41RR MASSONARY WORK FOR DTR PLINTH
42RCC WORK OF DTR PLINTH.
43CEMENT PLASTER ON DTR PLINTH
44Providing and fixing of 50x35 wire mesh around the plinth duly welded with frame of MS Angle Iron 35x35x5 mm and strip in size 35x5mm in the middle of each side along with the wire mesh (width of wire mesh 1.1 mtr) with the height of 1.0 mtr above the plinth with one number gate and locking arrangement complete duly painted with two coats of Al. paint. (All material will be arranged by the contractor)
45INST. OF 400/500 KVA DTR ON POLE
46INST. OF 250 KVA DTR ON POLE STRUCTURE
47INST. OF 100 KVA DTR ON POLE STRUCTURE
48INST. OF 63 KVA DTR ON POLE STRUCTURE
49INST. OF 25 KVA DTR ON POLE STRUCTURE
50Mounting & Fixing of TPMO on double pole structures including making of connections complete work
51Mounting & Fixing of Fuse sets on double pole structures including making of connections complete work
52Mounting & Fixing of TPMO on double pole structures including making of connections complete work
53LAYING OF DOG CONDUCTOR IN HT LINE
54LAYING OF 3P 5W LT LINE (RABBIT)
55Guarding of Line over (Telephone / Road / L.T. line crossing as per drawing with 6/8 SWG G.I. wire including fixing of guarding channel/ angle as per RESSPO manual. LT./11KV /33KV
56CARTAGE SP-55 POLE, 0-20 KM
57CARTAGE OF PETTY MATERIAL,0-20 KM
58DISCONNECTION & RECONNECTION OF CONsumer
59DISMANTLING OF AB CABLE
60SERVICE OF HYDRA MACHINE
61TIGHTENING OF STAY SET
62DIGGING OF PIT THROUGH HAMMER AT CC, DAM
63BACK CARTAGE OF PETTY MATERIAL,0-20 KM
64LAYING & FIXING LT XLPE CABLE
65LAYING, SAGGING OF COVERED COND FOR 11KV
66LAYING OF 11 KV CABLE
67LOOPING AND CHOPPING OF TREE BRANCHES Total - Part [B] 0.0 TOTAL [Part-(A) + Part (B)] 0.0 GST: Extra Place Date Superintending Engineer Please Enable Macros to View BoQ information

AI Tender Summary

OUR REF NO 58172451
AUTHORITY Boards / Undertakings / PSU
TENDER VALUE Ref. Documents
LAST DATE 12-11-2026
Authority
Authority Name Uttarakhand Power Corporation Limited
Work Description Tender for Shifting Of Electrical Assets (Poles With Lines And Transformers) Coming Between The Canal Covering From Call Tax To Saurab Hotel, Haldwani Under Edd (Town) Haldwani
Basic Detail
Tender No EDC(H)/59/2026-27
Bidding Type Tender
Location
City Nainital
State Uttarakhand
Key Dates
Publish Date 31 Oct 2026
Submission Date 12 Nov 2026
Open Date 13 Nov 2026
Finance
Tender Value Ref. Documents
Tender Fee 2360
EMD 75000
Exemption Available
Document List
1141ac7d-e3ce-4e9a-b4a8-1c4c652adb63.html
BOQ_119630.xls
TECHNICAL59.pdf
TENDERFORM.pdf
Tendernotice_1.pdf

Unlock Full AI Tender Summary

Get instant access to the complete AI-generated analysis — scope, eligibility, timeline & more.

Instant Access Secure Free
Your details are secure and used only for document delivery.

Tender Timeline

Oct 31, 2026
11:30 IST

Tender Published

Tender notice published.

Completed
Nov 12, 2026
18:00 IST

Corrigendum-1 Issued

Clarifications on tender conditions and amendments issued.

Upcoming · 2 days
Nov 12, 2026
17:00 IST

Bid Submission Deadline

Online submission via eProcurement portal.

Upcoming · 2 days
Nov 13, 2026

Bid Opening Date

Technical bids will be opened and evaluated.

Upcoming · 3 days

Tender Documents

Download All (ZIP) ↓
html

1141ac7d-e3ce-4e9a-b4a8-1c4c652adb63.html

xls

BOQ_119630.xls

pdf

TECHNICAL59.pdf

pdf

TENDERFORM.pdf

pdf

Tendernotice_1.pdf

Disclaimer

We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender