Drinking Water Supply and Sanitation Government Departments Closing in 12 days TDR #58147531

Tender For Used Water Management (Wps) For Nagar Palika Parishad Chirgaon Disst Jhansi Under Sbm (U) 2.0 Programme

Issued by Government Departments · Jhansi, Uttar Pradesh
Tender Value
2.43 Crore
Estimated cost
Bid Submission
05 Nov 2026
12 days left
EMD
4.87 Lakhs
Bank guarantee accepted
Document Fee
11800
Non-refundable
Tender Type
Online

Tender Overview

Competition Type
NCB
Bidding Type
Tender
Location / State
Jhansi → Uttar Pradesh
EMD Exemption
Available
Quantity
Not Available

Project Description

Tender for Used Water Management (Wps) For Nagar Palika Parishad Chirgaon Disst Jhansi Under Sbm (U) 2.0 Programme

BOQ

Name of Work:- Used Water Management (WPS) For Nagar Palika Parishad Chirgaon Disst Jhansi Under SBM (U) 2.0 Programme
Sl. No. Item Description
1Coarse Screen Chamber With Grit Chamber Before WSP
2Excavation 0.00 - 1.50 M deep in Ordiary Soil
3For Base, Extra Trangular Part and Extra Rectangular Part
4Cement concrete with 20 mm gauge approved stone ballast, coarse snad andcement in proportion of 1:4:8
5Base and For Slop
6R.C.C. With cement , Coarse Sand and 40 mm Stone Ballast 1:1.5:3 in RaftFoundations & Footing
7RCC Base,Side Wall,Trangular Wall,Overflow Wall and Outlet Wall
8Material : Extra for using 20 mm size stone Aggregate instead of 40 mm Size Stone Aggregate
9Qty Same As RCC Stone Ballast 20 mm Gauge and Stone Ballast 40 mm Gauge
10Mild Steel or Iron in Plain Work Steel reinforcement
11@1.5% Of RCC Qty
12Providing and fixing stainless steel ( Grade 304) railing made of Hollow tubes, channels, plates etc., including welding, grinding, buffing, polishing and making curvature (wherever required) and fitting the same with necessary stainless steel nuts and bolts complete, i/c fixing the railing with necessary accessories & stainless steel dash fasteners , stainless steel bolts etc., of required size, on the top of the floor or the side of waist slab with suitable arrangement as per approval of Engineer-in charge, (for payment purpose only weight of stainless steel members shall be considered excluding fixing accessories such as nuts, bolts,fasteners etc.)
1310 mm Sq Bar and Angle 35 x35 x6
14ESTIMATE OF WASTE STABILIZATION POND -300 KLD
15Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including getting out and disposal of excavated earth lead upto 50 m and for all lift, as directed by Engineer-in-charge. All kinds of soil
16Anaerobic Pond,Facultative Pond and Maturation Pond
17Banking With Excavated Earth
18Total Earthwork Qty
19Laying, Jointing 300mm Dia. RCC NP2 Hume Pipe 0.0-1.5 M
20Total Length = 60 m
21Random rubble masonry with hard stone in foundation and plinth including levelling up with cement concrete 1:6:12 (1 cement : 6 coarse sand : 12 graded stone aggregate 20 mm nominal size) upto plinth level with : Cement mortar 1:6 (1 cement : 6 coarsesand)
22Anaerobic Pond,Facultative Pond and Maturation Pond in Top Perifry,Bottom Perifry and on Slop
23Dry stone pitching 22.5 cm thick including supply of stones and preparing surface complete.
24Anaerobic Pond,Facultative Pond and Maturation Pond including Long Wall and Short Wall
25Estimate of Coarse Screen Chamber With Grit Chamber Before WSP
26Excavation 0.00 - 1.50 M deep in Ordiary Soil
27For Base, Extra Trangular Part and Extra Rectangular Part
28Cement concrete with 20 mm gauge approved stone ballast, coarse snad andcement in proportion of 1:4:8
29Base and For Slop
30R.C.C. With cement , Coarse Sand and 40 mm Stone Ballast 1:1.5:3 in RaftFoundations & Footing
31RCC Base,Side Wall,Trangular Wall,Overflow Wall and Outlet Wall
32Material : Extra for using 20 mm size stone Aggregate instead of 40 mm Size Stone Aggregate
33Qty Same As RCC Stone Ballast 20 mm Gauge and Stone Ballast 40 mm Gauge
34Mild Steel or Iron in Plain Work
35Steel reinforcement
36@1.5% Of RCC Qty
37Providing and fixing stainless steel ( Grade 304) railing made of Hollow tubes, channels, plates etc., including welding, grinding, buffing, polishing and making curvature (wherever required) and fitting the same with necessary stainless steel nuts and bolts complete, i/c fixing the railing with necessary accessories & stainless steel dash fasteners , stainless steel bolts etc., of required size, on the top of the floor or the side of waist slab with suitable arrangement as per approval of Engineer-in charge, (for payment purpose only weight of stainless steel members shall be considered excluding fixing accessories such as nuts, bolts,fasteners etc.)
3810 mm Sq Bar and Angle 35 x35 x6
39ESTIMATE OF WASTE STABILIZATION POND -1000 KLD
40Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including getting out and disposal of excavated earth lead upto 50 m and for all lift, as directed by Engineer-in-charge. All kinds of soil
41Anaerobic Pond,Facultative Pond and Maturation Pond
42Banking With Excavated Earth
43Total Earthwork Qty
44Laying, Jointing 300mm Dia. RCC NP2 Hume Pipe 0.0-1.5 M
45Total Length 60 m
46Random rubble masonry with hard stone in foundation and plinth including levelling up with cement concrete 1:6:12 (1 cement : 6 coarse sand : 12 graded stone aggregate 20 mm nominal size) upto plinth level with : Cement mortar 1:6 (1 cement : 6 coarsesand)
47Anaerobic Pond,Facultative Pond and Maturation Pond including Top Perifry, Bottom Perifry and on Slop
48Dry stone pitching 22.5 cm thick including supply of stones and preparing surface complete.
49Anaerobic Pond,Facultative Pond and Maturation Pond including Long Wall and Short Wall
50Estimate of Leach Pit With Silt Chamber [10 KLD] 11 Nos
51Excavation in Ordinary Soil Excavation 0.00 - 1.50 M deep in OrdiarySoil Silt Chamber and Leah - Pit
52Excavation 1.50 - 3.00 M
53Leach Pit
54Excavation 3.0 - 4.5 M
55Leach Pit
56Cement concrete with 20 mm gauge approved stone ballast, coarse snad andcement in proportion of 1:4:8
57Silt Chamber PCC Base and Leach Pit Base
58R.C.C. With cement , Coarse Sand and40 mm Stone Ballast 1:1.5:3 in Raft Foundations & Footing
59Silt Chamber RCC Cover and Leach pit RCC Slab (including Removable cover)
60Mild Steel or Iron in Plain Work
61Steel reinforcement
62@1.5% Of RCC Qty
631St Class Brick- work in 1:4 Cement & Local Sand Mortar in Foundation & Plinth.
64Silt Chamber and Leach - Pit
6512 mm Thick Plaster With Cement & Local Sand Mortar (1:4)
66Silt Chamner and Leach Pit
67Excavation For Pipe Line 0-1.5 M Deep in Ordinary Soil (Loam, Clay, Sand)
68110 mm Dia and 75/80 mm Dia
69Carting from Store ,Laying, Jointing,Fixing & testing 100 mm Dia P.V.C. Pipes & Specials
70100/110 mm Dia
71Carting from Store ,Laying, Jointing, Fixing & testing 80 mm Dia P.V.C. Pipes& Specials
7275/80 mm Dia
73Honey-comb brick work 10 / 11.4 cm thick with common burnt clay bricks of class designation 7.5 in super structure above plinth level upto floor V level with cement mortar 1:4 (1 cement : 4 coarse sand).
74Leach pit
75U- PVC Pipes (Working Pressure 4Kg/cm2 ) Single Socketed pipe 110 mm dia
7675 mm Dia
77110 mm Dia
78Drain (Cross Section 0.60 x 0.6 m) Length - 2170 M
79Excavation in Ordinary Soil
80Excavation 0.00 - 1.50 M deep in OrdiarySoil For Drain
81Cement concrete with 20 mm gaugeapproved stone ballast, coarse sand and cement in proportion of 1:4:8
8225mm thick 1:2:4 P.C.C. floor with cement, coarse sand and 20mm gauge stone ballast with base concrete (75mm thick) 1:4:8 cement, local sand & brick ballast 40mmgauge.
83CC Bedding
841st class brick-work in 1:4 cement and local sand mortar in foundation & plinth
85Side Wall
8612mm thick plaster with cement mortar in proportion (1:4) cement & local sand overbrick-work
87Inner Side and Top
88R.C.C. work with cement, coarse sand and20 mm gauge approved stone ballast in proportion of 1:2:4 in slabs
89Drain Cover
90Mild steel or iron work in plain work
91Steel Reinforcement @1% Of RCC Qty
92Planted Drying Bed
93Excavation in Ordinary Soil
94Excavation 0.00 - 1.50 M deep inOrdiary Soil Excavation of the PDB,Screen Chamber and Excavation of the Reciver
95Excavation 1.50 - 3.00 M
96Excavation of the PDB and Excavation of the Reciver
97Cement concrete with 20 mm gauge approved stone ballast, coarse snad and cement in proportion of 1:4:8
98Planted Drying Bed,Screen Chamber and Reciver
99R.C.C. With cement , Coarse Sand and40 mm Stone Ballast 1:1.5:3 in Raft Foundations & Footing
100For PDB,For Screening Chamber and For Reciver
101Mild Steel or Iron in Plain Work
102Steel Reinforcement
1031% of Total RCC
1041St Class Brick- work in 1:4 Cement & Local Sand Mortar in Foundation & Plinth.
105Brick work (PDB), Brick work (Screen Chamber) and Brick work (Reciver)
10612 mm Thick Plaster With Cement & Local Sand Mortar (1:4)
107Plastering (PDB), Plastering (Screen Chamber) and Plastering (Reciver)
10815 mm cement plaster1:3 (1 Cement :3 Coarse sand) finished with a floating coat of neat cement.
109Plastering (PDB), Plastering (Screen Chamber) and Plastering (Reciver)
110Supplying, filling, spreading & leveling stone boulders of size range 5 cm to 20 cm, in recharge pit, in the required thickness, for all leads & lifts, all complete as per direction of Engineer-in-charge.
111Supplying, filling, spreading & leveling gravels of size range 5 mm to 10 mm, in the recharge pit, over the existing layer of boulders, in required thickness, for all leads & lifts, all complete as per direction of Engineer-in-charge.
112Supplying, filling, spreading & leveling coarse sand of size range 1.5 mm to 2 mm in recharge pit, in required thickness over gravel layer, for all leads & lifts, all complete as per direction of Engineer - in charge.
113Excavation For Pipe Line 0-1.5 M Deep in Ordinary Soil (Loam, Clay, Sand)
114110 mm diameter
115Carting from Store ,Laying, Jointing, Fixing & testing 100 mm Dia P.V.C. Pipes & Specials
116100/110 mm Dia
117U- PVC Pipes (Working Pressure 4Kg/cm2 ) Single Socketed pipe 110 mm dia
118110 mm Dia
119Providing and fixing on wall face unplasticised - PVC moulded fittings/ accessories for unplasticised PVC pipes conforming to IS : 13592 Type A, including jointing with seal ring conforming to IS : 5382, leaving 10 mm gap for thermal expansion.
120Single tee without door 110x110x110mm
121Bend 87.5° 110 mm diameter
122Plantation of Trees, Shrubs, and Hedge at site i/c watering and removal of unserveiceable material’s as per direction of officer in charge (excluding cast of plant & water)
123Trees Plant
124KOTA STONE FLOORING: Kotastone slab flooring over 20 mm (average) thick base laid over and jointed with grey cement slurry mixed with pigment to match the shade of the slab, including rubbing and polishing complete with base of cement mortar 1 : 4 (1 cement : 4 coarse sand) :
12525 mm thick
126Providing and fixing stainless steel ( Grade 304) railing made of Hollow tubes, channels, plates etc., including welding, grinding, buffing, polishing and making curvature (wherever required) and fitting the same with necessary stainless steel nuts and bolts complete, i/c fixing the railing with necessary accessories & stainless steel dash fasteners , stainless steel bolts etc., of required size, on the top of the floor or the side of waist slab with suitable arrangement as per approval of Engineer-in charge, (for payment purpose only weight of stainless steel members shall be considered excluding fixing accessories such as nuts, bolts,fasteners etc.).
127Screen bar 5.76 Sqm @ 10 kg / sqm
128Collection Tank
129Excavation in Ordinary Soil
130Excavation 0.00 - 1.50 M deep in OrdiarySoil Excavation of the Collection Tank
131Excavation 1.50 - 3.00 M
132Excavation of the Collection Tank
133Excavation 3.0 - 4.5 M
134Excavation of the Collection Tank
135Cement concrete with 20 mm gauge approved stone ballast, coarse snad andcement in proportion of 1:4:8
136R.C.C. With cement , Coarse Sand and 20 mm Stone Ballast 1:1.5:3 in For Slabs
137For Collection Tank, Base Slab,Roof Slab and Manhole Cover
138Mild Steel or Iron in Plain Work
1391% of Total RCC
140Excavation For Pipe Line 0-1.5 M Deep in Ordinary Soil (Loam, Clay, Sand)
141110 mm diameter
142Carting from Store ,Laying, Jointing, Fixing & testing 100 mm Dia P.V.C. Pipes & Specials
143100/110 mm Dia
144U- PVC Pipes (Working Pressure 4 Kg/cm2 ) Single Socketed pipe 110 mm dia
145110 mm Dia
146Providing and fixing on wall face unplasticised - PVC moulded fittings/ accessories for unplasticised Rigid PVC rain water pipes conforming to IS: 13592 Type A, including jointing with seal ring conforming to IS : 5382, leaving 10 mm gap for thermal expansion.
147Single tee without door 110x110x110 mm
148Bend 87.5° 110 mm diameter
149Estimate of Anaerobic Baffaled Reactor
150Excavation in Ordinary Soil
151Excavation 0.00 - 1.50 M deep in OrdiarySoil Excavation of the ABR and Reciver
152Excavation 1.50 - 3.00 M
153Excavation of the ABR
154Cement concrete with 20 mm gauge approved stone ballast, coarse snad and cement in proportion of 1:4:8
155Planted Drying Bed and Reciver
1561St Class Brick- work in 1:4 Cement & Local Sand Mortar in Foundation & Plinth.
157Brick work (ABR) and Brick work (Reciver)
15812 mm Thick Plaster With Cement & Local Sand Mortar (1:4)
159Plastering (ABR) and Plastering (Reciver) inner and outer Wall
16015 mm cement plaster1:3 (1 Cement :3Coarse sand) finished with a floating coat of neat cement.
161Plastering (ABR) and Plastering (Reciver) inner and outer Wall
162R.C.C. With cement , Coarse Sand and 20 mm Stone Ballast 1:1.5:3 in For Slabs
163RCC in (ABR) and RCC in (Reciver)
164Mild Steel or Iron in Plain Work
165Total Reinforcement for perforated slab (1.5%of RCC)
166Supplying and stacking at site: 53 mm to 22.4mm size stone aggregate
167Providing and fixing in position pre-castR.C.C. manhole cover and frame of required shape and approved quality EHD - 35
168Circular Shape 560 mm internal dia
169Planted Gravel Filter
170Excavation in Ordinary Soil
171Excavation in Ordinary Soil Excavation 0.00 - 1.50 M deep in Ordiary Soil
172Excavation of the PGF Total
173Cement concrete with 20 mm gauge approved stone ballast, coarse snad and cement in proportion of 1:4:8
174PCC Bed
175R.C.C. With cement , Coarse Sand and20 mm Stone Ballast 1:1.5:3 in For Slabs
176For RCC Base, RCC Cover (R1) and RCC Cover (R2)
177Mild Steel or Iron in Plain Work
1781% of Total RCC
1791St Class Brick- work in 1:4 Cement & Local Sand Mortar in Foundation &Plinth.
180Brick work (PGF), Brick work (R1) and Brick work (R 2)
18112 mm Thick Plaster With Cement & Local Sand Mortar (1:4)
182Plastering (PGF),Plastering (R1) and Plastering (R 2)
18315 mm cement plaster1:3 (1 Cement :3 Coarse sand) finished with a floatingcoat of neat cement.
184Plastering (PGF),Plastering (R1) and Plastering (R 2)
185Excavation For Pipe Line 0-1.5 M Deep in Ordinary Soil (Loam, Clay, Sand)
186110 mm diameter
187Carting from Store ,Laying, Jointing, Fixing & testing 100 mm Dia P.V.C. Pipes & Specials
188100/110 mm Dia
189U- PVC Pipes (Working Pressure 4 Kg/cm2 ) Single Socketed pipe 110 mm dia
190110 mm Dia
191Providing and fixing on wall face unplasticised - PVC moulded fittings/ accessories for unplasticised Rigid PVC rain water pipes conforming to IS : 13592 Type A, including jointing with seal ring conforming to IS : 5382, leaving 10 mm gap for thermal expansion.
192Single tee without door 110x110x110mm
193Bend 87.5° 110 mm diameter
194Supplying and stacking at site: 53 mm to 22.4 mm size stone aggregate
195Average Width (0.5+0.7)/2 = 0.60m and Average Width (0.3+0.5)/2 = 0.40m
196Supplying, filling, spreading & leveling stone boulders of size range 5 cm to 20 cm, in recharge pit, in the required thickness, for all leads & lifts, all complete as per direction of Engineer-in-charge.
197Supplying, filling, spreading & leveling gravels of size range 5 mm to 10 mm, in the recharge pit, over the existing layer of boulders, in required thickness, for all leads & lifts, all complete as per direction of Engineer-in-charge.
198Supplying, filling, spreading & leveling coarse sand of size range 1.5 mm to 2 mm in recharge pit, in required thickness over gravel layer, for all leads & lifts, all complete as per direction of Engineer -in charge.
199POLISHING POND
200Earth work in excavation by mechanical means (Hydraulic excavator)/ manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including getting out and disposal of excavated earth lead upto 50 m and for all lift, as directed by Engineer-incharge.
201All kinds of soil
202Extra for levelling & neatly dressing of disposal soil completely as directed by Engineer-in-charge
203Laying, Jointing 300mm Dia. RCC NP2 Hume Pipe 0.0-1.5 M
204Brick on edge flooring with bricks of class designation 7.5 on a bed of12 mm cement mortar, including filling the joints with same mortar, with common burnt clay non modular bricks:
2051:6 (1cement : 6 coarse sand)
206Sludge Storage House
207Earth work in surface excavation not exceeding30 cm in depth but exceeding1.5 m in width as well as 10 sqm on plan including getting out and disposal of excavated earth upto 50 m and lift upto 1.5 m, as directed by Engineer-in-Charge:
208Dry brick on edge flooring in required pattern with bricks of class designation 7.5 on a bed of 12 mm mud mortar, including filling joints with Jamuna sand, with common burnt clay non modular bricks.
209Cement concrete with 20 mm gauge approved stone ballast, coarse snad and cement in proportion of 1:4:8
210Honey-comb brick work 10 / 11.4 cm thick with common burnt clay bricks of class designation 7.5 in super structure above plinth level upto floor V level with cement mortar 1:4 (1 cement : 4 coarse sand).
211Long Wall and ShortWall
212Mild Steel or iron Work of Small size & Section
213Long Side, Short Side and 65 MM dia MS Pipe, Purlin and Principal Rafter
214Supply & Fix Galvanised Corrugated iron roofing 0.63 mm thick
215Roofing Sheet
216Providing and fixing Chlorinated Polyvinyl Chloride (CPVC) pipes, having thermal stability for hot & cold water supply including all CPVC plain & brass threaded fittings This includes jointing of pipes & fittings with one step CPVC solvent cement, trenching, refilling & testing of joints complete as per direction of Engineer in Charge. 25 mm nominal diaPipes
217Providing and fixing expanded metal 20x60 mm strands 3.25 mm wide and 1.6mm thick for windows etc. including 62 x19 mm beading of II nd class teak wood and priming coat with approved steel primer all complete.
218Gaurd Room
219Excavation in Ordinary Soil
220Excavation 0.00 - 1.50 M deep in OrdiarySoil 230 mm wall (L= (2.33+3.23)X2=11.12 M
221Filling, dressing and raamming earth or sand or bajri or ballast or kankar or single etc.
222Filling available excavated earth / Total qtyof Excavated earth
223Sand filling in plinth Guard Room
224Cement concrete with 20 mm gauge approved stone ballast, coarse snad andcement in proportion of 1:4:8
225230 mm wall foundation base
22625 mm thick damp proof course with cement concrete consisting of cement, coarse sand and 12 mm graded approvedstone grit 1:1.5:3
227R.C.C. work with cement, coarse sand and20 mm gauge approved stone ballast in proportion of 1:1.5:3 in lintels of doors and windows
228Lintel Band for door and Window
229R.C.C. With cement , Coarse Sand and 20 mm Stone Ballast 1:1.5:3 in For Slabs
230Mild Steel or Iron in Plain Work
231@1% Of Qty of Rcc
2321St Class Brick- work in 1:4 Cement & Local Sand Mortar in Foundation & Plinth.
233In 230 mm wall
2341St Class Brick- work in 1:4 Cement & Local Sand Mortar in Superstructure One Brick Thick
235In 230 mm wall
23612 mm Thick Plaster With Cement & Local Sand Mortar (1:4)
237Internal plaster: Cement Plaster - 1: 6
23815mm thick plaster on rough side of single or half brick wall of Mix :
2391:6 (1 Cement :6 coarse Sand)
240External plaster: Cement Plaster - 1: 6
241Out Side
242Extra on all item of plaster if done on ceiling.
243Pump Room
244Supply & fix 35 mm thick Teak wood fully panelled in doors shutters
245Door -D
246Painting or varnishing on new iron work in small areas or new wood work with one coat priming & one coat paint or varnish.
247DOOR and WINDOW
248White washing one coat
249Same as Outer side plaster and Ceilling plaster
250one priming & one oil distemper coat on new work.
251Same as Inner plaster
25225mm thick 1:2:4 P.C.C. floor with cement, coarse sand and 20mm gauge stone ballast with base concrete (75mm thick) 1:4:8 cement, local sand & brick ballast 40mm gauge.
253Flooring
254for every coat after first coat.
255Door- D1 and Window
256Making plinth protection 50mm thick of cement concrete 1:3:6 (1 cement : 3 coarse sand (zone-III) derived from natural sources : 6 graded stone aggregate 20 mm nominal size derived from natural sources) over 75mm thick bed of dry brick ballast 40 mm nominal size, well rammed and consolidated and grouted with fine sand, including necessary excavation, levelling & dressing & finishing the top smooth.
257Providing and fixing factory made ISi marked steel glazed doors, windows and ventilators, side /top /centre hung, with beading and all members such as F7D,F4B, K11 Band K12 B etc.complete of standard rolled steel sections, joints mitred and flash butt welded and sash bars tenoned and riveted, including providing and fixing of hinges, pivots, priming coat of approved steel primer, but excluding the cost of other fittings,glass panes complete all as per approved design, (sectional weight of only steel members shall be measured for payment). Fixing with 15x3 mm lugs 10 cm long embedded in cement concrete block 15x10x10 cm of C.C. 1:3:6 (1 Cement: 3 coarse sand : 6 graded stone aggregate 20 mm nominal size)
2581.44 sqm @ 20kg/m^3
259Providing and fixing T-iron frames for doors, windows and ventilators of mild steel Tee-sections, joints mitred and welded, including fixing of necessary butt hinges and screws and applying a priming coat of approved steel primer.
260Fixing with 15x3 mm lugs 10 cm long embedded in cement concrete block 15x10x10 cm of C.C. 1:3:6 (1 Cement: 3 coarse sand : 6 graded stone aggregate 20 mm nominal size). @ 3.00 kg/m
261Providing & fixing glass panes with putty and glazing clips in steel doors,windows, clerestory windows, all complete with :
2624.0 mm thick glass panes
263Unit Estimate of Boundary Wall with Gate
264Excavation in Ordinary Soil
265Excavation 0.00 - 1.50 M deep in Ordiary Soil Boundary Wall and Footing Gate Column
266Filling, dressing and raamming earth or sand or bajri or ballast or kankar or single etc.
267@ 30 % of total Earth work
268Cement concrete with 20 mm gauge approved stone ballast, coarse snad and cement in proportion of 1:4:8
269Boundary Wall and Footing Gate Column
270Cement concrete with 20 mm gauge approved stone ballast, coarse sand andcement in the proportion of 4:2:1
271Copping PCC on Top and Copping Boundary Wall(Side /Back ) on Top
272R.C.C. With cement , Coarse Sand and40 mm Stone Ballast 1:1.5:3 in Raft Foundations & Footing
273Foundation Base,Pedestal and Column UP to GL
274R.C.C. With cement , Coarse Sand and20 mm Stone Ballast 1:1.5:3 in RCC Column
275Column Gl to Top
276Mild Steel or Iron in Plain Work Steel Reinforced
2771St Class Brick- work in 1:4 Cement & Local Sand Mortar in Foundation & Plinth.
278Footing Brick work in col.In Ist, 2nd and 3rd Footing
2791St Class Brick- work in 1:4 Cement & Local Sand Mortar in Superstructure One Brick Thick
280Boundary Wall (Front)
281Above Footing Brick work in col.
2821St Class Brick- work in 1:4 Cement & Local Sand Mortar in Superstructure Half Brick Thick
283Above Footing Brick work in Wall
28425 mm thick damp proof course with cement concrete consisting of cement, coarse sand and 12 mm graded approvedstone grit 1:1.5:3
285For Brick Piller and Brick Wall
28612 mm Thick Plaster With Cement & Local Sand Mortar (1:4)
287For Brick Piller and Brick Wall
288white washing one coat
289Same as plaster area and Copping
290Colour washing two coat using coloring materials of buff blue, brown shade.
291Same as plaster area and Copping
292Mild steel or iron work in heavy sizes
293Fixing barbed wire fencing to posts Barbed Wire
294Painting or varnishing on new iron work in small areas or new wood work with one coat priming & one coat paint or varnish.
295Estimate of Pump for Polishing Pond
296Supply, installation and commissioning of 1 HP Monoblock Pump of Kirloskar, CRI or equivalent make for pumping of water.Including civil works, fabrication work for mounting the pump, necessary plumbing / wiring as per instructions of engineer in charge.
297Chlorine Tank (300 KLD)
298Excavation in Ordinary Soil Excavation 0.00 - 1.50 M deep in OrdiarySoil
299Chlorine Tank and For Column
300Cement concrete with 20 mm gaugeapproved stone ballast, coarse snad and cement in proportion of 1:4:8
301Planted Drying Bed
302Tank PCC Bed,PCC Bed and For Column
303R.C.C. With cement , Coarse Sand and 40 mm Stone Ballast 1:1.5:3 in RaftFoundations & Footing
304Tank PCC Bed,PCC Bed and For Column
305R.C.C. With cement , Coarse Sand and 20 mm Stone Ballast 1:1.5:3 in RCC Column
306RCC Wall,Horizontal Long Wall,Horizontal Short Wall,Vertical Long Wall,Vertical Short Wall,Bafal Wall and Column
307R.C.C. With cement , Coarse Sand and 20 mm Stone Ballast 1:1.5:3 in For Slabs
308RCC Slab For PVC Tank
309Mild steel or iron work in plain work such asR.C.C. or R.B. work (when not included in over all rates), wrought to required shape, as necessary including bending for proper completion of work including supply of steel and wastage.
3101.5% of Total RCC
311Carting from store, laying, Jointing, fixing & testing 100 mm dia. (I.D.) P.V.C pipes & specials.
312100/110 mm Dia
313U- PVC Pipes (Working Pressure 4 Kg/cm2 ) Single Socketed pipe
314110 mm diameter
315Providing and placing on terrace (at all floor levels) polyethylene water storage tank, IS : 12701 marked, with cover and suitable locking arrangement and making necessary holes for inlet, outlet and overflow pipes but without fittings and the base support for tank.
316Chlorine Tank
317Providing and fixing PTMT extension nipplefor water tank pipe, fittings of approved quality and colour.
31825mm nominal bore, weighing not less than62 gms
319Providing and fixing gun metal gate valve with C.I. wheel of approved quality (screwed end) :
32025 mm nominal bore
321Providing and fixing Chlorinated Polyvinyl Chloride (CPVC) pipes, having thermal stability for hot & cold water supply including all CPVC plain & brass threaded fittings This includes jointing of pipes & fittings with one step CPVC solvent cement, trenching, refilling & testing of joints complete as per direction of Engineer in Charge.
32225 mm nominal dia Pipes
323Chlorine Tank (1000 KLD)
324Excavation in Ordinary Soil
325Excavation 0.00 - 1.50 M deep in OrdiarySoil Chlorine Tank and For Column
326Cement concrete with 20 mm gaugeapproved stone ballast, coarse snad and cement in proportion of 1:4:8
327Planted Drying Bed,Tank PCC Bed,PCC Bed and For Column
328R.C.C. With cement , Coarse Sand and 40 mm Stone Ballast 1:1.5:3 in RaftFoundations & Footing
329Tank PCC Bed,PCC Bed and For Column
330R.C.C. With cement , Coarse Sand and 20 mm Stone Ballast 1:1.5:3 in RCC Column
331RCC Wall,Horizontal Long Wall,Horizontal Short Wall,Vertical Long Wall,Vertical Short Wall,Bafal Wall and Column
332R.C.C. With cement , Coarse Sand and 20 mm Stone Ballast 1:1.5:3 in For Slabs
333RCC Slab For PVC Tank
334Mild steel or iron work in plain work such asR.C.C. or R.B. work (when not included in over all rates), wrought to required shape, as necessary including bending for proper completion of work including supply of steel and wastage.
3351.5% of Total RCC
336Carting from store, laying, Jointing, fixing & testing 100 mm dia. (I.D.) P.V.C pipes & specials.
337100/110 mm Dia
338U- PVC Pipes (Working Pressure 4 Kg/cm2 ) Single Socketed pipe
339110 mm diameter
340Providing and placing on terrace (at all floor levels) polyethylene water storage tank, IS : 12701 marked, with cover and suitable locking arrangement and making necessary holes for inlet, outlet and overflow pipes but without fittings and the base support for tank.
341Chlorine Tank
342Providing and fixing PTMT extension nipplefor water tank pipe, fittings of approved quality and colour.
34325mm nominal bore, weighing not less than62 gms
344Providing and fixing gun metal gate valve with C.I. wheel of approved quality (screwed end) :
34525 mm nominal bore
346Providing and fixing Chlorinated Polyvinyl Chloride (CPVC) pipes, having thermal stability for hot & cold water supply including all CPVC plain & brass threaded fittings This includes jointing of pipes & fittings with one step CPVC solvent cement, trenching, refilling & testing of joints complete as per direction of Engineer in Charge.
34725 mm nominal dia Pipes Please Enable Macros to View BoQ information

AI Tender Summary

OUR REF NO 58147531
AUTHORITY Government Departments
TENDER VALUE 2.43 Crore
LAST DATE 05-11-2026
Authority
Authority Name Uttar Pradesh Jal Nigam
Work Description Tender for Used Water Management (Wps) For Nagar Palika Parishad Chirgaon Disst Jhansi Under Sbm (U) 2.0 Programme
Basic Detail
Tender No NIT no 1448 /F-03 /221 dated 14.10.2026
Bidding Type Tender
Location
City Jhansi
State Uttar Pradesh
Key Dates
Publish Date 22 Oct 2026
Submission Date 05 Nov 2026
Open Date 05 Nov 2026
Finance
Tender Value 2.43 Crore
Tender Fee 11800
EMD 4.87 Lakhs
Exemption Available
Document List
b7ccf0e7-e468-438d-9c3d-027351266195.html
BOQ_2267939.xls
ChirgaonTD4thSBM.pdf
Tendernotice_1.pdf

Unlock Full AI Tender Summary

Get instant access to the complete AI-generated analysis — scope, eligibility, timeline & more.

Instant Access Secure Free
Your details are secure and used only for document delivery.

Tender Timeline

Oct 22, 2026
11:30 IST

Tender Published

Tender notice published.

Completed
Nov 05, 2026
17:00 IST

Bid Submission Deadline

Online submission via eProcurement portal.

Upcoming · 12 days
Nov 05, 2026

Bid Opening Date

Technical bids will be opened and evaluated.

Upcoming · 12 days

Tender Documents

Download All (ZIP) ↓
html

b7ccf0e7-e468-438d-9c3d-027351266195.html

xls

BOQ_2267939.xls

pdf

ChirgaonTD4thSBM.pdf

pdf

Tendernotice_1.pdf

Disclaimer

We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender