Environment and Forests Government Departments Closing in 13 days TDR #57987951

Tender For Maintenance Of Existing Road From Kovilmarathur To G.Marathur Road In Jamunamarathur Range Of Thiruvannamalai Forest Division During 2026-27

Issued by Government Departments · Tiruvannamalai, Tamil Nadu
Tender Value
2.07 Crore
Estimated cost
Bid Submission
11 Nov 2026
13 days left
EMD
2.08 Lakhs
Bank guarantee accepted
Document Fee
Ref. Documents
Non-refundable
Tender Type
Online

Tender Overview

Competition Type
NCB
Bidding Type
Tender
Location / State
Tiruvannamalai → Tamil Nadu
EMD Exemption
Available
Quantity
Not Available

Project Description

Tender for Maintenance Of Existing Road From Kovilmarathur To G.Marathur Road In Jamunamarathur Range Of Thiruvannamalai Forest Division During 2026-27

BOQ

Name of Work:- Maintenance of existing Road from Kovilmarathur to G.Marathur road in Jamunamarathur Range of Thiruvannamalai Forest Division during 2026-27
Sl. No. Item Description
1Maintenance of existing Road from Kovilmarathur to G.Marathur road in Jamunamarathur Range of Thiruvannamalai Forest Division during 2026-27
2Clearing the scrub jungles including cutting the scrubs and removing away from site etc complete
3Earth work excavation in all classes of soils except hard rock requiring blasting depositing on bank with initial lead of 10M and lift of 2M including all labour charges and incidental charges such as shoring, strutting, providing coffer dams, bailing out of water
4Collection and supply of Girrty gravel for side berms and labour charges for filling etc complete
5Construction of granular sub-base by providing close graded Material, mixing in a mechanical mix plant at OMC, carriage of mixed Material to work site, spreading in uniform layers with motor grader on prepared surface and compacting with vibratory Soil Compactor to achieve the desired density, complete
6Providing and laying spreading and compacting graded stone aggregate to Wet Mix Macadam(WMM) specification including premixing the material with water at OMC in machanical mix plant carriage of mixed material by tipper to site laying in uniform layers 250mm thick with pavers in SubBase/Base course on well prepared surface and compacting with vibratory roller to achieve the desired density including cost of material,labour charges, rentals for machinery, fuel and all other incidental charges etc., complete.
7Providing and laying PRIME COAT over the WMM surface using 7.00 Kg of Bituminous Emulsion SS I for 10 sqm. Including cost of bituminous emulsion which will be supplied by the department at section stores and its cost will be recovered as per special condition appended including labour charges for preparing the surface for laying prime coat and for applying required quantity of bituminous emulsion by mechanical sprayer including hire and fuel charges for all tools and plants employed etc., complete as per clause 503 of MOST specification.
8Providing and laying TACK COAT over the WMM surface (treated with primer) using 2.50 Kg of Bituminous Emulsion RS I for 10 sqm. Including cost of bituminous emulsion which will be supplied by the department at section stores and its cost will be recovered as per special condition appended including labour charges for preparing the surface for laying tack coat and for applying required quantity of bituminous emulsion by mechanical sprayer including hire and fuel charges for all tools and plants employed etc., complete as per clause 503 of MOST specification.
9Providing and laying Bituminious concrete to 25 mm thick using 0.13cum of 19.00-9.50mm. 0.17cum of 9.5-2.36 and below with 50.3kgs of VG30/VG40 heating the bitumen and aggregates to required temperature and mixing them in required temperature in central hot mix plant 20-30 ton capacity, carrying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 40mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonnes vibratory/phenumatic roller to the required density etc., including labour for attending to paver to site etc.including hire charges and fuel charges foe 20-30t CMP with bitumen boiler, tipper trucks,paver finisher/9m paver finisher,vibratory/phenumatic roller and all other tools and plants required, including fuel and all other incidental charges etc., complete as per specification using CMP as per clauses 507 of MORTH Part-5
10Construction of 1.50mts Culvert No.1
11Earth work excavation and depositing on bank with in initial lead of 10 m and initial lift of 2m in hard stiff clay, stiff black cotton soil, hard red earth,earth mixed with small sized boulders and hard gravelly soil as per SS 20B etc
12Cement concrete 1:4:8 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing,laying and curing etc complete for Levelling course
13Cement concrete 1:3:6 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing,laying and curing etc complete for Foundation
14Cement concrete 1:2:4 mix using 20mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing,laying and curing etc complete for Superstructure
15Cement concrete 1:2:4 mix using 20mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing,laying and curing etc complete for bed blocks
16Reinforced cement concrete 1:1.5:3 mix using 20mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying, and curing etc complete for Deckslab
17Supplying and erecting centering shuttering including necessary supports for plane surface in foundation and superstructure for Abutment /pier using mild steel sheets of size 90 x 60 cm and 10 guage stiffened, welded with mild steel angles of size 25mmx25mmx3mm for boarding laid over silver oak (country wood) scantlings of size 10cm x 6.5cm spaced of about 90cm centre to centre and supported by casurina props of 10cm to 13cm dia spaced at 75cm centre to centre complete complying with standard specifications and as directed by departmental officers etc.
18From Abutment to paraphet
19From Abutment to paraphet
20Deck slab and side
21Supplying and fabrication of steel including cost and conveyance of steel to site and all labour charges for straightening, cutting to length,bending to shape and tying in position and forming grills for all R.C.C works
22Providing and fixing 20mm Bitumen felt for expansion joint Between Dirtwall &Deck slab
23Providing weepholes in brick masonry/stone masonry, plain/reinforced concrete abutment, wing wall, return wall with 100 mm dia AC pipe extending through the full width of the structures with slope of 1(V):20(H) towards drawing face complete as per drawing
24Construction of 1.50mts Culvert No.2
25Earth work excavation and depositing on bank with in initial lead of 10 m and initial lift of 2m in hard stiff clay, stiff black cotton soil, hard red earth,earth mixed with small sized boulders and hard gravelly soil as per SS 20B etc
26Cement concrete 1:4:8 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing,laying and curing etc complete for Levelling course
27Cement concrete 1:3:6 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing,laying and curing etc complete for Foundation
28Cement concrete 1:2:4 mix using 20mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing,laying and curing etc complete for Superstructure
29Cement concrete 1:2:4 mix using 20mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing,laying and curing etc complete for bed blocks
30Reinforced cement concrete 1:1.5:3 mix using 20mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying, and curing etc complete for Deckslab
31Supplying and erecting centering shuttering including necessary supports for plane surface in foundation and superstructure for Abutment /pier using mild steel sheets of size 90 x 60 cm and 10 guage stiffened, welded with mild steel angles of size 25mmx25mmx3mm for boarding laid over silver oak (country wood) scantlings of size 10cm x 6.5cm spaced of about 90cm centre to centre and supported by casurina props of 10cm to 13cm dia spaced at 75cm centre to centre complete complying with standard specifications and as directed by departmental officers etc.
32From Abutment to paraphet
33From Abutment to paraphet
34Deck slab and side
35Supplying and fabrication of steel including cost and conveyance of steel to site and all labour charges for straightening, cutting to length,bending to shape and tying in position and forming grills for all R.C.C works
36Providing and fixing 20mm Bitumen felt for expansion joint Between Dirtwall &Deck slab
37Providing weepholes in brick masonry/stone masonry, plain/reinforced concrete abutment, wing wall, return wall with 100 mm dia AC pipe extending through the full width of the structures with slope of 1(V):20(H) towards drawing face complete as per drawing
38Construction of 1.50mts Culvert No.3
39Earth work excavation and depositing on bank with in initial lead of 10 m and initial lift of 2m in hard stiff clay, stiff black cotton soil, hard red earth,earth mixed with small sized boulders and hard gravelly soil as per SS 20B etc
40Cement concrete 1:4:8 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing,laying and curing etc complete for Levelling course
41Cement concrete 1:3:6 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing,laying and curing etc complete for Foundation
42Cement concrete 1:2:4 mix using 20mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing,laying and curing etc complete for Superstructure
43Cement concrete 1:2:4 mix using 20mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing,laying and curing etc complete for bed blocks
44Reinforced cement concrete 1:1.5:3 mix using 20mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying, and curing etc complete for Deckslab
45Supplying and erecting centering shuttering including necessary supports for plane surface in foundation and superstructure for Abutment /pier using mild steel sheets of size 90 x 60 cm and 10 guage stiffened, welded with mild steel angles of size 25mmx25mmx3mm for boarding laid over silver oak (country wood) scantlings of size 10cm x 6.5cm spaced of about 90cm centre to centre and supported by casurina props of 10cm to 13cm dia spaced at 75cm centre to centre complete complying with standard specifications and as directed by departmental officers etc.
46From Abutment to paraphet
47From Abutment to paraphet
48Deck slab and side
49Supplying and fabrication of steel including cost and conveyance of steel to site and all labour charges for straightening, cutting to length,bending to shape and tying in position and forming grills for all R.C.C works
50Providing and fixing 20mm Bitumen felt for expansion joint Between Dirtwall &Deck slab
51Providing weepholes in brick masonry/stone masonry, plain/reinforced concrete abutment, wing wall, return wall with 100 mm dia AC pipe extending through the full width of the structures with slope of 1(V):20(H) towards drawing face complete as per drawing
52Providing Cement Concrete pavement
53Earth work Excavation for Foundation in all soils and Sub Soil to full depth as may be directed except in hard rock requiring blasting but inclusive of shoring strutting and requiring the sides of foundation.
54Cement concrete 1:4:8 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete for 10 cum.
55Providing and laying spreading and compacting graded stone aggregate to Wet Mix Macadam(WMM) specification including premixing the material with water at OMC in machanical mix plant carriage of mixed material by tipper to site laying in uniform layers 2
56Cement concrete 1:2:4 mix using 20mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete for bed blocks for 10 cum
57Construction of un-reinforced, dowel jointed at expansion and construction joint only, plain cement concrete pavement, thickness as per design, over a prepared sub base, with 43 grade cement or any other type as per Clause 1501.2.2 M30 (Grade), coarse an
58Supplying and erecting centering for sides and soffits including supports for all reinforced cement concrete works like lintels, beams, etc., including strutting 3M high using Mild steel sheets of size 90cm × 60cm and B.G. 10, stiffened with Mild steel Angles of size 25mm × 25mm × 3mm laid over Silver oak (cw) joists of size 10cm × 6.5cm (Spaced about 91cm c/c) including removing the same after specified period without damaging RCC works in all floors etc., complete as directed by the departmental officers complying with relevant standard specifications
59Construction of Retaining wall
60Earth work excavation and depositing on bank with in initial lead of 10 m and initial lift of 2m in hard stiff clay, stiff black cotton soil, hard red earth, earth mixed with small sized boulders and hard gravelly soil as per SS 20B
61Cement concrete 1:4:8 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing,laying and curing etc complete for 10 cum.
62Cement concrete 1:3:6 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing,laying and curing etc complete for 10 cum. FOOTING
63Cement concrete 1:3:6 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete for 10 cum. FOR BODYWALL
64Supplying and erecting centering shuttering including necessary supports for plane surface in foundation and basement and in all floors for R C C column footing column plinth beam, beams, roof slabs, staircase steps, bed blocks, critical pier etc using mild steel sheets of size 90 x 60 cm and 10 guage stiffened, welded with mild steel angles of size 25mmx25mmx3mm for boarding laid over silver oak (country wood) scantlings of size 10cm x 6.5cm spaced of about 90cm centre to centre and supported by casurina props of 10cm to 13cm dia spaced at 75cm centre to centre complete complying with standard specifications and as directed by departmental officers including conveyance of all materials to site and proper centering etc complete.
65BELOW GL
66Above GL
67Providing and fixing seepage pipes of 100 mm dia. PVC pipes of required lengths for Retaining Wall including cost and conveyance of all materials to work site and labour charges for fixing, complete
68Construction of Minor Bridge
69Earth work Excavation for Foundation in all soils and Sub Soil to full depth as may be directed except in hard rock requiring blasting but inclusive of shoring strutting and requiring the sides of foundation.
70Supplying and Filling foundation and basement with filling sand in layers not more than 15cm . Thick well ramed, watered and compacted Complete complying with stanard specification.
71Cement concrete 1:4:8 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete for 10 cum.
72Cement concrete 1:3:6 mix using 20mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete for bed blocks for 10 cum
73Reinforced Cement concrete 1:1.5:3 using 20mm ISS HBG metal for all RCC item of works excluding cost of Rein forcement and fabricating charges, centering and shuttering but including curing and shall be finished smooth with cement mortar 1:3, 12mm thick. and with kraft paper without claiming extra as directed by the departmental officers complete complying with standard specifications.
74Supplying and Fabricating and placing in position MS steel or Ribbed Tor Steel for all Reinforced Cement Concrete works as per the design given including cost of steel and binding wire in all floors etc, Complete complying with stanard specification.(MS rod or RTS bar will be supplied departmentally at section stores and cost will be recoverd at issue rate). the binding wire shall supplied by the contactor.
75Providing and fixing Tar Paper for bearing Between Bed Block & Deck slab
76Providing weepholes in brick masonry/stone masonry, plain/reinforced concrete abutment, wing wall, return wall with 100 mm dia AC pipe extending through the full width of the structures with slope of 1(V):20(H) towards drawing face complete as per drawing
77Gravel filling between body wall including cost and conveyance of gravel, labour for filling, watering and compacting etc complete complying with standard specification and as directed by the departmental officer.
78Supplying and erecting centering shuttering including necessary supports for plane surface in foundation and basement and in all floors for R C C column footing column plinth beam, beams, roof slabs, staircase steps, bed blocks, critical pier etc using mild steel sheets of size 90 x 60 cm and 10 guage stiffened, welded with mild steel angles of size 25mmx25mmx3mm for boarding laid over silver oak (country wood) scantlings of size 10cm x 6.5cm spaced of about 90cm centre to centre and supported by casurina props of 10cm to 13cm dia spaced at 75cm centre to centre complete complying with standard specifications and as directed by departmental officers including conveyance of all materials to site and proper centering etc complete.
79BELOW GL
80Above GL
81Provision for Hectometer stone
82Provision for Kilometer stone
83Provision for Citizen Information Board
84Calculation of SubTotal, GST and Total carried out by system automatically
85Sub Total Amount for above all items
86GST 18% for the above SubTotal Amount Please Enable Macros to View BoQ information
87GST 18% for the above SubTotal Amount Please Enable Macros to View BoQ information

AI Tender Summary

OUR REF NO 57987951
AUTHORITY Government Departments
TENDER VALUE 2.07 Crore
LAST DATE 11-11-2026
Authority
Authority Name Forest Department
Work Description Tender for Maintenance Of Existing Road From Kovilmarathur To G.Marathur Road In Jamunamarathur Range Of Thiruvannamalai Forest Division During 2026-27
Basic Detail
Tender No 203/2026/D
Bidding Type Tender
Location
City Tiruvannamalai
State Tamil Nadu
Key Dates
Publish Date 12 Oct 2026
Submission Date 11 Nov 2026
Open Date 12 Nov 2026
Finance
Tender Value 2.07 Crore
Tender Fee Ref. Documents
EMD 2.08 Lakhs
Exemption Available
Document List
464c093f-5311-403a-b440-769707b7d19f.html
BOQ_856363.xls
Kovilmarathur1.pdf
Tendernotice_1.pdf

Unlock Full AI Tender Summary

Get instant access to the complete AI-generated analysis — scope, eligibility, timeline & more.

Instant Access Secure Free
Your details are secure and used only for document delivery.

Tender Timeline

Oct 12, 2026
11:30 IST

Tender Published

Tender notice published.

Completed
Nov 11, 2026
17:00 IST

Bid Submission Deadline

Online submission via eProcurement portal.

Upcoming · 13 days
Nov 12, 2026

Bid Opening Date

Technical bids will be opened and evaluated.

Upcoming · 14 days

Tender Documents

Download All (ZIP) ↓
html

464c093f-5311-403a-b440-769707b7d19f.html

xls

BOQ_856363.xls

pdf

Kovilmarathur1.pdf

pdf

Tendernotice_1.pdf

Disclaimer

We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender