Tender For Construction Of Compund Wall On Park & Play Field Plot In Ward 6B & Cleaning Work At Adisor Pond In Ward 2-A At Adipur.
Tender Overview
Project Description
Tender For Construction Of Compund Wall On Park & Play Field Plot In Ward 6B & Cleaning Work At Adisor Pond In Ward 2-A At Adipur.
Corrigendum
| Sr No | Corrigendum Date | Corrigendum | Type | New Submission Date |
|---|---|---|---|---|
| 1 | 22-Oct-2026 | Corrigendum 1 for Correction Tender Documents | Technical Bid | 28-Oct-2026 |
BOQ
| Sl. No. | Item Description |
| 1 | Part \\"A\\" Civil work |
| 2 | JUNGLE CUTTING |
| 3 | Cleaning jungle including uprooting of rank vegetation, grass, brush wood, trees and saplings of girth up to 30 cm. measured at a height of 1 mt. above ground level and removal of rubbish up to a distance of 50 mt, outside the periphery of the area cleared. |
| 4 | EARTH WORK |
| 5 | Earth work in excavation in all kinds of soil & murrum lift upto 1.5 mt. including dressing & ramming of bottom to the required level & plumbing the sides as per dimensions including getting out and stacking the excavated soil & disposal of the surplus excavated soil within the lead of 50 mt. dewatering of rain water or sub soil water if any complete as directed. |
| 6 | Filling of earth obtained from the excavated stuff by laying in layers not exceeding 20 cm. loose thickness wherever required in trenches, plinth, sides of foundation etc. including consolidation of each layer by ramming,watering etc. complete and removal of the surplus earth within a lead of 50 mt, or as directed. |
| 7 | PLAIN CEMENT CONCRETE |
| 8 | Providing & laying cement concrete with mix 1:3:6 (1 cement, 3 coarse screened sand, 6 graded trap stone aggregate 25 to 40 mm. nominal size) Volume batching with boxes of steel/wood0including mixing, placing, compacting, levelling, cuing necessary steel/plywood form work shuttering, scafolding etc. complete as directed. |
| 9 | Reniforced cement concrete :- |
| 10 | Providing & laying design mix reinforced cement controlled concrete of M-20 grade consisting of ingredients of cement, coarse screened sand, crushed graded trap stone metal, etc. Volume batching with boxes of steel/wood including shuttering, mixing in mixer, placing, vibrating, levelling, curing etc. complete as directed. (Cost is exclusive of reinforcement & form work.)(a) Beams and Cantilevers. |
| 11 | Providing & laying design mix reinforced cement controlled concrete of M-20 grade consisting of ingredients of cement, coarse screened sand, crushed graded trap stone metal, etc. Volume batching with boxes of steel/wood including shuttering, mixing in mixer, placing, vibrating, levelling, curing etc. complete as directed. (Cost is exclusive of reinforcement & form work.)(b) Column. |
| 12 | Providing & laying design mix reinforced cement controlled concrete of M-20 grade consisting of ingredients of cement, coarse screened sand, crushed graded trap stone metal, etc. Volume batching with boxes of steel/wood including shuttering, mixing in mixer, placing, vibrating, levelling, curing etc. complete as directed. (Cost is exclusive of reinforcement & form work.)( c )coping. |
| 13 | FORMWORK |
| 14 | Providing formwork of ordinary timber planking so as to give a rough finish including centering shuttering strutting and propping etc. height of propping and centering below supporting floor to ceiling not exceeding 4 Mt. and removal of the same for in situ reinforced concrete and plain concrete work. ( Rates are for all heights & levels.(a) Beam |
| 15 | Providing formwork of ordinary timber planking so as to give a rough finish including centering shuttering strutting and propping etc. height of propping and centering below supporting floor to ceiling not exceeding 4 Mt. and removal of the same for in situ reinforced concrete and plain concrete work. ( Rates are for all heights & levels.(b) Coloumn |
| 16 | Providing formwork of ordinary timber planking so as to give a rough finish including centering shuttering strutting and propping etc. height of propping and centering below supporting floor to ceiling not exceeding 4 Mt. and removal of the same for in situ reinforced concrete and plain concrete work. ( Rates are for all heights & levels.( c )Coping |
| 17 | MASONRY WORK |
| 18 | Providing & laying uncoarsed rubble masonry with hard black stone of approved quality in foundation and plinth in cement mortar 1:4 (1 cement : 4 coarse sand) including levelling, placing through stones at 2 nos per sq. mt. curing etc. complete with all labour, material and as directed by Engineer in charge. |
| 19 | Providing & laying 20 cm.thick block masonary in 15 cm. layers with 40 cm.long,20 cm.wide,15cm. high c.c.solid blocks having V-notch grooves as approved, machine made with an average mix of 1:6:2:6 ( 1 cement:6 screened coarse sand:2 stone grit:6 graded stone aggregate of 20 mm. nominal size). laid in cement mortar 1:4 ( 1cement: 4 screened coarse sand) including simultaneously raking of joints on both faces, scaffolding, curing etc complete as directed.( i ) In superstructure |
| 20 | PLASTER WORK |
| 21 | Plastering single coat 15mm.thick with cement mortor (1:4) (1 cement : 4 screened sand) on brick / concrete walls for interior / exterior plaster including raking out joints, hacking all R.C.C. surfaces scrubbing and cleaning, finishing smooth curing etc. complete as directed for work on all heights & levels. |
| 22 | Plastering two coat 20mm.thick (12 mm.+8 mm thick) with cement mortor (1:4) (1 cement : 4 screened sand) on brick / concrete walls for exterior plaster including raking out joints, hacking all R.C.C. surfaces scrubbing and cleaning, finishing smooth curing etc. complete as directed for work on all heights & levels. |
| 23 | Reinforcement & fabrication:- |
| 24 | Providing & laying reinforcement for reinforced cement concrete works of National, Gallant,Welspun or equivalent approved brand including cutting, bending, tying with binding wires,preparing cages and placing in position etc. complete as directed.Ribbed tor steel reinforcement. (TMT/FE 500). |
| 25 | Providing & fixing M.S. ornamental grills as per requirement & approved design for gates / Railing etc. fabricated from M.S.bars, G.I.pipes, M.S.sheets,flat,angles etc. including cutting, bending, welding necessary fittings and locking arragements etc.and fixing with hold fasts of required size in inner faces of opening including one priming coat of red oxide with all labour & material complete as directed for works on all heights & levels. |
| 26 | Painting work. |
| 27 | Applying primer coat over new steel and other metal surfaces/ grills/ gates etc after and including preparing the surface by thoroughly cleaning oil, grease, dirt and other foreign mater and scoured with wire brushes fine steel wool, scrappers and sand paper with ready mixed priming paint, brushing oxide zinc chrome of Asian/ Nerolac/ Berger/ ICI make complete as directed . |
| 28 | Painting two coats (excluding priming coat) on new steel and other metal surfaces/ grills/ gates with synthetic enamel paint brushing exterior type I to give an even shade including cleaning the surfaces of all dirt, dust, and other foreign mater with paint of 1st./ Premium quality of Asian/ Nerolac/ Berger/ ICI make complete as directed . |
| 29 | Total of part \\"A\\" |
| 30 | CLEANING OF ADISOR POND PART - II |
| 31 | (1) The work comprises dewatering, cleaning, disposal of garbage material, repair, and restoration of Adisor Pond by deploying suitable machinery, equipment, manpower, and all allied arrangements required for successful completion of the work.(2) The contractor shall dewater the pond using suitable mechanical pumps and discharge their water through pipes, hose reels, or any other approved arrangement into the nearby nallah or designated disposal point. Adequate precautions shall be taken to ensure that the discharged water does not cause inconvenience, flooding, damage or nuisance to adjoining areas or the public.(3) Dewatering shall be carried out in a phased and controlled manner to faciliate the safe shifting of fish and other aquatic species to suitable locations without causing harm to the ecosystem.The shifting is to be done by the contractor & necessary permission from concern authorities to be taken by him. |
| 32 | (4) After complete dewatering, , the contractor shall remove all accumulated mud, silt, dirt, vegetation, bushes, trees, plastic waste, garbage, debris, and other unwanted materials from the pond using suitable machinery such as JCBs, hydraulic excavators, dumpers, tractor-trolleys, and other required equipment.(5) The contractor shall prepare temporary earthen ramps/slopes wherever required to facilitate safe movement of machinery from the ground level into the pond and vice versa. Adequate safety measures shall be adopted during excavation and operation of machinery to ensure the safety of workmen, equipment, and the general public.(6) The contractor shall deploy adequate numbers of skilled and unskilled labourers, supervisors, machine operators, and all other personnel required for timely and satisfactory completion of the work. |
| 33 | (7) The contractor shall transport and dispose off all excavated mud, silt, debris, garbage, and other waste materials at the designated dumping yard of Gandhidham Municipal Corporation (GDMC). No material shall be dumped at any unauthorized location.(8) During execution of the work, the contractor shall maintain cleanliness of the surrounding area and comply with all environmental protection measures, labour laws, safety regulations, and instructions issued by the Corporation and other statutory authorities.(9) Upon completion of cleaning operations, the contractor shall dismantle the temporary earthen ramps/slopes created for machinery movement and transport the excavated earth to the designated GDMC dumping yard. The pond and surrounding area shall be restored to their original condition. |
| 34 | (10) After completion of cleaning, all necessary repair works to the pond, including repairs to the bottom slab and side slopes, crack filling, concrete repairs, patchwork, and any other incidental civil works required to make the pond watertight and serviceable, shall be carried out. All concrete repair works shall be properly cured for a minimum period of seven (7) days.(11) On completion of the entire work, the pond shall be handed over to the Corporation in a clean, safe, orderly, and fully usable condition.(12) The rates quoted by the contractor shall be deemed to include the cost of all labour, machinery, pumps, fuel, transportation, lifting equipment, safety devices, barricading, consumables, temporary works, disposal charges, curing, supervision, taxes, and all incidental expenses necessary for satisfactory completion of the work. |
| 35 | (13) Site Visit: Tenderers are advised to visit and thoroughly inspect the site before submitting their bids to fully understand the nature, extent, and working conditions of the project. No claim whatsoever on account of site conditions, foul smell, water quality, quantity of sludge, scope of work, accessibility, or any other unforeseen condition shall be entertained after submission of the tender or during execution of the work. |
| 36 | CLEANING OF ADISOR POND PART - II Please Enable Macros to View BoQ information |
AI Tender Summary
Tender Timeline
Tender Published
Tender notice published.
CompletedCorrigendum-1 Issued
Clarifications on tender conditions and amendments issued.
Upcoming · 1 dayBid Submission Deadline
Online submission via eProcurement portal.
Upcoming · 1 dayTender Documents
Download All (ZIP) ↓We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender