Tender For Development Of A 1.0 Mld Water Treatment Plant On The Deval Talao And C Us Dug Well Source And Associated Infrastructure At Seepz-Sez, Mumbai
Tender Value
Ref. Documents
Estimated cost
Bid Submission
28 Oct 2026
10 days left
EMD
20 Lakhs
Bank guarantee accepted
Document Fee
Ref. Documents
Non-refundable
Tender Type
Online
Tender Overview
Organization
Tender ID
Competition Type
NCB
Bidding Type
Tender
Location / State
Mumbai Suburban → Maharashtra
EMD Exemption
Not Available
Quantity
Not Available
Website
Contact Person
Address
Project Description
Tender for Development Of A 1.0 Mld Water Treatment Plant On The Deval Talao And C Us Dug Well Source And Associated Infrastructure At Seepz-Sez, Mumbai
BOQ
| Sl. No. | Item Description |
| 1 | SECTION 1 — DEVAL TALAO INTAKE & RAW WATER LIFTING [RFP Vol III Section No. 1.2(A)] |
| 2 | Lake intake structure |
| 3 | Coarse bar screen |
| 4 | Mechanically cleaned fine screen |
| 5 | Raw water sump |
| 6 | Raw water pumps, VFD |
| 7 | VFD + local starter panel |
| 8 | Hard-wired low-level cut-off |
| 9 | Abstraction flow meter |
| 10 | Walkway, handrail, fall-arrest |
| 11 | Davit crane |
| 12 | Intake piping & valves |
| 13 | Power & control cabling to intake |
| 14 | Intake lighting & small power |
| 15 | SECTION 2 — DUG WELL REHABILITATION [RFP Vol III Section No. 1.2(B)] |
| 16 | Dewatering of standing water |
| 17 | Desilting & muck removal |
| 18 | Lining inspection & repair |
| 19 | Plugging of contamination points |
| 20 | Plinth & apron |
| 21 | Jet cleaning of strata |
| 22 | Permanent cover & lockable access |
| 23 | Surrounding drainage repair |
| 24 | Safety provisions |
| 25 | SECTION 3 — PRODUCTION WELL DEVELOPMENT [RFP Vol III Section No. 1.2(C)] |
| 26 | Hydrogeological assessment |
| 27 | Constant-rate pumping tests |
| 28 | Piezometers |
| 29 | Submersible pumps |
| 30 | Pump lowering & installation |
| 31 | Pump commissioning & trial |
| 32 | Wellhead works |
| 33 | Well flow meters |
| 34 | SECTION 4 — RAW WATER TRANSMISSION [RFP Vol III Section No. 1.2(D)] |
| 35 | Rising main — Lake to WTP |
| 36 | Rising main — well to WTP |
| 37 | Isolation, NRV & air valves |
| 38 | Washouts & drain points |
| 39 | Valve chambers |
| 40 | SECTION 5 — WATER TREATMENT PLANT, 1.0 MLD [RFP Vol III Section No. 1.2(E), Section No. 5] (reference process — see Basis flag) |
| 41 | Raw water blending sump at WTP |
| 42 | Cascade aerator + pre-oxidation |
| 43 | Flash mixer, flocculator & lamella clarifier |
| 44 | Dual-media pressure filters |
| 45 | Ultrafiltration system |
| 46 | UF backwash & CIP system |
| 47 | RO stage (partial stream) |
| 48 | Blending, remineralisation & pH correction |
| 49 | Disinfection system |
| 50 | Chemical storage & dosing skids |
| 51 | PAC dosing provision |
| 52 | Interconnecting piping & valves |
| 53 | Plant MCC, VFDs & power cabling |
| 54 | Instrument air & service water |
| 55 | Erection, installation & painting |
| 56 | Commissioning + 2-yr mandatory spares |
| 57 | Trial-run consumables & chemicals |
| 58 | SECTION 6 — TREATED WATER STORAGE [RFP Vol III Section No. 1.2(F), Section No. 9.1] |
| 59 | RCC treated water reservoir |
| 60 | Food-grade internal lining |
| 61 | Vents, covers, ladders |
| 62 | Level instrumentation |
| 63 | Sampling taps & pipework |
| 64 | SECTION 7 — TREATED WATER PUMPING & TRANSMISSION [RFP Vol III Section No. 1.2(G), Section No. 9.2] |
| 65 | Treated water transfer pumps, VFD |
| 66 | Surge protection (transfer main) |
| 67 | Residual chlorine boosting |
| 68 | Transmission main to Delivery Point |
| 69 | Line valves & specials |
| 70 | SECTION 8 — DELIVERY POINT (PAYMENT METERING) WORKS [RFP Vol III Section No. 1.2(H), Section No. 9.3] |
| 71 | Bulk meter chamber |
| 72 | Payment bulk flow meter |
| 73 | Isolation & non-return valves |
| 74 | Pressure transmitter |
| 75 | Online turbidity analyser |
| 76 | Online residual chlorine analyser |
| 77 | Sampling tap & appurtenances |
| 78 | SECTION 9 — REJECT, BACKWASH & RESIDUALS [RFP Vol III Section No. 1.2(J), Section No. 6] |
| 79 | Backwash settling / recovery tank |
| 80 | Supernatant return pumps |
| 81 | Sludge holding & dewatering |
| 82 | RO reject conditioning & disposal line |
| 83 | Reject stream flow meter |
| 84 | SECTION 10 — ON-SITE LABORATORY [RFP Vol III Section No. 1.2(K), Section No. 8.3] |
| 85 | Bench turbidimeter |
| 86 | pH / EC / TDS bench meters |
| 87 | UV-Vis spectrophotometer |
| 88 | Jar test apparatus |
| 89 | Analytical balance |
| 90 | Incubator + membrane filtration set |
| 91 | Hot air oven, fridge, hotplate |
| 92 | Glassware & reagents — initial |
| 93 | Lab furniture, sink, fume provision |
| 94 | Samplers, coolboxes, custody kit |
| 95 | SECTION 11 — INSTRUMENTATION, CONTROL & SCADA [RFP Vol III Section No. 1.2(L), Section No. 8.2] |
| 96 | Online turbidity analysers |
| 97 | Online pH analysers |
| 98 | Online conductivity analysers |
| 99 | Online residual chlorine — outlet |
| 100 | Stage DP / head-loss transmitters |
| 101 | Pressure transmitters — misc |
| 102 | Redundant PLC system |
| 103 | SCADA + historian |
| 104 | HMI / engineering station |
| 105 | UPS for controls & telemetry |
| 106 | Campus command-centre integration |
| 107 | Instrument cabling, JBs, trays |
| 108 | FAT / SAT & loop commissioning |
| 109 | SECTION 12 — SOLAR PV [RFP Vol III Section No. 1.2(M)] |
| 110 | Solar PV plant |
| 111 | Net metering & protections |
| 112 | Earthing & lightning protection |
| 113 | SECTION 13 — BUILDINGS & SITE WORKS [RFP Vol III Section No. 1.2(N)] |
| 114 | Process/plant building & control room |
| 115 | Chemical store with bund |
| 116 | Internal roads & hardstanding |
| 117 | Boundary treatment & gate |
| 118 | Area lighting |
| 119 | Fire safety provision |
| 120 | CCTV & access control |
| 121 | Lightning protection — plant building |
| 122 | Site drainage |
| 123 | Water supply & sanitation |
| 124 | Landscaping & restoration |
| 125 | SECTION 14 — SECTOR-1 BOOSTER STATION [RFP Vol III Section No. 1.2(Q), Section No. 9.4.1] |
| 126 | Booster pump sets, VFD |
| 127 | Hydropneumatic vessel + compressor |
| 128 | Delivery header & valves |
| 129 | Surge protection device |
| 130 | Booster kiosk / canopy — civil |
| 131 | Booster MCC / VFD panel |
| 132 | Misc piping, supports, ID |
| 133 | SECTION 15 — MCGM STANDING-BACKUP CHANGEOVER FACILITY [RFP Vol III Section No. 1.2(R), Section No. 9.4.2] |
| 134 | Motorised changeover valve |
| 135 | Double non-return protection |
| 136 | Isolation valves |
| 137 | Bulk meters — both feeds |
| 138 | Actuator control, logic, battery |
| 139 | Changeover chamber — civil |
| 140 | SECTION 16 — DEDICATED DELIVERY MAINS, GSR & CORRIDOR WORKS [RFP Vol III Section No. 1.2(S),(T), Section No. 9.4.3–9.4.5] |
| 141 | Utility detection survey |
| 142 | Trial pits for utility confirmation |
| 143 | Delivery main DN150 |
| 144 | Delivery main DN100 |
| 145 | Polyethylene sleeving for DI mains |
| 146 | Trench shoring & dewatering |
| 147 | Valve chambers |
| 148 | Isolation valves at takeoffs & line |
| 149 | CC road cutting & reinstatement |
| 150 | Bituminous road reinstatement |
| 151 | Paver-block / footpath reinstatement |
| 152 | Utility shifting & protection |
| 153 | GSR connections |
| 154 | GSR level instrumentation + RTU |
| 155 | Telemetry head-end & integration |
| 156 | Marker tape & potable ID |
| 157 | Hydrostatic testing & bact. clearance |
| 158 | SECTION 17 — DELIVERY-SYSTEM ELECTRICAL WORKS [RFP Vol III Section No. 1.2(U)] |
| 159 | Power feed to booster station |
| 160 | Changeover facility supply + UPS |
| 161 | Earthing pits & grid |
| 162 | Automation control cable |
| 163 | MCB distribution boards |
| 164 | Cable laying, glanding, termination |
| 165 | Road-crossing conduits |
| 166 | SECTION 18 — RAW WATER CHARACTERISATION PROGRAMME & PILOT [RFP Vol III Section No. 4] |
| 167 | Phase 1 weekly sampling & analysis |
| 168 | Pesticide suite (T5) |
| 169 | Radioactivity (gross α/β) |
| 170 | Cryptosporidium & Giardia |
| 171 | Phase 3 monthly sampling |
| 172 | Pilot plant — mob, operate 30 d, demob |
| 173 | Pilot analytical programme |
| 174 | Hydrogeology consultant & reporting |
| 175 | Seasonal observation instruments |
| 176 | RWC / Pilot / Process Selection Reports |
| 177 | SECTION 19 — ENGINEERING, APPROVALS & GENERAL [Concessionaire scope] |
| 178 | Topographic survey & geotechnical |
| 179 | Process & detailed engineering |
| 180 | Surge analysis |
| 181 | Approvals & liaison |
| 182 | Third-party inspection |
| 183 | Construction QA/QC & site management |
| 184 | As-builts, O&M manuals, training |
| 185 | Construction insurances |
| 186 | BG commissions — construction period |
| 187 | SECTION 20 — GENERAL CONSTRUCTION ITEMS [s] |
| 188 | Site establishment & mobilisation / demob |
| 189 | Barricading, traffic & pedestrian management |
| 190 | Construction-phase ESHS implementation |
| 191 | Construction power & water arrangements |
| 192 | O&M-1 — MANPOWER (2-operator roster + unattended night window per Section No.5.2(i); matched-estimate assumption) |
| 193 | Plant-in-charge cum chemist |
| 194 | Shift operators |
| 195 | E&M technician |
| 196 | Helpers / attendants |
| 197 | Statutory add-on (EPF/ESIC/bonus) |
| 198 | O&M-2 — CHEMICALS (dose × volume formulas; doses are RWCP-dependent levers on 1_Basis) |
| 199 | Poly-aluminium chloride (PACl) |
| 200 | Polyelectrolyte |
| 201 | Sodium hypochlorite (12%) |
| 202 | Powdered activated carbon |
| 203 | RO antiscalant |
| 204 | CIP chemicals (UF+RO) |
| 205 | Remineralisation media top-up |
| 206 | O&M-3 — MEMBRANE & MEDIA REPLACEMENT PROVISION (sinking basis) |
| 207 | UF membrane elements |
| 208 | RO membrane elements |
| 209 | Filter media & cartridges |
| 210 | O&M-4 — WATER QUALITY TESTING & MONITORING (contractual minimum per RFP Vol III Section No.8, Table 8.1; annual-contract NABL rates) |
| 211 | Weekly bacteriological — NABL |
| 212 | Monthly full suite (T1–3 + extras) — NABL |
| 213 | Quarterly toxic suite (T4 + THM/HAA) — NABL |
| 214 | Half-yearly pesticides (T5) — NABL |
| 215 | Annual complete suite incl. T6, Crypto/Giardia |
| 216 | Monthly raw water characterisation (Phase 4) |
| 217 | Quarterly consumer-tap survey |
| 218 | Analyser calibration standards & site consumables |
| 219 | Annual bulk-meter calibration — accredited |
| 220 | Reservoir annual clean & clearance |
| 221 | O&M-5 — MAINTENANCE, SPARES & AMCs |
| 222 | M&E spares and repairs |
| 223 | Online analyser AMC |
| 224 | SCADA/IT, comms & telemetry fees |
| 225 | Civil upkeep & painting provision |
| 226 | Residuals transport & disposal |
| 227 | O&M-6 — INSURANCE, STATUTORY & ADMINISTRATION |
| 228 | O&M insurances |
| 229 | Consent renewals & statutory returns |
| 230 | PPE, safety consumables, medicals |
| 231 | Office, reporting & documentation |
| 232 | O&M Security BG commission Please Enable Macros to View BoQ information |
AI Tender Summary
Tender Timeline
Oct 07, 2026
11:30 IST
Tender Published
Tender notice published.
CompletedOct 28, 2026
17:00 IST
Bid Submission Deadline
Online submission via eProcurement portal.
Upcoming · 10 daysOct 29, 2026
Bid Opening Date
Technical bids will be opened and evaluated.