Erection of new 33/11kV Indoor substation with 2x8 MVA PTR and Construction of control room and other Civil works near Centro Shopping Mall under Gachibowli Kondapur flyover Shilpa Phase II in Gachibowli and Kondapur Divisions of Cybercity circle in
Tender Overview
Project Description
Erection Of New 33/11Kv Indoor Substation With 2X8 MVA PTR And Construction Of Control Room And Other Civil Works Near Centro Shopping Mall Under Gachibowli Kondapur Flyover Shilpa Phase II In Gachibowli And Kondapur Divisions Of Cybercity Circle In Master Plan Sub Division I Of WCGH Division In Master Plan RR Circle
Corrigendum
| Sr No | Corrigendum Date | Corrigendum | Type | New Submission Date |
|---|---|---|---|---|
| 1 | 07-Nov-2026 | Insufficient Response by prospective Bidders, tender extended further one week with Hard copies to be submitted on 17.11.2026 on or before 12.00PM | 17-Nov-2026 | |
| 2 | 19-Nov-2026 | Insufficient Response by prospective Bidders, tender extended further one week with Hard copies to be submitted on 27.11.2026 on or before 12.00PM | 27-Nov-2026 |
AI Tender Summary
Tender Timeline
Tender Published
Tender notice published.
CompletedCorrigendum-1 Issued
Clarifications on tender conditions and amendments issued.
CompletedCorrigendum-2 Issued
Clarifications on tender conditions and amendments issued.
Upcoming · 4 daysBid Submission Deadline
Online submission via eProcurement portal.
Upcoming · 4 daysTender Documents