Tender For Reconstruction Of Sluice At Kalakattur Thangal Eri In Kalakattur Panchayat In Kancheepuram Union Kancheepuram District Estimate Amount : 1100000 Schem : Union General Fund 2026-27
Tender Value
11 Lakhs
Estimated cost
Bid Submission
30 Oct 2026
0 days left
EMD
11000
Bank guarantee accepted
Document Fee
Ref. Documents
Non-refundable
Tender Type
Online
Tender Overview
Organization
Tender ID
Competition Type
NCB
Bidding Type
Tender
Location / State
Kanchipuram → Tamil Nadu
EMD Exemption
Not Available
Quantity
Not Available
Website
Contact Person
Address
Project Description
Tender for Reconstruction Of Sluice At Kalakattur Thangal Eri In Kalakattur Panchayat In Kancheepuram Union Kancheepuram District Estimate Amount : 1100000 Schem : Union General Fund 2026-27
BOQ
| Sl. No. | Item Description |
| 1 | Name of Work: Reconstruction of Sluice at Kalakattur Thangal Eri in Kalakattur Panchayat in Kancheepuram Union Kancheepuram District ESTIMATE AMOUNT : 1100000 SCHEM : UNION GENERAL FUND 2026-27 |
| 2 | Dismantling&Removing the Existing Damaged Brick / Stone Masonry in cement mortar walls under 3m high including all labour charges etc complete |
| 3 | Dismantling&Removing the Existing Damaged CC 1:4:8 Mix Base Concrete including all labour charges etc complete |
| 4 | Earth work Excavation in all classes of soils such as hard stiff clay. Stiff block hard red earth, shales, murram, gravel, stoney earth expect hard rock requiring blassing and depositing on bank with all leads and lifts and all incidental charges such as storing shuddering and balling out water in necessary etc.completed for foundation as SS 20B. |
| 5 | Cement Concrete 1:4:8 mix using 40mm ISS HBG metal including cost & conveyance of all materials to site including cost of cement which will be supplied departmentally from section store at the cost three of which will be recovered for the contractors bills as per special condition including labour for mixing laying compacting curing concrete and all other incidental charges etc., complete |
| 6 | Cement Concrete 1:2:4 mix using 20mm ISS HBG metal including cost & conveyance of all materials to site including cost of cement which will be supplied departmentally from section store at the cost three of which will be recovered for the contractors bills as per special condition including labour for mixing laying compacting curing concrete and all other incidental charges etc., complete |
| 7 | Supplying and erecting of centering of RCC items including cost & conveyance of all materials to site and all labour charges etc., complete.(Above Sill level upto 0.90m) |
| 8 | Above 0.90m |
| 9 | supplying &fixing of cut stone slab including all labor charges etc complete |
| 10 | Supply and fabrication of steel as per IS432/1960 (Tested Quality) including fabrication charges for all RCC items schedule in the tender including cost of steel which will be supplied by the department section store and the cost will be recovered from the contractors bill at the rate of specified in the special conditions appended including handling charges for straightening, cleaning, cutting bending, tying grills with steel wire and hoisting and positioning before concerting joining of 20mm placing the reinforcement in correct position as specified including cost of electrodes and power for wilding typing wires, space bars cover blocks and all other incidental charges etc., completed. |
| 11 | RCC 1:1.5:3 mix using 20mm ISS HBG metal including cost & conveyance of all materials to work site and including cost of cement which will be supplied and departmental section store attend the cost will be record from contractors bill at the rate of specified in the special conditions appended and including all other incidental charges etc., completed but executing cost and conveyance of steel fabrication charges and centering complete for Roof slab. |
| 12 | Steps arrangements : Earth work excavation in all clauses of soil except hard rock which required blasting such as hard red earth, shalls, murrams including all cost and all labour charges etc.complete. As per SS 20B for foundation |
| 13 | CC 1:4:8 mix using 40mm ISS HBG Metal including all cost and conveyance etc.complete. |
| 14 | Supplying and centering shuttering including necessary supports for plane |
| 15 | Cement concrete 1:3:6 mix using 40mm ISS HBG metal including all cost and labour charges etc.complete . Complying with standard specification etc. |
| 16 | Cement Concrete 1:2:4 mix using 20mm ISS HBG metal including cost & conveyance of all materials to site including cost of cement which will be supplied departmentally from section store at the cost three of which will be recovered for the contractors bills as per special condition including labour for mixing laying compacting curing concrete and all other incidental charges etc., complete |
| 17 | GST Amount for providing Service to Government Contract Works for the above Construction Work. { GST Amount is the Total GST Amount for overall quoted amount Construction above this row in column \\"BB\\" for all works in this package}(Refer Clause 13.2 & 13.3 of Section 2 of Instruction to Bidders (ITB) of SBD) Please Enable Macros to View BoQ information |
AI Tender Summary
Tender Timeline
Oct 15, 2026
11:30 IST
Tender Published
Tender notice published.
CompletedOct 30, 2026
17:00 IST
Bid Submission Deadline
Online submission via eProcurement portal.
TodayOct 30, 2026
Bid Opening Date
Technical bids will be opened and evaluated.
TodayTender Documents