Bids Are invited for Facility Management Services - Lumpsum Based - M And R Of Parapet Sunshade Balcony And Other Misc Civil Works At Typeii Residences For 01 Nos Block Res Ii To 31 To Ii And 36 At Pn Road Staff Hydel Colony Lucknow; M And R Of Parap
Tender Overview
Project Description
Bids Are invited for Facility Management Services - Lumpsum Based - M And R Of Parapet Sunshade Balcony And Other Misc Civil Works At Typeii Residences For 01 Nos Block Res Ii To 31 To Ii And 36 At Pn Road Staff Hydel Colony Lucknow; M And R Of Parapet Sunshade .. - Demolishing Brick Work Manually/ By Mechanical Means Including Stacking Of Serviceable Material And Disposal Of Unserviceable Material Within 50 Metres Lead As Per Direction Of Engineer-In-Charge. , Demolishing R.B. Work Manually/ By Mechanical Means Including Stacking Of Steel Bars And Disposal Of Unserviceable Material Within 50 Metres Lead As Per Direction Of Engineer-In- Charge. , Providing And Fixing Double Scaffolding System (Cup Lock Type) On The Exterior Side, Up To Seven Story Height Made With 40 Mm Dia M.S. Tube 1.5 M Centre To Centre, Horizontal & Vertical Tubes Joining With Cup & Lock System With M.S. Tubes, M.S. Tube Challies, M.S. Cl S And M.S. Staircase System In The Scaffolding For Working Platform Etc. And Maintaining It In A Serviceable Condition For The Required Duration As Approved And Removing It There After .The Scaffolding System Shall Be Stiffened With Bracings, Runners, Connection With The Building Etc Wherever Required For Inspection Of Work At Required Locations With Essential Safety Features For The Workmen Etc. Complete As Per Directions And Approval Of Engineer-In-Charge .The Elevational Area Of The Scaffolding Shall Be Measured For Payment Purpose .The Payment Will Be Made Once Irrespective Of Duration Of Scaffolding. , Felling Trees Of The Girth (Measured At A Height Of 1 M Above Ground Level), Including Cutting Of Trunks And Branches, Removing The Roots And Stacking Of Serviceable Material And Disposal Of Unserviceable Material. , Brick Work With Common Burnt Clay F.P.S. (Non Modular) Bricks Of Class Designation 7.5 In Superstructure Above Plinth Level Up To Floor V Level In All Shapes And Sizes In : , Brick Work In Foundation & Plinth With Old Dismantled Bricks (Supplied By Department Free Of Cost) And Coarse Sand Mortar In 1:6 Including Supply Of All Other Materials, Labour, Removing Mortar & Cleaning Of Old & Used Bricks,T&P Etc Complete. , Supply And Fixing 6Mm Thick Polycarbonate Multiwall Sheet ,Fixing In Position With J Or U Bolts 10 Mm. Dia With G.I. Limpet & Bitumen Washers Including Supply Of All Materials, Labour,Wastage. And T&P Etc. Required For Proper Completion Of The Work. , Removing Mortar From Bricks And Cleaning Bricks Including Stacking Within A Lead Of 50 M (Stacks Of Cleaned Bricks Shall Be Measured): , 12 Mm Cement Plaster Of Mix : , Providing And Fixing On Wall Face Unplasticised Rigid Pvc Rain Water Pipes Conforming To Is : 13592 Type A, Including Jointing With Seal Ring Conforming To Is : 5382, Leaving 10 Mm Gap For Thermal Expansion, (I) Single Socketed Pipes. , Attending To Petty Maintenance Service Like Plumbing Service,Welder Service, Mansion Service And Carpenter Service Required As Below. (Job Attending By One No. Plumber/Welder/Mason /Carpenter With One No. Helper Per Hour Or Part Of An Hour.) , Providing And Fixing Chlorinated Polyvinyl Chloride (Cpvc) Pipes, Having Thermal Stability For Hot & Cold Water Supply, Including All Cpvc Plain & Brass Threaded Fittings, Including Fixing The Pipe With Cl S At 1.00 M Spacing. This Includes Jointing Of Pipes & Fittings With One Step Cpvc Solvent Cement And Testing Of Joints Complete As Per Direction Of Engineer In Charge. , Finishing Walls With Water Proofing Cement Paint Of Required Shade : , Removing Dry Or Oil Bound Distemper, Water Proofing Cement Paint And The Like By Scrapping, Sand Papering And Preparing The Surface Smooth Including Necessary Repairs To Scratches Etc. Complete. , Steel Reinforcement For R.C.C. Work Including Straightening, Cutting, Bending, Placing In Position And Binding All Complete Upto Plinth Level. , Providing And Laying In Position Specified Grade Of Reinforced Cement Concrete, Excluding The Cost Of Centering, Shuttering, Finishing And Reinforcement - All Work Up To Plinth Level : , Reinforced Cement Concrete Work In Beams, Suspended Floors, Roofs Having Slope Up To 15° Landings, Balconies, Shelves, Chajjas, Lintels, Bands, Plain Window Sills, Staircases And Spiral Stair Cases Above Plinth Level Up To Floor Five Level, Excluding The Cost Of Centering, Shuttering, Finishing And Reinforcement With 1:1.5:3 (1 Cement : 1.5 Coarse Sand(Zone-Iii) Derived From Natural Sources : 3 Graded Stone Aggregate 20 Mm Nominal Size Derived From Natural Sources). , Centering And Shuttering Including Strutting, Propping Etc. And Removal Of Form For , Earth Work In Surface Excavation Not Exceeding 30 Cm In Depth But Exceeding 1.5 M In Width As Well As 10 Sqm On Plan Including Getting Out And Disposal Of Excavated Earth Upto 50 M And Lift Upto 1.5 M, As Directed By Engineer-In- Charge: , Providing & Fixing Fly Proof Wire Gauze To Windows, Clerestory Windows & Doors With M.S. Flat 15X3 Mm And Nuts & Bolts Complete. , Providing And Fixing Fly Proof Galvanized M.S. Wire Gauge To Windows And Clerestory Windows Using Wire Gauge With Average Width Of Aperture 1.4 Mm In Both Directions With Wire Of Dia 0.63 Mm All Complete. , Hiring Charge Of Welding Equipment Complete In Well Working Condition Along With Trained Helper And Welder And Also Sufficient Lead Of Cable Not Less Than 15M Long Including Cost Of Approved Quality Electrodes Used And Work For A Day I.E 8.00 Hour Called One Job Excluding Cost Of M.S Angle ,Flat, Sheet ,Channel Etc.Which Shall Be Measured And Paid Seperately. (Nsi Approved) 2025 , Structural Steel Work Riveted, Bolted Or Welded In Built Up Sections, Trusses And Framed Work, Including Cutting, Hoisting, Fixing In Position And Applying A Priming Coat Of Approved Steel Primer All Complete. , Painting With Synthetic Enamel Paint Of Approved Brand And Manufacture Of Required Colour To Give An Even Shade :
BOQ
| Sl. No. | Item Title | Item Description |
| 1 | Demolishing brick work manually/ by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-charge. | Demolishing brick work manually/ by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-charge. |
| 2 | Demolishing R.B. work manually/ by mechanical means including stacking of steel bars and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in- charge. | Demolishing R.B. work manually/ by mechanical means including stacking of steel bars and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in- charge. |
| 3 | Providing and fixing double scaffolding system (cup lock type) on the exterior side, up to seven story height made with 40 mm dia M.S. tube 1.5 m centre to centre, horizontal & vertical tubes joining with cup & lock system with M.S. tubes, M.S. tube challies, M.S. clamps and M.S. staircase system in the scaffolding for working platform etc. and maintaining it in a serviceable condition for the required duration as approved and removing it there after .The scaffolding system shall be stiffened with bracings, runners, connection with the building etc wherever required for inspection of work at required locations with essential safety features for the workmen etc. complete as per directions and approval of Engineer-in-charge .The elevational area of the scaffolding shall be measured for payment purpose .The payment will be made once irrespective of duration of scaffolding. | Providing and fixing double scaffolding system (cup lock type) on the exterior side, up to seven story height made with 40 mm dia M.S. tube 1.5 m centre to centre, horizontal & vertical tubes joining with cup & lock system with M.S. tubes, M.S. tube challies, M.S. clamps and M.S. staircase system in the scaffolding for working platform etc. and maintaining it in a serviceable condition for the required duration as approved and removing it there after .The scaffolding system shall be stiffened with bracings, runners, connection with the building etc wherever required for inspection of work at required locations with essential safety features for the workmen etc. complete as per directions and approval of Engineer-in-charge .The elevational area of the scaffolding shall be measured for payment purpose .The payment will be made once irrespective of duration of scaffolding. |
| 4 | Felling trees of the girth (measured at a height of 1 m above ground level), including cutting of trunks and branches, removing the roots and stacking of serviceable material and disposal of unserviceable material. | Felling trees of the girth (measured at a height of 1 m above ground level), including cutting of trunks and branches, removing the roots and stacking of serviceable material and disposal of unserviceable material. |
| 5 | Brick work with common burnt clay F.P.S. (non modular) bricks of class designation 7.5 in superstructure above plinth level up to floor V level in all shapes and sizes in : | Brick work with common burnt clay F.P.S. (non modular) bricks of class designation 7.5 in superstructure above plinth level up to floor V level in all shapes and sizes in : |
| 6 | Brick work in foundation & plinth with old dismantled bricks (supplied by department free of cost) and coarse sand mortar in 1:6 including supply of all other materials, labour, removing mortar & cleaning of old & used bricks,T&P etc complete. | Brick work in foundation & plinth with old dismantled bricks (supplied by department free of cost) and coarse sand mortar in 1:6 including supply of all other materials, labour, removing mortar & cleaning of old & used bricks,T&P etc complete. |
| 7 | Supply and fixing 6mm thick polycarbonate multiwall sheet ,fixing in position with J or U bolts 10 mm. dia with G.I. Limpet & bitumen washers including supply of all materials, labour,wastage. and T&P etc. required for proper completion of the work. | Supply and fixing 6mm thick polycarbonate multiwall sheet ,fixing in position with J or U bolts 10 mm. dia with G.I. Limpet & bitumen washers including supply of all materials, labour,wastage. and T&P etc. required for proper completion of the work. |
| 8 | Removing mortar from bricks and cleaning bricks including stacking within a lead of 50 m (stacks of cleaned bricks shall be measured): | Removing mortar from bricks and cleaning bricks including stacking within a lead of 50 m (stacks of cleaned bricks shall be measured): |
| 9 | 12 mm cement plaster of mix : | 12 mm cement plaster of mix : |
| 10 | Providing and fixing on wall face unplasticised Rigid PVC rain water pipes conforming to IS : 13592 Type A, including jointing with seal ring conforming to IS : 5382, leaving 10 mm gap for thermal expansion, (i) Single socketed pipes. | Providing and fixing on wall face unplasticised Rigid PVC rain water pipes conforming to IS : 13592 Type A, including jointing with seal ring conforming to IS : 5382, leaving 10 mm gap for thermal expansion, (i) Single socketed pipes. |
| 11 | Attending to petty maintenance service like plumbing service,welder service, mansion service and carpenter service required as below. (Job attending by one no. Plumber/welder/mason /carpenter with one no. helper per hour or part of an hour.) | Attending to petty maintenance service like plumbing service,welder service, mansion service and carpenter service required as below. (Job attending by one no. Plumber/welder/mason /carpenter with one no. helper per hour or part of an hour.) |
| 12 | Providing and fixing Chlorinated Polyvinyl Chloride (CPVC) pipes, having thermal stability for hot & cold water supply, including all CPVC plain & brass threaded fittings, including fixing the pipe with clamps at 1.00 m spacing. This includes jointing of pipes & fittings with one step CPVC solvent cement and testing of joints complete as per direction of Engineer in Charge. | Providing and fixing Chlorinated Polyvinyl Chloride (CPVC) pipes, having thermal stability for hot & cold water supply, including all CPVC plain & brass threaded fittings, including fixing the pipe with clamps at 1.00 m spacing. This includes jointing of pipes & fittings with one step CPVC solvent cement and testing of joints complete as per direction of Engineer in Charge. |
| 13 | Finishing walls with water proofing cement paint of required shade : | Finishing walls with water proofing cement paint of required shade : |
| 14 | Removing dry or oil bound distemper, water proofing cement paint and the like by scrapping, sand papering and preparing the surface smooth including necessary repairs to scratches etc. complete. | Removing dry or oil bound distemper, water proofing cement paint and the like by scrapping, sand papering and preparing the surface smooth including necessary repairs to scratches etc. complete. |
| 15 | Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete upto plinth level. | Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete upto plinth level. |
| 16 | Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level : | Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level : |
| 17 | Reinforced cement concrete work in beams, suspended floors, roofs having slope up to 15° landings, balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiral stair cases above plinth level up to floor five level, excluding the cost of centering, shuttering, finishing and reinforcement with 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources). | Reinforced cement concrete work in beams, suspended floors, roofs having slope up to 15° landings, balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiral stair cases above plinth level up to floor five level, excluding the cost of centering, shuttering, finishing and reinforcement with 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources). |
| 18 | Centering and shuttering including strutting, propping etc. and removal of form for | Centering and shuttering including strutting, propping etc. and removal of form for |
| 19 | Earth work in surface excavation not exceeding 30 cm in depth but exceeding 1.5 m in width as well as 10 sqm on plan including getting out and disposal of excavated earth upto 50 m and lift upto 1.5 m, as directed by Engineer-in- Charge: | Earth work in surface excavation not exceeding 30 cm in depth but exceeding 1.5 m in width as well as 10 sqm on plan including getting out and disposal of excavated earth upto 50 m and lift upto 1.5 m, as directed by Engineer-in- Charge: |
| 20 | Providing & fixing fly proof wire gauze to windows, clerestory windows & doors with M.S. Flat 15x3 mm and nuts & bolts complete. | Providing & fixing fly proof wire gauze to windows, clerestory windows & doors with M.S. Flat 15x3 mm and nuts & bolts complete. |
| 21 | Providing and fixing fly proof galvanized M.S. wire gauge to windows and clerestory windows using wire gauge with average width of aperture 1.4 mm in both directions with wire of dia 0.63 mm all complete. | Providing and fixing fly proof galvanized M.S. wire gauge to windows and clerestory windows using wire gauge with average width of aperture 1.4 mm in both directions with wire of dia 0.63 mm all complete. |
| 22 | Hiring charge of welding equipment complete in well working condition along with trained helper and welder and also sufficient lead of cable not less than 15m long including cost of approved quality electrodes used and work for a day i.e 8.00 hour called one job excluding cost of M.S ANGLE ,flat, sheet ,channel etc.which shall be measured and paid seperately. (NSI APPROVED) 2025 | Hiring charge of welding equipment complete in well working condition along with trained helper and welder and also sufficient lead of cable not less than 15m long including cost of approved quality electrodes used and work for a day i.e 8.00 hour called one job excluding cost of M.S ANGLE ,flat, sheet ,channel etc.which shall be measured and paid seperately. (NSI APPROVED) 2025 |
| 23 | Structural steel work riveted, bolted or welded in built up sections, trusses and framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer all complete. | Structural steel work riveted, bolted or welded in built up sections, trusses and framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer all complete. |
| 24 | Painting with synthetic enamel paint of approved brand and manufacture of required colour to give an even shade : | Painting with synthetic enamel paint of approved brand and manufacture of required colour to give an even shade : |
AI Tender Summary
Tender Timeline
Tender Published
Tender notice published.
CompletedBid Submission Deadline
Online submission via eProcurement portal.
Upcoming · 10 daysBid Opening Date
Technical bids will be opened and evaluated.
Upcoming · 11 daysTender Documents